Edward J. Gerrits, Inc. v. Astor Elec. Service, Inc.

Decision Date02 March 1976
Docket NumberNos. 75--525 and 75--644,s. 75--525 and 75--644
Citation328 So.2d 522
PartiesEDWARD J. GERRITS, INC., a Florida Corporation, and the National Fire Insurance Company of Hartford, a Foreign Corporation, Appellants, v. ASTOR ELECTRIC SERVICE, INC., a Florida Corporation, Appellee.
CourtFlorida District Court of Appeals

Richard M. Gale, Miami, Cypen & Nevins, Miami Beach, for appellants.

Therrel, Baisden, Peterson, Stanton & Stillman and Fred R. Baisden, Jr., Miami Beach, for appellee.

Before BARKDULL, C.J., and PEARSON and NATHAN, JJ.

PEARSON, Judge.

These appeals are by the defendants from a summary final judgment and an amended summary final judgment respectively. The difference in the two judgments is that the second fixed attorney's fees for the plaintiff. The defendants are Edward J. Gerrits, Inc., the general contractor for the construction of the Cedars of Lebanon Hospital in Miami, and The National Fire Insurance Company of Hartford, the general contractor's surety. The appealed judgment held that the general contractor must pay the plaintiff subcontractor, Astor Electric Service, Inc., the balance of its unpaid subcontract even though the owner is insolvent and the general contractor may be forced to accept an agreement by the receiver for payment of 62% Of the amount due on the contract.

The question presented on this appeal arises out of the following provision in the contract between the contractor and the subcontractor:

'SECTION IV--Payments: The General Contractor agrees to pay to the Subcontractor for the performance of his work the sum of ONE MILLION, TWELVE THOUSAND, FOUR HUNDRED FORTH Dollars and no/100 ($1,012,440.00) which amount includes all work in Section II of this contract, all permits that must be taken out for the performance of his work, all taxes, licenses, fees, etc. The money to be paid in current funds and at such times as the General Contractor receives it from the Owner.' (Emphasis added)

The contractor relies upon the rule that where a promise to pay is conditioned upon the realization of a particular fund, then the promise may not be enforced unless the fund is realized. 1 Cohen v. Mohawk, Inc., Fla.1962, 137 So.2d 222; see Mascioni v. I. B. Miller, Inc., 261 N.Y. 1, 184 N.E. 473 (1933).

The subcontractor urges that the provision for payment to it 'at such times as the General Contractor receives it from the owner' is a provision as to time of payment and is not a condition of payment. The subcontractor further points out that in such circumstances, some courts have held that the debt still exists and must be paid within a reasonable time. See Mock v. Trustees of First Baptist Church of Newport, 252 Ky. 243, 67 S.W.2d 9, 94 A.L.R. 716 (1934); Thos. J. Dyer Co. v. Bishop International Engineering Co., 303 F.2d 655, (6th Cir. 1962). 2

We hold that the better reasoned view is that expressed by the Court of Appeals of New York in Mascioni v. I. B. Miller, Inc., 261 N.Y. 1, 184 N.E. 473 (1933). The court dealt there with a provision in a contract providing for 'payments to be made as received from the Owner.' The provision in the present contract is a very similar one providing for 'The money to be paid in current funds and at such times as the General Contractor receives it from the Owner.' In each case, the subject is not a debt already in existence but an obligation to any upon a contract which created the obligation. The contract may be reasonably interpreted as shifting to the subcontractor the risk of the owner's failure to pay.

We recognize that every contract is to be construed in accordance with the intention of the parties. On the motion for summary judgment, the contractor, by its affidavit, has introduced into this cause the issue of the intention of the parties. 3 The subcontractor has maintained as to the summary judgment that the intention is immaterial, but this does not bar a litigation of the issue if it is found to be material.

In addition, as pointed out, it appears from the record that the prospects are that there will be a payment of 62% Of the balance due on the general contract from a settlement by the bankruptcy court.

We, therefore, reverse the summary...

To continue reading

Request your trial
7 cases
  • Gardinier, Inc., In re
    • United States
    • U.S. Court of Appeals — Eleventh Circuit
    • November 5, 1987
    ...noted, the intention of the parties is the governing principle in contract construction, Edward J. Gerrits, Inc. v. Astor Electric Service, Inc., 328 So.2d 522, 524 (Fla.Dist.Ct.App.1976); Rylander v. Sears Roebuck & Co., 302 So.2d 478, 479 (Fla.Dist.Ct.App.1974); Bal Harbour Shops, Inc. v.......
  • Peacock Const. Co., Inc. v. Modern Air Conditioning, Inc.
    • United States
    • Florida Supreme Court
    • December 15, 1977
    ...decisions in them of the District Court of Appeal, Second District, conflict with the decision in Edward J. Gerrits, Inc. v. Astor Electric Service, Inc., 328 So.2d 522 (Fla.3d DCA 1976). 1 The two causes have been consolidated for all appellate purposes in this Court because they involve t......
  • Snead Const. Corp. v. Langerman
    • United States
    • Florida District Court of Appeals
    • July 12, 1978
    ...in the record. Appellants have waived this point on appeal. See 2 Fla.Jur. Appeals § 66. Next, relying on Gerrits v. Astor Electrical Services, 328 So.2d 522 (Fla. 3d DCA 1976), appellants argue their obligation to pay Avanti was conditioned on payment to Snead by the owner. 1 In Gerrits th......
  • Aetna Cas. & Sur. Co. v. Warren Bros. Co., Division of Ashland Oil, Inc., 50761
    • United States
    • Florida Supreme Court
    • February 16, 1978
    ...affirmance without opinion, reported at 341 So.2d 296, which is alleged to be in conflict with Edward J. Gerrits, Inc. v. Astor Electric Service, Inc., 328 So.2d 522 (Fla. 3d DCA 1976). This Court has jurisdiction pursuant to Article V, Section 3(b)(3), Florida Constitution. See Foley v. We......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT