Devco Development Corp. v. Hooker Homes, Inc., s. 86-3233

Decision Date04 December 1987
Docket Number87-640,Nos. 86-3233,s. 86-3233
Citation518 So.2d 922
Parties5 UCC Rep.Serv.2d 157 DEVCO DEVELOPMENT CORPORATION, Appellant, v. HOOKER HOMES, INC., and Nona Barnes, Inc., d/b/a Hooker Barnes Homes, Appellees.
CourtFlorida District Court of Appeals

Mark K. Straley and Frances Makemie Toole of Bush, Ross, Gardner, Warren & Rudy, Tampa, for appellant.

James M. Shuler and Charles L. Weissing of Kass, Hodges & Massari, Tampa, for appellees.

PER CURIAM.

Devco Development Corporation, the developer of a residential subdivision under a contract with appellees, hereinafter referred to as "Hooker Barnes," to sell developed lots to Hooker Barnes appeals from a final judgment determining that Devco was not entitled to liquidated damages by reason of the failure of Hooker Barnes to close purchases of the lots developed by Devco. We affirm.

There is no question raised as to Devco's satisfactory performance of the development work called for by the contract. The only issues are, first, whether Devco timely performed under the terms of the contract so that Hooker Barnes was in default on its obligation to purchase lots from Devco and, second, even if there was such timely performance, whether Devco properly exercised its contractual right to the liquidated damages it claims. The trial court decided against Devco on both issues.

As to the first issue, we disagree with the trial court's conclusion that appellant Devco breached the contract for development and sale. Briefly stated, (a) excessive rain, by the terms of the contract, would constitute "any other condition" beyond Devco's control which would excuse a delay in performance; (b) in the absence of any showing of fraud or bad faith, the Heidt certificate, which stated in pertinent part that Devco was entitled to an additional fifty days because of delays caused by rainfall, should have been accepted as settling the dispute between the parties, as provided by the contract; and (c) the technical deficiency of the certificate (i.e., the failure to list the beginning and ending dates of delay periods) did not render the certificate fatally defective, especially in the absence of any pretrial objection by Hooker Barnes to the form of the certificate. Accordingly, the final judgment is reversed insofar as it finds that Devco breached the contract.

At the heart of the second issue are the following contractual provisions: Paragraph 3.a. of the contract between Devco and Hooker Barnes provides that Hooker Barnes "will deposit with [Devco] ... an irrevocable bank letter of credit in the amount of $200,000. The Letter of Credit shall provide for payment to [Devco] upon presentation of a sight draft...." Paragraph 16 of that contract provides that "[i]n the event [Hooker Barnes] defaults with respect to its obligations under this Contract, the ... Letter of Credit held by [Devco] on this Contract may be taken and kept by [Devco] as full liquidated damages." An addendum to that contract provides "that Stewart Title Company will hold the Letter of Credit in the amount of $200,000.... It is also agreed that the Letter of Credit will contain a provision that [Devco] sign a certification that [Hooker Barnes] is in default in order to make any claim against said Letter of Credit." The letter of credit, issued by Mellon Bank addressed to Devco provided that "We hereby issue our Irrevocable Letter of Credit ... in your favor for the account of [Hooker Barnes] ... in the amount of US $200,000 available by your drafts at sight drawn on Mellon Bank ... accompanied by the following: 'Demand for payment and certification' per Exhibit 'A' as attached." The exhibit A attached to the letter of credit is entitled "Demand for Payment and Certification" and contains the statement, to be signed by Devco, that "We are entitled pursuant to that certain contract ... between Devco and [Hooker Barnes] to draw the sum of $200,000 under the aforesaid irrevocable letter of credit. Default has occurred under the contract ... and [Hooker Barnes] has not cured said default."

The court's conclusions concerning these contractual provisions were that (a) Devco gave up its right to recover on the letter of credit by failing to take the requisite steps to collect on the letter before the letter's expiration on April 4, 1985, and (b) the letter was Devco's sole liquidated damages remedy. We agree with the trial court.

As to (a), the contract and the letter of credit provided that Devco could be paid by Mellon upon presentation of two documents--a sight draft and a completed form of Demand for Payment and Certification. Devco provided neither of the required documents to Mellon.

Devco argues that it was not entitled to payment under the letter of credit without having possession of the letter itself and that Hooker Barnes, by protesting to Stewart Title Devco's request to Stewart that the letter be delivered to Devco, thus leading to an interpleader suit filed by Stewart Title, prevented Devco from getting the letter and thereby from getting payment of the $200,000 before the letter expired. However, nothing in either the contract or the letter required that Devco present the letter in...

To continue reading

Request your trial
9 cases
  • State v. Peters
    • United States
    • Florida District Court of Appeals
    • November 15, 1988
    ...414 F.2d 1014 (3d Cir.1969); Ratner v. Miami Beach First National Bank, 362 So.2d 273, 274 (Fla.1978); Devco Development Corp. v. Hooker Homes, Inc., 518 So.2d 922, 923 (Fla. 2d DCA 1987), review denied, 525 So.2d 877 (Fla.1988); McCoy v. Hoffmeister, 435 So.2d 989 (Fla. 5th DCA 1983); Stat......
  • Newcastle Properties, Inc. v. Shalowitz
    • United States
    • United States Appellate Court of Illinois
    • September 26, 1991
    ...Walgreen Co. v. American National Bank & Trust Co. of Chicago (1972), 4 Ill.App.3d 549, 281 N.E.2d 462, Devco Development Corp. v. Hooker Homes, Inc. (Fla.App.1987), 518 So.2d 922, Makris v. Williams (Fla.App.1983), 426 So.2d 1186, Stewart v. Mehrlust (Fla.App.1982), 409 So.2d 1085, Giammat......
  • Stein v. Paradigm Mirasol, LLC, No. 08-10983.
    • United States
    • U.S. Court of Appeals — Eleventh Circuit
    • September 30, 2009
    ...company's heart attack was held to be beyond the control of the company for force majeure purposes. See Devco Dev. Corp. v. Hooker Homes, Inc., 518 So.2d 922, 923 (Fla. 2d DCA 1987) (excessive rain); Camacho Enters., Inc. v. Better Constr., Inc., 343 So.2d 1296, 1297 (Fla. 3d DCA 1977) (hea......
  • Lacy v. Ticor Title Ins. Co.
    • United States
    • Texas Court of Appeals
    • June 15, 1990
    ...satisfied its obligation to pay the $200,000 to Lacy in the event of a breach of the contract. In Devco Development Corp. v. Hooker Homes, Inc., 518 So.2d 922 (Fla.Dist.Ct.App.1987), rev. denied, 525 So.2d 877 (Fla.1988), a $200,000 standby letter of credit was to provide liquidated damages......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT