Edward H. Schwartz Const., Inc. v. Driessen, 20050150.

Decision Date31 January 2006
Docket NumberNo. 20050150.,20050150.
Citation2006 ND 15,709 N.W.2d 733
CourtNorth Dakota Supreme Court
PartiesEDWARD H. SCHWARTZ CONSTRUCTION, INC., Plaintiff and Appellee v. Garry DRIESSEN d/b/a A & G Construction Company, Defendant and Appellant.

Dann E. Greenwood, Greenwood & Ramsey, PLLP, Dickinson, ND, for plaintiff and appellee.

Ronald G. Schmidt, Schmidt, Schroyer, Moreno & Lee, P.C., Rapid City, SD, for defendant and appellant.

CROTHERS, Justice.

[¶ 1] Garry Driessen, doing business as A & G Construction Company, appeals from a judgment awarding Edward H. Schwartz Construction, Inc., $20,615, plus interest, for breach of an oral contract to provide aggregate at $2 per cubic yard for a road construction project. We conclude the district court did not clearly err in finding Driessen orally contracted with Schwartz Construction to provide aggregate for the project at $2 per cubic yard, and we affirm.

I

[¶ 2] In May 2002, the North Dakota Department of Transportation solicited bids on County Federal Aid Project No. SC-1927(056) for grading and aggregate surfacing of a county road south of Carson. Bids for the project were due on May 17, 2002, and on the evening of May 16, 2002, Randall Schwartz, the president of Schwartz Construction, secured bids from prospective subcontractors for the different parts of the project, including aggregate. According to Schwartz, Driessen orally offered to provide aggregate at $2 per cubic yard for the project. According to Driessen, his quote for the aggregate was $2 per ton. Schwartz testified he informed Driessen that Driessen had the low bid for the aggregate and that Schwartz Construction's bid for the project was based on Driessen's bid for the aggregate. Schwartz Construction was awarded the contract for the project, and Driessen acknowledged that he learned Schwartz Construction had been awarded the contract shortly after the bids were opened on May 17, 2002.

[¶ 3] The parties did not have any further contact until June 2002, when Schwartz and Driessen had a telephone conversation and Schwartz Construction faxed several documents to Driessen. According to Driessen, he received a call from Schwartz on June 23, 2002, while Driessen was traveling to Aberdeen, South Dakota. Driessen testified he had taken other work in Aberdeen, because he did not know he had the job with Schwartz Construction. Driessen testified that during the phone conversation, Schwartz said "[h]e wanted [Driessen] to do the job," and Driessen replied that "maybe we could do it on the way back." According to Schwartz, he asked Driessen "point-blank if he was still going to do [the job]. And [Driessen] said, yeah, he'd do it after South Dakota." On June 26, 2002, Schwartz Construction faxed several documents to Driessen, including a cover letter, a request to sublet form, and a standard subcontract agreement form for the project. Those documents stated the price for the aggregate was $2 per cubic yard. In the cover letter, Schwartz Construction asked Driessen to "sign & mail subcontracts & request to sublet back to me," but Driessen did not return those documents to Schwartz Construction.

[¶ 4] Driessen did not provide Schwartz Construction with the aggregate for the project, and Schwartz Construction subsequently subcontracted with another firm to provide aggregate for the project at the price of $2.95 per cubic yard. Schwartz Construction sued Driessen for the difference in prices. Schwartz Construction claimed Driessen had contracted to provide aggregate for the project at the price of $2 per cubic yard. Driessen claimed there was no contract because his quote was conditioned upon Schwartz Construction providing a gravel pit to supply the aggregate, his quote was not accepted by Schwartz Construction in a timely manner, and his quote was to provide the aggregate at $2 per ton and not $2 per cubic yard. After a bench trial, the district court found Driessen contracted with Schwartz Construction to provide aggregate for the project at $2 per cubic yard. The court awarded Schwartz Construction damages of $20,615, plus interest.

II

[¶ 5] During oral argument to this Court, Driessen abandoned his claim that this Court's review of the district court's findings is not governed by the clearly erroneous rule because the court's findings rest primarily upon documentary evidence. Compare Dolajak v. State Auto. & Cas. Underwriters, 252 N.W.2d 180, 181-82 (N.D.1977) (declining to apply clearly erroneous rule to findings based on documentary evidence), with Stracka v. Peterson, 377 N.W.2d 580, 582 (N.D.1985) (applying clearly erroneous rule to findings based on undisputed facts or documentary evidence). Driessen argues the district court clearly erred in finding he orally contracted with Schwartz Construction to provide aggregate for the project at $2 per cubic yard. Driessen argues there was no meeting of the minds between the parties, because his offer was conditioned upon Schwartz Construction securing a gravel pit to supply the aggregate, his offer was not accepted in a timely manner and lapsed, and his offer was to supply aggregate at $2 per ton. Driessen argues the district court's finding that there was an oral contract is not supported by substantial evidence and was induced by an erroneous view of the law. He also claims this Court should be left with a definite and firm conviction the district court made a mistake in finding he orally contracted with Schwartz Construction to provide aggregate at $2 per cubic yard.

[¶ 6] The existence of an oral contract and the extent of its terms are questions of fact, subject to the "clearly erroneous" standard of review under N.D.R.Civ.P. 52(a). Forster v. West Dakota Veterinary Clinic, Inc., 2004 ND 207, ¶ 57, 689 N.W.2d 366; Comstock Constr., Inc. v. Sheyenne Disposal, Inc., 2002 ND 141, ¶ 13, 651 N.W.2d 656. In Brandt v. Somerville, 2005 ND 35, ¶ 12, 692 N.W.2d 144 (citations omitted) we recently outlined our scope of review under the "clearly erroneous" rule:

A finding of fact is clearly erroneous if it is induced by an erroneous view of the law, if no evidence exists to support the finding, or if, on the entire record, we are left with a definite and firm conviction the trial court made a mistake. A trial court's choice between two permissible views of the weight of the evidence is not clearly erroneous, and simply because we may have viewed the evidence differently does not entitle us to reverse the trial court. On appeal, we do not reweigh conflicts in the evidence, and we give due regard to the trial court's opportunity to judge the credibility of the witnesses.

A

[¶ 7] Driessen argues the district court clearly erred in finding he did not condition his quote upon Schwartz Construction securing a gravel pit for the aggregate. Driessen argues the district court misapplied the law because the performance of the conditions of a proposal is necessary for the acceptance of a proposal under N.D.C.C. § 9-03-20 and the record clearly establishes he conditioned acceptance of his quote upon Schwartz Construction securing a gravel pit.

[¶ 8] Although Driessen testified his offer was conditioned upon Schwartz Construction procuring a gravel pit for the aggregate, Schwartz testified Driessen did not limit or condition his offer to Schwartz Construction. The district court found Driessen did not condition his quote upon Schwartz Construction securing a pit for the aggregate. On appeal, we do not reweigh conflicting evidence, and a choice between two permissible views of the evidence is not clearly erroneous. Brandt, 2005 ND 35, ¶ 12, 692 N.W.2d 144. Simply because we may have viewed the evidence differently does not entitle us to reverse the district court. Id. We conclude the district court's finding that Driessen did not condition his quote upon Schwartz Construction securing a gravel pit is supported by evidence in this record and that finding was not induced by an erroneous application of the law. We are not left with a definite and firm conviction the court made a mistake in finding Driessen did not condition his quote, and we conclude the court's finding is not clearly erroneous.

B

[¶ 9] Driessen...

To continue reading

Request your trial
17 cases
  • Wfnd, LLC v. Fargo Marc, LLC
    • United States
    • North Dakota Supreme Court
    • May 7, 2007
    ...of its terms are questions of fact subject to the clearly erroneous standard of review under N.D.R.Civ.P. 52(a). Edward H. Schwartz Constr., Inc. v. Driessen, 2006 ND 15, ¶ 6, 709 N.W.2d 733. A contract requires parties capable of contracting, consent of the parties, a lawful object, and su......
  • Crandall v. Crandall
    • United States
    • North Dakota Supreme Court
    • July 13, 2011
    ...and simply because we may have viewed the evidence differently does not entitle us to reverse the trial court.’ ” Edward H. Schwartz Constr., Inc. v. Driessen, 2006 ND 15, ¶ 6, 709 N.W.2d 733 (quoting Brandt v. Somerville, 2005 ND 35, ¶ 12, 692 N.W.2d 144). “ ‘On appeal, we do not reweigh c......
  • Heng v. Rotech Medical Corp.
    • United States
    • North Dakota Supreme Court
    • August 2, 2006
    ...or if, on the entire record, we are left with a definite and firm conviction the district court made a mistake. Edward H. Schwartz Constr., Inc. v. Driessen, 2006 ND 15, ¶ 6, 709 N.W.2d 733. A district court's choice between two permissible views of the weight of the evidence is not clearly......
  • Hoverson v. Hoverson
    • United States
    • North Dakota Supreme Court
    • February 12, 2015
    ...or if, on the entire record, we are left with a definite and firm conviction the trial court made a mistake.” Edward H. Schwartz Constr., Inc. v. Driessen, 2006 ND 15, ¶ 6, 709 N.W.2d 733 (quoting Brandt v. Somerville, 2005 ND 35, ¶ 12, 692 N.W.2d 144). Under the clearly erroneous standard ......