Elliott Elec. Supply Co., Inc. v. Adolfson & Peterson, Inc., 28J

Decision Date17 November 1988
Docket NumberNo. 28J,No. 86CA1863,28J,86CA1863
Parties50 Ed. Law Rep. 1252 ELLIOTT ELECTRIC SUPPLY CO., INC., a Colorado corporation, Plaintiff, v. ADOLFSON & PETERSON, INC., a Minnesota corporation, Defendant-Appellant, and Joint Districtof the Counties of Adams and Arapahoe, a Body corporate, Defendant-Appellee. . V
CourtColorado Court of Appeals

Pryor, Carney and Johnson, P.C., A. Craig Fleishman, Mary E. McPherson, Englewood, for defendant-appellant.

Holland & Hart, Wiley E. Mayne, Marcy G. Glenn, Denver, for defendant-appellee.

PLANK, Judge.

Adolfson & Peterson, Inc., (A & P) appeals the summary judgment entered by the trial court which determined that Joint District No. 28J of Adams and Arapahoe Counties (school district) had no obligation to pay interest on funds withheld pursuant to § 38-26-107, C.R.S. (1982 Repl.Vol. 16A). We affirm.

A & P, a general contractor, agreed to build a high school for the school district. A & P subcontracted electrical work for the project to Tee-Pee Electric, Inc. (Tee-Pee). Tee-Pee in turn ordered materials from Elliott Electric Supply Company, Inc. (Elliott). Subsequently, A & P terminated its subcontract with Tee-Pee alleging that it was not staffing the project adequately. Elliott then filed verified notice of claims with the school district asserting claims against funds due A & P from the school district. These claims were based on Tee-Pee's failure to pay Elliott for supplies used for the building of the high school.

Based on the number of conflicting claims between the parties, the school district, pursuant to § 38-26-107, C.R.S. (1982 Repl.Vol. 16A) placed $356,296.36 into an account. This figure represented the amount claimed plus interest owed on that sum. In August of 1986, a settlement was reached by all parties to the litigation. The school district paid the $356,296.36 to the parties and they in turn determined the appropriate distribution of the funds.

During the period that the school district was obligated to retain the funds, interest accrued on the $356,296.36 in the sum of $123,497.97. Elliott subsequently assigned to A & P whatever claims it might have had against the school district for the interest on the withheld funds. The only issue not resolved between A & P and the school district was who was entitled to the interest on the retained $356,296.36.

On cross-motions for summary judgment, the trial court ruled that the school district was entitled to the $123,497.97, and this appeal followed.

I

A & P initially contends that the trial court misconstrued § 38-26-107 in finding that the school district had no statutory obligation to pay interest on the withheld funds. We disagree.

Pursuant to § 38-26-107(2), C.R.S. (1982 Repl.Vol. 16A), the school district was required to withhold all payments to A & P upon the filing of a verified claim by Elliott. The statute is designed to protect those who supply materials to public works projects and stands in the place of the mechanics' lien statute. See South-Way v. Adams City Service, 169 Colo. 513, 458 P.2d 250 (1969).

By its plain language, the bond statute makes no provision for a claimant to receive the interest earned on withheld funds that are ultimately paid to the claimant. Rather, § 38-26-107 requires that the public body withhold sufficient funds to insure the payment of contractor's and subcontractor's claims, and that it retain the withheld amounts until the final outcome of any resultant litigation. In comparison, the general mechanics' lien statute has an express provision for the claimant under a lien to receive interest on its claim. Section 38-22-101(5), C.R.S. (1982 Repl.Vol. 16A).

A & P contends that the trial court...

To continue reading

Request your trial
3 cases
  • Mesa Sand & Gravel Co. v. Landfill, Inc.
    • United States
    • Colorado Supreme Court
    • June 26, 1989
    ...without resort to other rules of statutory construction. In re R.C., 775 P.2d 27, 29 (Colo.1989); Elliott Elec. Supply Co. v. Adolfson & Peterson, Inc., 765 P.2d 1079, 1081 (Colo.App.1988). Statutes susceptible to more than one interpretation, however, must be construed in light of their ap......
  • Portofino Corp. v. Board of Assessment Appeals
    • United States
    • Colorado Court of Appeals
    • August 29, 1991
    ...but inappropriate. See Lassner v. Civil Service Commission, 177 Colo. 257, 493 P.2d 1087 (1972); Elliott Electric Supply Co., Inc. v. Adolfson & Peterson, Inc., 765 P.2d 1079 (Colo.App.1988). Based on these principles, a division of this court in 5050 S. Broadway Corp. v. Arapahoe County Bo......
  • Ackerman v. Power Equipment Co.
    • United States
    • Colorado Court of Appeals
    • July 14, 1994
    ...as it is in this case, resort to legislative intent is not only unnecessary, but inappropriate. Elliott Electric Supply Co. v. Adolfson & Peterson, Inc., 765 P.2d 1079 (Colo.App.1988). However, solely to answer plaintiff's assertion, we note that Representative Robb, in introducing an amend......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT