Dugan v. Kelly
Decision Date | 08 April 1905 |
Citation | 86 S.W. 831 |
Parties | DUGAN v. KELLY. |
Court | Arkansas Supreme Court |
Appeal from Circuit Court, Garland County; Alexander M. Duffie, Judge.
Action by John Kelly against Charles Dugan. From a judgment for plaintiff, defendant appeals. Affirmed.
This is an action by appellee to recover for work performed for appellant under a written contract, the material portions of which are as follows: The item and amount in controversy is for the removal of 686 cubic yards of stone and earth, as "extra sloping," in addition to the 300 yards stipulated for in the contract; and the question presented is whether, under the contract, appellee was compelled, without extra charge, to remove all the slope, regardless of the amount, or whether he could charge for all in addition to 300 yards. The contention of appellee is that, for the stipulated sum, he was to remove not exceeding the 300 yards named, and could charge for any excess, whilst appellant claims that appellee, by the contract, agreed to remove all the slope, and that he could make no extra charge for an excess over 300 yards unless required by appellant to do it as extra work. "Sloping" is defined by one of the witnesses to be "all the earth necessary to be taken off on back of a perpendicular line to keep it from caving"; and it is shown by proof that, when the contract was made, it was estimated that it would probably be necessary to remove about 300 yards of slope. It is conceded that a considerable amount of the work claimed by appellee as additional sloping was in removing earth which caved into the excavation from the bank before erection of the retaining wall. It appears also that a part of the additional sloping was on account of irregular and abutting points and angles in the bank left by the cave or landslide. Another disputed point in the construction of the contract is whether the slope in the bank should have begun from the top or from the bottom of the retaining wall. Appellee testified that the slope began from the bottom of the wall, and that that was essential, as the only purpose served by the wall was to retain the dirt falling from the mountain side, and that it was not necessary for protection against caving.
The case was submitted to the jury upon the following instructions:
To continue reading
Request your trial