Dishington v. A. W. Kuettel & Sons, Inc.

Decision Date15 May 1959
Docket NumberNo. 37539,37539
Citation96 N.W.2d 684,255 Minn. 325
PartiesEdward B. DISHINGTON, Appellant, v. A. W. KUETTEL & SONS, INC., Respondent.
CourtMinnesota Supreme Court

Syllabus by the Court

1. One who on behalf of the possessor of land erects a structure or creates any other condition thereon is subject to the same liability, and enjoys the same immunity from liability, As though he were the possessor of the land, for bodily harm caused to others within and without the land, While the work is in his charge, by the dangerous character of the structure or other condition.

2. Under the above rule Control of the work, and not an actual transfer of possession by contract, is decisive.

3. A possessor of land is subject to liability for bodily harm caused to gratuitous licensees by a natural or artificialcondition thereon if, but only if, he knows of the condition and realizes that it involves an unreasonable risk to them and has reason to believe that they will not discover the condition or realize the risk, and invites or permits them to enter or remain upon the land, without exercising reasonable care to make the condition reasonably safe, or to warn them of the condition and the risk involved therein.

4. The operation of the law of gravity is a matter of such common knowledge that all persons of ordinary intelligence and judgment, even if they are illiterate, are required to take notice of it.

5. There is no duty to warn against an obvious danger.

Lewis, Hammer, Heaney, Weyl & Halverson, Gene W. Halverson, Duluth, for appellant.

Palmer, Hood, Crassweller & McCarthy, Duluth, for respondent.

MATSON, Justice.

Plaintiff appeals from an order denying his motion for a new trial solely on the issue of damages or in the alternative for a new trial on all issues and granting defendant's motion for judgment notwithstanding the verdict and from the judgment entered pursuant thereto.

Prior and subsequent to February 4, 1956, plaintiff was employed by St. Mary's Hospital in Duluth as a maintenance engineer particularly responsible for electrical work. During the years 1955 and 1956 a new 9-story wing was under construction on the west end of the existing building. Seven principal contractors were engaged under the general contractor. Defendant was a subcontractor of the new wing and engaged by the principal contractors who held the steampiping, heating, and ventilating contract.

On Saturday, February 4, 1956--the date when plaintiff was injured--the exterior structure of the new wing was nearly completed. The steel superstructure was completed to the ninth floor. The masonry was up to about the seventh floor. On Saturdays no construction work was done, the outside doors were locked, and there was little light inside the new wing. The lightest area was near the west wall where plastic cloth covering the windows admitted some light. At about 11 a.m. plaintiff, aided by a flashlight, entered the new wing through a tunnel leading from the old building to the north side of the newly constructed part. He had been ordered by the maintenance superintendent of the hospital to read the steam-condensate meters once per week, which meters were located in a subbasement in the new wing's northwest corner. These meters measured the amount of condensed steam used by and eventually paid for by the contractors.

After plaintiff had read the condensate meters, he did not retrace his steps eastward along the east-west corridor and tunnel back to the old building. Instead he proceeded southerly from the northwest corner along a north-south corridor parallel to the west wall of the new wing. He intended to go to the southeast corner of the new wing (where three electrical outlets connected to the hospital electrical circuit were located) to see if any construction workmen had left any burning lights connected to the hospital circuit. Although the subcontractors had their own separate electric meters in the subbasement of the new wing, plaintiff had found on previous occasions that the electrical subcontractor had attached some of its electrical equipment to the hospital circuit. Plaintiff testified that on previous Saturdays he had found strings of burning lights connected to the hospital circuit. Furthermore, on several occasions during construction, 60-amp. fuses on the hospital electrical circuit had blown, resulting ina complete shutdown of electric lights and appliances in the kitchen. Evidence existed from which the jury could find that the cause of the fuse blowouts was attributable to the use of the kitchen circuit for electrical tools and lights of the workmen.

The defendant had never used the hospital circuit outlets and there was no evidence that it had any notice or knowledge that any of the contractors had used them. Defendant had used only electrical current flowing through the heating contractor's separate meter in the subbasement of the new wing, under arrangement with the heating contractor.

In going in a southerly direction from the northwest corner, after having checked the condensate meters, plaintiff had a choice of two routes. These two northsouth routes or corridors were separated from each other by a low wall or parapet of a height of 37 inches. The corridor to the east of this parapet was customarily kept open for the passage of workmen and the transport of materials. The one to the west of the parapet was occupied by the electrical contractor's workshop and by the defendant's sheet metal shop. Plaintiff testified that he started to walk down the east side corridor but found it partially blocked by scaffolding whereupon he elected to turn back and enter the workshop corridor on the west side of the parapet. This latter corridor is flanked on the east by the parapet and on the west by the outside wall. Along the parapet are pillars located about 10 feet apart, and these pillars protrude into the corridor about 2 1/2 feet. Opposite the parapet-wall pillars are corresponding outside-wall pillars which extend into the corridor about 13 inches. Although from the parapet to the outside wall the corridor has a width of 19 feet, its width between the opposing pillars is only 15 feet and 3 inches.

In entering the workshop corridor plaintiff first passed through the space used as an electrical workshop and then approached the space occupied by the defendant's workbench and sheet metal shaping machine. Defendant's workbench was 32 inches high, 7 feet wide, and 14 feet long and stood with its westerly end about a foot from the outside wall and its easterly end pointing at right angles toward the parapet-wall space between two pillars. Between the east end of the workbench and the parapet wall was a space about 4 feet wide. The two parapet pillars, however, protruded to such an extent that only about 1 1/2 to 2 1/2 feet clearance existed between the corner of each pillar and the corner of the workbench. Leaning or standing against the east end of the workbench were 27 sheets of 22-gauge sheet metal weighing over 33 pounds per sheet and 10 to 15 sheets of 24-gauge sheet metal weighing over 27 pounds per sheet. These sheets, each 3 feet wide and 8 feet long, were stacked together on edge, long side down, against the east end of the workbench. About 6 inches of the sheet metal stack extended from each side of the bench. The total weight of the metal was between 1,100 and 1,300 pounds. In aggregate the sheets were from 1 3/4 to 2 inches thick.

Plaintiff first observed the sheet metal when he was 4 to 6 feet from the bench. As he reached the bench he put his hand on the edge of the pile using it like a banister. When he reached the middle of the sheet metal stack, he again put his hand on the edge. The end sheets began to 'feather.' Plaintiff attempted to hold the pile in place but despite his efforts the whole pile of metal fell upon him, pinned his left foot under his right knee, and cramped plaintiff tightly against the parapet wall. Unable to remove the sheets, plaintiff remained in this position for about a half an hour before help arrived.

Plaintiff brought this action alleging defendant's employees were negligent in improperly stacking the sheet metal in a position so nearly perpendicular that it would easily fall. Medical testimony indicated plaintiff has suffered a permanent 30-percent loss of the use of his right leg and that he probably will always limp and never be able to run. His medical and hospital expenses exceeded $2,500 and he had a loss of wages in excess of $700. The jury gave him a verdict of $6,192.

Did the trial court err in denying plaintiff's motion for a new trial on the issue of damages alone or in the alternative for a new trial on all issues, and in granting defendant's motion for judgment notwithstanding the verdict?

After ascertaining the legal status of defendant and plaintiff in respect to each other, we need only consider whether the evidence as a whole, taken in the light most favorable to the verdict, presented issues of negligence for the jury.

1--2. We first turn to a consideration of defendant's status. Defendant alleges that as a construction subcontractor he occupies the same status as a possessor of land. Plaintiff asserts, however, that since the contract governing the construction does not specifically turn over possession of the premises to the contractors but rather indicates a sharing of possession between the contractors and the hospital, defendant does not occupy the position of a possessor of land. Plaintiff is in error. Restatement, Torts, § 384, 1 reads 'One who on behalf of the possessor of land erects a structure or creates any other condition thereon is subject to the same liability, and enjoys the same immunity from liability, As though he were the possessor of the land, for bodily harm caused to others within and without the land, While the work is in his charge, by the dangerous character of the structure or other condition.' (Italics supplied.)

...

To continue reading

Request your trial
18 cases
  • Whirlpool Corporation v. Morse
    • United States
    • U.S. District Court — District of Minnesota
    • June 13, 1963
    ...Court of Minnesota seems to have expressly rejected at least one of Dean Prosser's arguments, Dishington v. A. W. Kuettel & Sons, Inc., 255 Minn. 325, 96 N.W.2d 684, 689, at fn. 7 (1959), without saying whether it disagreed with the numerous cases from Minnesota and elsewhere upon which tha......
  • Simmers v. Bentley Constr. Co.
    • United States
    • Ohio Supreme Court
    • September 9, 1992
    ...by such owner or occupier. See, e.g., 2 Restatement of the Law 2d, Torts (1965) 287, Section 383 3; Dishington v. A.W. Kuettel & Sons, Inc. (1959), 255 Minn. 325, 96 N.W.2d 684; Ireland v. Complete Mach. & Equip. Co. (1940), 174 Misc. 91, 21 N.Y.S.2d Under the law set forth by the majority,......
  • Broadway v. Blythe Industries, Inc.
    • United States
    • North Carolina Supreme Court
    • February 27, 1985
    ...work is in his charge." (Emphasis added.) Accord, Coggins v. Hanchette, 52 Cal.2d 67, 74, 338 P.2d 379; Dishington v. A.W. Kuettel & Sons, Inc., 255 Minn. 325, 329-30, 96 N.W.2d 684; see Greene v. DiFazio, supra [148 Conn. 419, 171 A.2d 411 (1961) ]. This is consistent with our view express......
  • Thill v. Modern Erecting Co.
    • United States
    • Minnesota Supreme Court
    • September 3, 1965
    ...12, 50 N.W.2d 620.2 La Malfa v. Piombo Bros., 70 Cal.App.2d 840, 161 P.2d 964; Restatement, Torts, § 414.3 Dishington v. A. W. Kuettel & Sons, Inc., 255 Minn. 325, 96 N.W.2d 684; Restatement, Torts, § 384.4 Rosenberg v. Schwartz, 260 N.Y. 162, 183 N.W. 282; Hooey v. Airport Const. Co., 253 ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT