Edward L. Nezelek, Inc. v. Southern Bell Tel. and Tel. Co., 78-2561

Decision Date28 May 1980
Docket NumberNo. 78-2561,78-2561
Citation383 So.2d 979
PartiesEDWARD L. NEZELEK, INC., Appellant, v. SOUTHERN BELL TELEPHONE AND TELEGRAPH COMPANY, Appellee.
CourtFlorida District Court of Appeals

Wayne A. Cypen of Cypen & Nevins, Miami Beach, for appellant.

Eugene L. Heinrich and G. Ware Cornell, Jr. of McCune, Hiaasen, Crum, Ferris & Gardner, P. A., Fort Lauderdale, for appellee.

LETTS, Chief Judge.

A contractor here appeals a directed verdict by a trial court because it failed to adequately establish its lost profits under a construction contract which its customer allegedly breached. We reverse.

The contractor found out it was successful on a bid of $989,760. for a building when Southern Bell wrote the following letter:

November 20, 1974

E. L. Nezelek, Inc.

P.O. Box 23490

Fort Lauderdale, Florida

Gentlemen:

We are pleased to inform you that your bid for the new Boca Raton Sandalfoot ESS building is low and has been accepted. Alternate Number One is also accepted.

Three sets of signed and sealed plans and specifications and septic tank approval are being forwarded to you by Baker and Associates for your use in obtaining the required building permits.

Please do not proceed with any work at the site until a contract has been properly executed and you have received official notice to proceed from this office.

Yours truly,

The contractor responded to this letter immediately by forwarding a standard form building contract duly signed by it. This contract was neither signed nor returned by Southern Bell.

Thereafter on January Third, some 45 days after the letter accepting the bid, the contractor wrote a letter claiming that the concluding paragraph of the letter set forth above constituted an illegal stop order and that Southern Bell had "wrongfully failed to give . . . notice to proceed."

We commence by disagreeing with the trial judge who ruled that the loss of prospective profits testimony did not meet the reasonable certainty test enunciated in Adams v. Dreyfus, 352 So.2d 76 (Fla. 4th DCA 1977). 1 At trial, the contractor introduced its bid sheet containing forty-one line items showing a cost including variable overhead of $914,180. From this, a profit of $75,580 was calculated (71/2%). The chief estimator for the contractor testified as to how he had prepared the bid sheet and how he had calculated the variable overhead costs for the job, without objection as to his calculations. Moreover, other evidence introduced set forth a summary of profits made from nine other contract jobs with Southern Bell including a profit in excess of 10% for a very similar building.

Southern Bell argues that these introduced pieces of evidence did not tend to prove or disprove lost...

To continue reading

Request your trial
7 cases
  • Lennar Homes, Inc. v. Masonite Corp.
    • United States
    • U.S. District Court — Eastern District of Louisiana
    • November 9, 1998
    ...Co. v. Union Carbide Corp., 737 F.2d 941, 948 (11th Cir.1984), such damages may be estimated. Nezelek, Inc. v. Southern Bell Tel. and Tel. Co., 383 So.2d 979, 981 (Fla. Dist.Ct.App.1980).6 Lennar has prepared a detailed cost summary outlining various repairs, extending beyond damages possib......
  • U.S. Home Corp. v. Suncoast Utilities, Inc.
    • United States
    • Court of Appeal of Florida (US)
    • June 29, 1984
    ...profits were calculated from certain company records, these records were not introduced. See Edward L. Nezelek, Inc. v. Southern Bell Telephone & Telegraph, 383 So.2d 979 (Fla. 4th DCA 1980). We recognize that a trial judge is vested with reasonable discretion in awarding damages where they......
  • AROK Const. Co. v. Indian Const. Services
    • United States
    • Court of Appeals of Arizona
    • February 11, 1993
    ...fact alone does not preclude as a matter of law a jury finding that an oral contract was made. See Edward L. Nezelek, Inc. v. Southern Bell Tel. & Tel. Co., 383 So.2d 979 (Fla.App.1980) (whether parties intend to be bound prior to a further writing is question for AROK also claims that it i......
  • Marshall Const., Ltd. v. Coastal Sheet Metal & Roofing, Inc.
    • United States
    • Court of Appeal of Florida (US)
    • November 6, 1990
    ...for a new trial on damages and liability. WIGGINTON and MINER, JJ., concur. 1 The case of Edward L. Nezelek, Inc. v. Southern Bell Telephone and Telegraph Co., 383 So.2d 979 (Fla. 4th DCA 1980), relied upon by appellee for the proposition that bid estimates are sufficient to demonstrate los......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT