District of Columbia v. Royal

Decision Date02 August 1983
Docket NumberNo. 82-522.,82-522.
PartiesDISTRICT OF COLUMBIA, Appellant, v. Thelma ROYAL, et al., Appellees.
CourtD.C. Court of Appeals

Richard B. Nettler, Asst. Corp. Counsel, Washington, D.C., with whom Judith W. Rogers, Corp. Counsel, and Charles L. Reischel, Deputy Corp. Counsel, Washington, D.C., were on the brief, for appellant. Leo A. Roth, Jr., Washington, D.C., for appellees.

Before NEBEKER, BELSON and TERRY, Associate Judges.

NEBEKER, Associate Judge:

On May 13, 1977, a six-year-old child, Sabrina Nicholas, was injured on the grounds of Bancroft Elementary School by a cross-pole which fell off a fence from which the fence fabric had recently been removed. The child's mother, Thelma Royal, sought recovery from both the construction company, Edward M. Crough, Inc. (Crough), and the District of Columbia alleging that the former negligently performed its construction work and the latter negligently failed to supervise school children in the construction area. The two defendants filed cross-claims against each other for contribution, the District additionally cross-claiming for indemnification. On the date set for trial, Crough entered into a settlement agreement with appellees for $280,500. A bench trial did proceed, however, on Crough's cross-claim against the District. The trial court ruled in favor of Crough on its contribution claim, awarding them $140,250. Concurrently, the trial court ruled against the District on its indemnity claim. It is these rulings which are the subject of this appeal. We affirm.

In 1974, the District of Columbia contracted with Crough to construct an addition and make alterations to the Bancroft Elementary School and to remove temporary classrooms from the school grounds. Article 14 of the Construction Contract provided that:

[t]he Contractor [Crough] shall indemnify and save harmless the District and all of its officers, agents and servants against any and all claims or liability arising from or based on, or as a consequence or result of, any act, omission or default of the Contractor, his employees, or his subcontractors, in the performance of, or in connection with, any work required, contemplated or performed under the Contract.

Sometime between mid-April and early May 1977, Crough removed the fence fabric from the vertical and horizontal poles of a metal fence surrounding some temporary classrooms which were being relocated. Once the fence fabric had been taken down, some of the cross-poles fell off the vertical poles upon which they were situated. Other cross-poles were removed by Crough because they were obviously loose. Crough did not, however, test the cross-poles that remained standing.

On the afternoon of May 13, 1977, some children were swinging on the fence poles near where Sabrina Nicholas was waiting to be picked up by her father. Sabrina was subsequently struck by a cross-pole as it fell to the ground. No Bancroft teacher was stationed at the construction site to supervise the dismissal of the children, although teachers were stationed at other points around the school building. The children had, however, been instructed daily that they were to keep away from the construction area, including the grass strip that separated the street from the fence which surrounded the temporary classrooms.

I

Initially, lvve focus our attention upon the District's indemnity claim. It is the District's contention that the language of the indemnification clause noted above is sufficiently broad so as to indemnify the District against liability based upon its own negligence. We disagree. Though concededly deciding a question under federal law not binding on us, the Supreme Court in United States v. Seckinger, 397 U.S. 203, 90 S.Ct. 880, 25 L.Ed.2d 224 (1970), declared that in order to permit an indemnitee to recover for his own negligence, the reviewing court must be "firmly convinced that such an interpretation reflects the intention of the parties." Id. at 211, 90 S.Ct. at 885. The Court then construed an indemnification clause similar to the one at issue here1 and concluded that "[w]e can hardly say that this intention is manifested by the formulation incorporated into the present contract. By its terms Seckinger is clearly liable for its negligence, but the contractual language cannot readily be stretched to encompass the Government's negligence as well." Id. at 212-13, 90 S.Ct. at 885-86. (Emphasis in original.)

The United States District Court for the District of Columbia followed the Seckinger rationale in District of Columbia v. C.F. & B., Inc., 442 F.Supp. 251 (D.D.C.1977). There, again, the language of the indemnity provisions paralleled that with which we are presented.2 The court held that under the contract the District could not "recover for damages resulting either from its own negligence or from acts or omissions in which it was concurrently negligent. . . ." Id. at 257. We see no reason why a different result should obtain here. Where the District expects to shift the ultimate responsibility for its negligence to its contractors, such an intention should be plainly evident from the face of the contract.

II

We turn now to the issue of whether the District was negligent in failing to assign a teacher to supervise the dismissal of Bancroft school children along the north side of the school grounds. At the outset, we recognize that the District of Columbia is not the insurer of the complete safety of school children nor is it strictly liable for any injuries which may occur to them. Benton v. School Board of Broward County, 386 So.2d 831, 834 (Fla.App.1980); Lauricella v. Board of Education, 52 A.D.2d 710, 381 N.Y.S.2d 566 (1976); Annot., 36 A.L.R.3d 330 (1971). "Teachers and school boards do, however, have an obligation to supervise the activity of students when the school is entrusted with their care." Benton, supra; McLeod v. Grant County School District No. 128, 42 Wash.2d 316, 255 P.2d 360 (1953); Annot., 38...

To continue reading

Request your trial
16 cases
  • Hedgepeth v. Clinic
    • United States
    • D.C. Court of Appeals
    • June 30, 2011
    ...have a duty to “scrupulously honor the trust and confidence reposed in them because” of fiduciary relationship); District of Columbia v. Royal, 465 A.2d 367, 369 (D.C.1983) (recognizing the District's duty of care for the protection of school children in its schools); Smith v. Safeway Store......
  • Munn v. Hotchkiss Sch.
    • United States
    • Connecticut Supreme Court
    • August 11, 2017
    ...360, 87 Cal.Rptr. 376 (1970) ; Hecksher v. Fairwinds Baptist Church, Inc. , 115 A.3d 1187, 1206 (Del. 2015) ; District of Columbia v. Royal , 465 A.2d 367, 369 (D.C. 1983) ; Rupp v. Bryant , 417 So.2d 658, 666 (Fla. 1982) ; Doe Parents No. 1 v. State Dept. of Education , 100 Hawai'i 34, 74,......
  • POWELL v. DISTRICT OF COLUMBIA, 92-CV-423
    • United States
    • D.C. Court of Appeals
    • November 29, 1993
    ...reasonable care to prevent foreseeable harm to students attending public schools. It relies, inter alia, on District of Columbia v. Royal, 465 A.2d 367, 369 (D.C. 1983) and District of Columbia v. Doe 524 A.2d 30, 33-34 (D.C. 1987). These cases, however, involved events originating or occur......
  • National RR Passenger Corp. v. Consolidated Rail Corp.
    • United States
    • U.S. District Court — District of Columbia
    • October 3, 1988
    ...224 (1970); Princemont Construction Corp. v. Baltimore and Ohio Railroad Co., 131 A.2d 877, 878 (D.C. 1957); District of Columbia v. Royal, 465 A.2d 367, 369 (D.C.1983). Moreover, in light of the very strong public policy considerations, the Court cannot conclude that the indemnification pr......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT