Demers Nursing Home, Inc. v. R.C. Foss & Son, Inc.

Citation449 A.2d 1231,122 N.H. 757
Decision Date17 August 1982
Docket NumberNo. 82-021,82-021
PartiesDEMERS NURSING HOME, INC. v. R.C. FOSS & SON, INC.
CourtSupreme Court of New Hampshire

Emile R. Bussiere P.A., Manchester (James M. Warren, Manchester, on the brief and orally), for plaintiff.

Orr & Reno P.A., Concord (John A. Malmberg, Concord, on the brief and orally), for defendant.

BOIS, Justice.

The plaintiff, Demers Nursing Home, Inc., brought an action at law claiming failure on the part of the defendant, R.C. Foss & Son, Inc., to perform according to the terms of their construction contract. The defendant filed a motion to dismiss, alleging that the contract compelled the parties to submit the claim to arbitration. The Trial Court (Flynn, J.) granted the motion, and the plaintiff appealed to this court. We affirm.

In 1978, the parties entered into an agreement entitled "Standard Form of Design-Build Agreement Between Owner and Contractor," prepared by the Associated General Contractors of America. According to the terms of the contract, the defendant was to construct a nursing home. Article 16 of the contract provided for the submission to arbitration of all claims arising out of or relating to the contract.

The construction work was substantially completed and the nursing home was occupied in March 1979. Shortly thereafter, defects in the construction were discovered which required corrective work by the defendant company. Severe problems developed with the heating system, and finally on January 19, 1981, the plaintiff requested that the defendant take the necessary steps to repair the defects.

The defendant responded to the plaintiff's request by a letter dated January 26, 1981. Although this letter is not technically part of the record, we will consider its contents because the plaintiff included a copy of the letter in its notice of appeal, and because both parties referred to the letter in their briefs. The defendant stated in the letter that it had fully complied with its contractual obligations and that the warranty period had expired. The letter further contained a request by the defendant that it be allowed to send a representative to observe the plaintiff's alleged problems "in anticipation of the arbitration ... which I [the defendant] presume[s] you [the plaintiff] will undertake...." Following receipt of the letter, the plaintiff hired other contractors to perform the corrective work and notified the defendant of this development. The defendant did not send a representative to observe the work that was being done.

The plaintiff brought suit in superior court in July 1981. The defendant filed a motion to dismiss on August 31, 1981, and a hearing thereon was held by the court on November 23, 1981. A formal demand for arbitration was filed by the defendant with the American Arbitration Association on December 8, 1981. The court granted the motion to dismiss on December 10, 1981.

On this appeal, the plaintiff argues that arbitration statutes presuppose the existence of a valid and enforceable contract at the time arbitration is sought. Accordingly, the plaintiff contends that arbitration is precluded in this case because the instant contract had allegedly expired at the time the defendant filed its request for arbitration.

We have recognized that the right to arbitration does not generally survive the expiration of the contract creating that right. Babcock v. Sol Corp., 118 N.H. 340, 342, 386 A.2d 1259, 1261 (1978). However, a contractual provision creating a right to arbitration remains subject to the traditional principles of contract law, and its interpretation and construction is therefore a question of law for the court. See Dunn & Sons, Inc. v. Paragon Homes of New Eng., Inc., 110 N.H. 215, 217, 265 A.2d 5, 7 (1970); see also Murphy v. Doll-Mar, Inc., 120 N.H. 610, 611, 419 A.2d 1106, 1108 (1980). We have held that under certain circumstances the right to compel arbitration does in fact survive the termination of the contract that created the right. See, e.g., Babcock v. Sol Corp., 118 N.H. at 342-43, 386 A.2d at 1261; Tothill v. Richey Ins. Agency, Inc., 117 N.H. 449, 453, 374 A.2d 656, 658 (1977). In these circumstances, "[t]he court's inquiry should focus on the intent of the parties in agreeing to the arbitration clause." Babcock v. Sol Corp., 118 N.H. at 342, 386 A.2d at 1261.

Because no testimony was presented at the hearing on the motion to dismiss, we must examine the language of article 16 of the contract to determine the intent of the parties in agreeing to the arbitration clause. See Dunn & Sons, Inc. v. Paragon Homes of New Eng., Inc., 110 N.H. at 217, 265 A.2d at 7. Article 16 provides in pertinent part as follows:

"16.1 All claims, disputes and other matters ... arising out of, or relating to, this Agreement or the breach thereof, except with respect to the Architect/Engineer's decision on matters relating to artistic effect, and except for claims which have been waived by the making or acceptance of Final Payment shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association ....

16.2 Notice of the demand for arbitration shall be filed ... within a reasonable time ... and in no event shall it be made after the date when institution of legal or equitable proceedings based on such claim ... would be barred by the applicable statute of limitations."

(Emphasis added.)

In light of the language requiring arbitration for all matters "relating to ... the breach" of the contract, we hold that Article 16 reveals the parties' intention to have the right to arbitration survive the...

To continue reading

Request your trial
16 cases
  • Village of Cairo v. Bodine Contracting Co.
    • United States
    • Missouri Court of Appeals
    • January 29, 1985
    ...Incorporated v. Local 50, etc., 370 U.S. 254, 256, 82 S.Ct. 1346, 1348, 8 L.Ed.2d 474 (1962); Demers Nursing Home v. R.C. Foss & Son, Inc., 122 N.H. 757, 449 A.2d 1231, 1232[1, 2] (1982). On these principles, "a party cannot be required to submit to arbitration any dispute which he has not ......
  • Gold Coast Mall, Inc. v. Larmar Corp.
    • United States
    • Maryland Court of Appeals
    • December 8, 1983
    ...848, 857 (N.D.1966); Mamlin v. Susan Thomas, Inc., 490 S.W.2d 634, 639 (Tex.Civ.App.1973). Cf. Demers Nursing Home, Inc. v. R.C. Foss & Son, Inc., 122 N.H. 757, 761, 449 A.2d 1231, 1233 (1982). 4 The rationale underlying these cases is that a party asserting a claim who sues instead of seek......
  • Donaldson, Lufkin & Jenrette Futures, Inc. v. Barr
    • United States
    • Illinois Supreme Court
    • October 20, 1988
    ...Gibbons-Grable Co. v. Gilbane Building Co. (1986), 34 Ohio App.3d 170, 172, 517 N.E.2d 559, 561; Demers Nursing Home v. R.C. Foss & Sons (1982), 122 N.H. 757, 759-60, 449 A.2d 1231, 1232; Milwaukee Police Association v. City of Milwaukee (1983), 113 Wis.2d 192, 198, 335 N.W.2d 417, 420; Uni......
  • Rizzo v. Allstate Ins. Co., 2016–0592
    • United States
    • New Hampshire Supreme Court
    • May 1, 2018
    ...that arbitration provides parties with a "speedy and inexpensive resolution of a dispute," Demers Nursing Home, Inc. v. R. C. Foss & Son, Inc., 122 N.H. 757, 761, 449 A.2d 1231 (1982), while saving "scarce and valuable legal and judicial time and talent," Pittsfield Weaving Co., Inc. v. Gro......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT