Elec-Trol, Inc. v. C. J. Kern Contractors, Inc., ELEC-TRO

Decision Date17 November 1981
Docket NumberINC,ELEC-TRO,No. 8121SC315,8121SC315
Citation284 S.E.2d 119,54 N.C.App. 626
CourtNorth Carolina Court of Appeals
Parties, Plaintiff, v. C. J. KERN CONTRACTORS, INC., Defendant and Third-Party Plaintiff, v. NORTH CAROLINA BAPTIST HOSPITALS, INC., Third-Party Defendant.

Adams, Kleemeier, Hagan, Hannah & Fouts by Walter L. Hannah and Bruce H. Connors, Greensboro, and Tornow & Lewis by Michael J. Lewis, Winston-Salem, for plaintiff-appellant.

Brooks, Pierce, McLendon, Humphrey & Leonard by James T. Williams, Jr., Greensboro, and Anthony H. Brett and Womble, Carlyle, Sandridge & Rice by Roddy M. Ligon, Jr., Winston-Salem, for defendants-appellees.

ROBERT M. MARTIN, Judge.

Plaintiff assigns as error the entry of summary judgment for the defendant and the third-party defendant. It argues that where the parties have not agreed that the architect's decisions are final, the subcontractor may bring an action for payment of certain accepted change order work when changes were ordered by the contractor and the architect either failed to rule on the change order requests or ruled erroneously.

In support of this argument the plaintiff relies on three theories, the first of which is that the contract and subcontract do not provide that the architect's determinations shall be final. We disagree.

The terms of the contract between the defendant and the third-party defendant, which terms were incorporated by reference into the contract between plaintiff and defendant, contained provisions governing the procedures by which claims for additional costs were to be determined. Section 12.2.1 of the General and Supplementary Conditions provided that "[i]f the Owner and the Contractor cannot agree on the amount of the adjustment in the contract sum, it shall be determined by the Architect."

The North Carolina courts have recognized that a provision in a contract, providing for the architect's approval before the contractor can recover compensation on his contract, is binding on the parties. When the contract so provides, the architect's certificate is a condition precedent to the contractor's recovery, absent a showing of bad faith or failure to exercise honest judgment. J. R. Graham and Son, Inc. v. Board of Education, 25 N.C.App. 163, 212 S.E.2d 542, cert. denied, 287 N.C. 465, 215 S.E.2d 623 (1975). In Heating Co. v. Board of Education, 268 N.C. 85, 89-90, 150 S.E.2d 65, 68 (1966) the Court stated as follows:

"In building and construction contracts the parties frequently provide that the completion, sufficiency, classification, or amount of the work done by the contractor shall be determined by a third person, usually an architect or engineer. Such stipulations which, in their origin, were designed to avoid harassing litigation over questions that can be determined honestly only by those possessed of scientific knowledge, have generally been held valid. This is true even though the architect or engineer is employed by the owner unless unknown to the contractor, he has guaranteed to keep the cost of the work below a certain sum."

* * *

"Although plain language in the contract is required in order to make the decision or certificate of an architect or engineer acting thereunder final and conclusive, it may be stated generally that the decision of the architect or engineer is conclusive as to any matter connected with the contract if the parties, by any stipulation, constitute the architect or engineer the final arbiter of such matter as between the parties. Accordingly, where the contract provides that the work shall be done to the satisfaction, approval, or acceptance of an architect or engineer, such architect or engineer is thereby constituted sole arbitrator between the parties, and the parties are bound by his decision, in the absence of fraud or gross mistake. The same rule applies where it is provided that payments shall be made only upon the certificate of the architect.

"It is also clear that where the parties stipulate expressly or in necessary effect, that the determination of the architect or engineer shall be final and conclusive, both parties are bound by his determination of those matters which he is authorized to determine, except in case of fraud or such gross mistake as would necessarily imply bad faith or a failure to exercise an honest judgment. The reason underlying this rule is that under such circumstances the contract makes the architect or engineer the arbitrator, and his determination can be attacked only in the same manner as that of any other arbitrator. On the other hand, where the stipulations are such that the meaning to be gathered...

To continue reading

Request your trial
12 cases
  • Speedway Motorsports Int'l Ltd. v. Trading
    • United States
    • North Carolina Court of Appeals
    • February 15, 2011
    ...the parties to a provision in the incorporated document is only one possible result, as in Elec–Trol, Inc. v. C.J. Kern Contractors, Inc., 54 N.C.App. 626, 628, 284 S.E.2d 119, 120 (1981) (enforcing as to subcontractor dispute resolution provision contained in general contractor's contract ......
  • MCI Construction v. Hazen and Sawyer, 1:99CV00002 (M.D.N.C. 8/29/2003)
    • United States
    • U.S. District Court — Middle District of North Carolina
    • August 29, 2003
    ...Kitchen's decisions are not to be evaluated under the FAA, but under the law as set out in Elec-Trol, Inc. v. C. J. Kern Contractors, Inc., 54 N.C. App. 626, 284 S.E.2d 119 (1981), rev, denied, 305 N.C. 298, 290 S.E.2d 701 (1982), and Welborn Plumbing & Heating Co. v. Randolph County Bd. of......
  • Mci Constructors, Inc. v. Hazen and Sawyer, P.C.
    • United States
    • U.S. District Court — Middle District of North Carolina
    • March 10, 2004
    ...case of fraud or such gross mistake as would necessarily imply bad faith or a failure to exercise an honest judgment. 54 N.C.App. 626, 629-30, 284 S.E.2d 119, 121 (1981); see also Welborn Plumbing & Heating Co. v. Randolph County Bd. of Educ., 268 N.C. 85, 91, 150 S.E.2d 65, 69 (1966). Alth......
  • RAD-Razorback Ltd. Partnership v. B.G. Coney Co., RAD-RAZORBACK
    • United States
    • Arkansas Supreme Court
    • July 21, 1986
    ...after the work is completed. Ida Grove Roofing v. City of Storm Lake, 378 N.W.2d 313 (Iowa App.1985); Elec-Trol, Inc. v. C.J. Kern Contractors, 54 N.C.App. 626, 284 S.E.2d 119 (1981); Chambless v. J.J. Fritch, 336 S.W.2d 200 (Tex.Civ.App.1960); 13 Am.Jur.2d § 22, Building and Construction C......
  • Request a trial to view additional results
2 books & journal articles
  • Architect's Contract Administration
    • United States
    • ABA General Library Construction Law
    • January 1, 2009
    ...be a condition 49. See AIA Document A201–2007, supra note 2, § 15.2.5. 50. See, e.g., Elec-Trol, Inc. v. C. J. Kern Contractors, Inc., 284 S.E.2d 119 (N.C. Ct. App. 1981). 51. See SWEET & SCHNEIER, supra note 34, §§ 29.09–29.10. 52. See 5 BRUNER & O’CONNOR, supra note 15, § 17:83 (2006). 53......
  • Architect's Contract Administration
    • United States
    • ABA General Library Construction Law
    • June 22, 2009
    ...be a condition 49. See AIA Document A201–2007, supra note 2, § 15.2.5. 50. See, e.g., Elec-Trol, Inc. v. C. J. Kern Contractors, Inc., 284 S.E.2d 119 (N.C. Ct. App. 1981). 51. See SWEET & SCHNEIER, supra note 34, §§ 29.09–29.10. 52. See 5 BRUNER & O’CONNOR, supra note 15, § 17:83 (2006). 53......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT