Elsinore Union Elementary School Dist. of Riverside County v. Kastorff
Decision Date | 01 July 1960 |
Citation | 353 P.2d 713,54 Cal.2d 380,6 Cal.Rptr. 1 |
Court | California Supreme Court |
Parties | , 353 P.2d 713 ELSINORE UNION ELEMENTARY SCHOOL DISTRICT OF RIVERSIDE COUNTY, Plaintiff and Respondent, v. E. J. KASTORFF and the Seaboard Surety Company, a corporation, Defendants and Appellants. L.A. 25739. |
Wallace & Wallace, W. W. Wallace and A. W. Wallace, Los Angeles, for appellant.
Ray T. Sullivan, Jr., County Counsel, and James H. Angell, Asst. County Counsel, Riverside, for respondent.
Defendants, who are a building contractor and his surety, appeal from an adverse judgment in this action by plaintiff school district to recover damages allegedly resulting when defendant Kastorff, the contractor, refused to execute a building contract pursuant to his previously submitted bid to make certain additions to plaintiff's school buildings.We have concluded that because of an honest clerical error in the bid and defendant's subsequent prompt rescission he was not obliged to execute the contract, and that the judgment should therefore be reversed.
Pursuant to plaintiff's call for bids, defendant Kastorff secured a copy of the plans and specifications of the proposed additions to plaintiffs school buildings and proceeded to prepare a bid to be submitted by the deadline hour of 8 p. m., August 12, 1952, at Elsinore, California.Kastorff testified that in preparing his bid he employed worksheets upon which he entered bids of various subcontractors for such portions of the work as they were to do, and that to reach the final total of his own bid for the work he carried into the right-hand column of the work sheets the amounts of the respective sub bids which he intended to accept and then added those amounts to the cost of the work which he would do himself rather than through a subcontractor; that there is 'a custom among subcontractors, in bidding on jobs such as this, to delay giving * * * their bids until the very last moment'; that first sub bid for plumbing was in the amount of $9,285 and he had received it 'the afternoon of the bid-opening,' but later afternoon when 'the time was drawing close for me to get by bids together and get over to Elsinore'(from his home in San Juan Capistrano)he received a $6,500 bid for the plumbing.Erroneously thinking he had entered the $9,285 plumbing bid in his total column and had included that sum in his total bid and realizing that the second plumbing bid was nearly $3,000 less than the first, Kastorff then deducted $3,000 from the total amount of his bid and entered the resulting total of $89,994 on the bid form as his bid for the school construction.Thus the total include no allowance whatsoever for the plumbing work.
Kastorff then proceeded to Elsinore and deposited his bid with plaintiff.When the bids were opened shortly after 8 p. m. that evening, it was discovered that of the five bids submitted that of Kastorff was some $11,306 less than the next lowest bid.The school superintendent and the four school board members present thereupon asked Kastorff whether he was sure his figures were correct, Kastorff stepped out into the hall to check with the person who had assisted in doing the clerical work on the bid, and a few minutes later returned and stated that the figures were correct.He testified that he did not have his worksheets or other papers with him to check against at the time.The board thereupon, on August 12, 1952, voted to award Kastorff the contract.
The next morning Kastorff checked his worksheets and promptly discovered his error.He immediately drove to the Los Angels office of the firm of architects which had prepared the plans and specifications for plaintiff, and there saw Mr. Rendon.Mr. Rendon testified that Kastorff That same morning (August 13) Rendon telephoned the school superintendent and informed him of the error and of its nature and that Kastorff asked to be released from his bid.On August 14 Kastorff wrote a letter to the school board explaining his error and again requesting that he be permitted to withdraw his bid.On August 15, after receiving Kastorff's letter, the board held a special meeting and voted not to grant his request.Thereafter, on August 28, written notification was given to Kastorff of award of the contract to him.1 Subsequently plaintiff submitted to Kastorff a contract to be signed in accordance with his bid, and on September 8, 1952, Kastorff returned the contract to plaintiff with a letter again explaining his error and asking the board to reconsider his request for withdrawal of his bid.
Plaintiff thereafter received additional bids to do the subject construction; let the contract to the lowest bidder, in the amount of $102,900; and brought this action seeking to recover from Kastorff the $12,906 difference between that amount and the amount Kastorff had bid.2Recovery of $4,499.60 is also sought against Kastorff's surety under the terms of the bond posted with his bid.
Defendants in their answer to the complaint pleaded, among other things, that Kastorff had made an honest error in compiling his bid; that 'he thought he was bidding, and intended to bid, $9500.00 more, making a total of $99,494,00 as his bid'; that upon discovering his error he had promptly notified plaintiff and rescinded the $89,994 bid.The trial court found that it was true that Kastorff made up a bid sheet, which was introduced in evidence; that the subcontractor's bids thereupon indicated were those received by Kastorff; that he'had 16 subcontracting bids to ascertain from 31 which were submitted'; and that Kastorff had neglected to carry over from the left-hand column on the bid sheet to the right-hand column on the sheet a portion of the plumbing (and heating) subcontractor's bid.Despite the uncontradicted evidence related hereinabove, including that of plaintiff's architect and of its school superintendent, both of whom testified as plaintiff's witnesses, the court further found, however, that And although finding that 'on or about August 15, 1952,'plaintiff received Kastorff's letter of August 14 explaining that he'made an error of omitting from my bid the item of Plumbing,'the court also found that 3 Judgment was given for plaintiff in the amounts sought, and this appeal by defendants followed.
In reliance upon M. F. Kemper Const. Co. v. City of Los Angeles(1951), 37 Cal.2d 696, 235 P.2d 7, andLemoge Electric v. County of San Mateo(1956), 46 Cal.2d 659, 662, 664(1a, 1b, 2, 3), 297 P.2d 638, defendants urged that where, as defendants claim is the situation here, a contractor makes a clerical error in computing a bid on a public work he is entitled to rescind.
In the Kemper case one item on a worksheet in the amount of $301,769 was inadvertently omitted by the contractor from the final tabulation sheet and was overlooked in computing the total amount of a bid to do certain construction work for the defendant city.The error was caused by the fact that the men preparing the bid were exhausted after working long hours under pressure.When the bids were opened it was found that plaintiff's bid was.$780,305, and the next lowest bid was $1,049,592.Plaintiff discovered its error several hours later and immediately notified a member of defendant's board of public works of its mistake in omitting one item while preparing the final accumulation of figures for its bid.Two days later it explained its mistake to the board and withdrew its bid.A few days later it submitted to the board evidence which showed the unintentional omission of the $301,769 item.The board nevertheless passed a resolution accepting plaintiff's erroneous bid of.$780,305, and plaintiff refused to enter into a written contract at that figure.The board then awarded the contract to the next lowest bidder, the city demanded forfeiture of plaintiff's bid bond, and plaintiff brought action to cancel its bid and obtain discharge of the bond.The trial court found that the bid had been submitted as the result of an excusable and honest mistake of a material and fundamental character, that plaintiff company had not been negligent in preparing the proposal, that it had acted promptly to...
To continue reading
Request your trialUnlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete case access with no limitations or restrictions
-
AI-generated case summaries that instantly highlight key legal issues
-
Comprehensive legal database spanning 100+ countries and all 50 states
-
Advanced search capabilities with precise filtering and sorting options
-
Verified citations and treatment with CERT citator technology

Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete case access with no limitations or restrictions
-
AI-generated case summaries that instantly highlight key legal issues
-
Comprehensive legal database spanning 100+ countries and all 50 states
-
Advanced search capabilities with precise filtering and sorting options
-
Verified citations and treatment with CERT citator technology

Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete case access with no limitations or restrictions
-
AI-generated case summaries that instantly highlight key legal issues
-
Comprehensive legal database spanning 100+ countries and all 50 states
-
Advanced search capabilities with precise filtering and sorting options
-
Verified citations and treatment with CERT citator technology

Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete case access with no limitations or restrictions
-
AI-generated case summaries that instantly highlight key legal issues
-
Comprehensive legal database spanning 100+ countries and all 50 states
-
Advanced search capabilities with precise filtering and sorting options
-
Verified citations and treatment with CERT citator technology

Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete case access with no limitations or restrictions
-
AI-generated case summaries that instantly highlight key legal issues
-
Comprehensive legal database spanning 100+ countries and all 50 states
-
Advanced search capabilities with precise filtering and sorting options
-
Verified citations and treatment with CERT citator technology

Start Your 7-day Trial
-
Sun ' Sand, Inc. v. United California Bank
...(Van Meter v. Bent Construction Co. (1956) 46 Cal.2d 588, 595, 297 P.2d 644, 648; see also Elsinore Union etc. Sch. Dist. v. Kastorff (1960) 54 Cal.2d 380, 386-388, 6 Cal.Rptr. 1, 353 P.2d 713; M. F. Kemper Const. Co. v. City of L.A. (1951) 37 Cal.2d 696, 702, 235 P.2d 7.) The rule develope......
-
Donovan v. RRL Corp.
...city had not known of or contributed to the mistake before it opened the bid. Similarly, in Elsinore Union etc. Sch. Dist. v. Kastorff (1960) 54 Cal.2d 380, 6 Cal.Rptr. 1, 353 P.2d 713 (Elsinore), we authorized the rescission of an erroneous bid even where the contractor had assured the pub......
-
MJ McGough Company v. Jane Lamb Memorial Hospital
...7, 240 N.E.2d 880 (1968); Bd. of Ed. of Floyd County v. Hooper, 350 S.W.2d 629 (Ky.1961); Elsinore Union Elementary School Dist. etc. v. Kastorff, 54 Cal.2d 380, 6 Cal.Rptr. 1, 353 P.2d 713 (1960); James T. Taylor and Son, Inc., v. Arlington Ind. School Dist., 160 Tex. 617, 335 S.W.2d 371 (......
-
Eskra v. Grace (In re Eskra)
..."to examine bank statements and returned checks for alterations or forgeries"]; Elsinore Union Elementary Sch. Dist. of Riverside Cty. v. Kastorff (1960) 54 Cal.2d 380, 388, 6 Cal.Rptr. 1, 353 P.2d 713 ["inadvertent clerical error of omitting" cost of plumbing from a bid]; M. F. Kemper Cons......