Dillard Smith Const. Co. v. Greene, AA--173

Decision Date01 October 1976
Docket NumberNo. AA--173,AA--173
Citation337 So.2d 841
PartiesDILLARD SMITH CONSTRUCTION CO., a corporation, Appellant, v. C. Ray GREENE, Jr., Appellee.
CourtFlorida District Court of Appeals

Edward S. Parrish, Jr., of Fischette, Parrish, Owen & Held, Jacksonville, for appellant.

Charles Cook Howell, III, and Henry H. Graham, Jr., of Howell, Kirby, Montgomery, D'Aiuto & Dean, Jacksonville, for appellee.

SMITH, Judge.

The trial court held that appellant's second amended complaint fails to state a cause of action and dismissed appellant's malpractice claim against its former attorney.

Having a construction contract with the Jacksonville Electric Authority (JEA), appellant subcontracted the pile driving to another, who further subcontracted it to still another, who performed it. A claim for extra pile driving came back up the chain to appellant. When JEA had not paid for extra pile driving at the conclusion of the job, appellant became concerned whether it might apply for 'final payment' of the contract price and still preserve its claim against JEA for the cost of extra pile driving. The contract between JEA and appellant provided that '(t)he making and acceptance of final payment shall constitute . . . (a) waiver of all claims by the Contractor against the Owner other than those previously made in writing and still unsettled.' Appellant engaged appellee, a lawyer, for advice.

The second amended complaint alleges that appellee advised appellant to submit a final builling and execute the required release, so to receive the balance of the contract price, without making reference to the claim for extra pile driving. Acting on that advice, appellant obtained final payment from JEA which later interposed appellant's release and the quoted terms of the contract in bar of appellant's action against JEA for the sum found owing by appellant to the subcontractor and by it to the pile driver. After trial, judgment was rendered for appellant and against JEA. On JEA's appeal, appellant argued that its claim on account of extra pile driving had been properly preserved because 'the correspondence between the parties (appellant and JEA) evidenced a claim in writing which satisfied the terms and conditions of the contract. . . .' Jacksonville Elect. Auth. v. Dillard Smith Constr. Co., 299 So.2d 639, 640 (Fla.App.1st, 1974), cert. den. 304 So.2d 131 (Fla.1974). This Court, however, found that appellant had not preserved its claim against JEA to the extent of $21,875.

By the present action appellant alleges that appellee, its lawyer, negligently advised appellant in submitting appellant's claim on JEA for final payment. The allegations of negligence are (a) that the lawyer negligently failed to advise plaintiff that its acceptance of final payment would bar further claims against JEA, 'even though the simple reading of the contract and release recited same'; (b) that the lawyer negligently interpreted the 'plain wording' of the contract and release 'or negligently failed to read said contract and release before wrongfully advising Plaintiff to accept final payment and execute a release;' (c) that the lawyer negligently failed to advise appellant 'of the progression of the litigation and the options'; and (d) that the lawyer negligently failed to appeal the trial court's adjudication of appellant's liability to the subcontractor, and so let stand a judgment which was erroneous if JEA was not liable to appellant.

The trial court correctly held that specification (a) and the unitalicized portion of specification (b) of the complaint, summarized above, are insufficient. A lawyer does not guarantee the efficacy of his advice. His contractual interpretations, rendered in the exercise of judgment, in good faith and with the degree of knowledge and skill ordinarily possessed by other lawyers similarly situated, do not become actionable simply because a court later rules against his client. Appellant's lawyer espoused a substantial position, endorsed by the trial court's judgment in the JEA litigation, that the correspondence between appellant and JEA constituted a written claim within the meaning of the contract requirement. In these circumstances, it is not sufficient that appellant alleges by way of conclusion that his lawyer negligently misconstrued the contract's 'simple' meaning and 'plain wording.' Kartikes v. Demos, 214 So.2d 86 (Fla.App.3d, 1968). See Hodges v. Carter, 239 N.C. 517, 80 S.E.2d 144, 45 A.L.R.2d 1 (1954).

The trial court was correct also in holding insufficient the complaint's general allegations, in specification (c) above, concerning the lawyer's neglect to keep appellant informed. Without more, those allegations lack specificity as well as causative relation to appellant's loss. Similarly, the allegation of negligence in specification (d), that the lawyer failed to appeal the judgment rendered for the subcontractor against appellant, is without causative effect. There is no basis for contending the subcontractor's judgment would have been...

To continue reading

Request your trial
12 cases
  • Arky, Freed, Stearns, Watson, Greer, Weaver & Harris, P.A. v. Bowmar Instrument Corp.
    • United States
    • Florida District Court of Appeals
    • 8 Diciembre 1987
    ...types of automobile negligence actions." Accord Parker v. Gordon, 442 So.2d 273 (Fla. 4th DCA 1983); Dillard Smith Construction Co. v. Greene, 337 So.2d 841 (Fla. 1st DCA 1976). See also Kislak v. Kreedian, 95 So.2d 510 (Fla.1957) (conclusory allegations insufficient to state cause of actio......
  • Martinson Bros. v. Hjellum
    • United States
    • North Dakota Supreme Court
    • 3 Enero 1985
    ...132 A. 102, 103 (1926) ]. See also Kirsch v. Duryea, 21 Cal.3d 303, 146 Cal.Rptr. 218, 578 P.2d 935 (1978); Dillard Smith Const. Co. v. Greene, 337 So.2d 841 (Fla.Dist.Ct.App.1976). A successfully asserted claim of legal malpractice requires more than the fact, standing alone, that a trial ......
  • Keramati v. Schackow
    • United States
    • Florida District Court of Appeals
    • 14 Diciembre 1989
    ...528 (Fla. 3d DCA 1985).9 See Daytona Development Corp. v. McFarland, 505 So.2d 464 (Fla. 2d DCA 1987); Dillard Smith Construction Co. v. Greene, 337 So.2d 841 (Fla. 1st DCA 1976). ...
  • Bohn v. Johnson
    • United States
    • North Dakota Supreme Court
    • 23 Julio 1985
    ...132 A. 102, 103 (1926) ]. See also Kirsch v. Duryea, 21 Cal.3d 303, 146 Cal.Rptr. 218, 578 P.2d 935 (1978); Dillard Smith Const. Co. v. Greene, 337 So.2d 841 (Fla.Dist.Ct.App.1976). A successfully asserted claim of legal malpractice requires more than the fact, standing alone, that a trial ......
  • Request a trial to view additional results
1 books & journal articles
  • 1-2 Complaint
    • United States
    • Full Court Press Florida Legal Malpractice Law Title Chapter 1 Basics
    • Invalid date
    ...legal malpractice was so implausible that dismissal with prejudice was the only possible outcome."); Dillard Smith Constr. Co. v. Greene, 337 So. 2d 841 (Fla. 1st Dist. Ct. App. 1976) (client's allegation that attorney neglected to keep client informed, without more, lacked specificity as w......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT