Ex parte Bagby Elevator & Elec. Co., Inc.

Decision Date04 April 1980
Citation383 So.2d 173
PartiesEx parte BAGBY ELEVATOR & ELECTRIC COMPANY, INC., a corporation. In re BAGBY ELEVATOR & ELECTRIC COMPANY, INC., a Corporation v. Orlin BUZBEE, d/b/a Buzbee Contracting Company and Balboa Insurance Company. 79-125.
CourtAlabama Supreme Court

Ernest W. Weir, Birmingham, for petitioner.

Robert B. Huie, Birmingham, for respondents.

BEATTY, Justice.

This Court granted certiorari to review the action of the Court of Civil Appeals 383 So.2d 170 in affirming the trial court's grant of summary judgment to the respondents/defendants. We reverse and remand.

The facts of this case revolve around the execution and performance of a construction contract awarded to respondent/defendant Orlin Buzbee, d/b/a Buzbee Contracting Company (hereinafter Buzbee), by the Industrial Water Board of the City of Birmingham. The contract contemplated the construction of various improvements to the Water Board's Sipsey and Cane Creek Pumping Stations, and was awarded to Buzbee on the basis of certain plans and specifications. The improvements were aimed at enhancing the distribution of drinking water to residents of the City of Birmingham, and for use by industrial consumers. As security for its performance, Buzbee executed a labor and material payment bond to the Water Board, with respondent/defendant Balboa Insurance Company (hereinafter Balboa) being named as surety.

Prior to any performance under the contract, Buzbee subcontracted the work to the petitioner/plaintiff Bagby Elevator & Electric Company, Inc. (hereinafter Bagby). Bagby engaged in and completed performance under the contract, with all the work being done in a good and workmanlike manner and in full accord with the specifications of the original agreement. Bagby thereafter filed suit against Buzbee and Balboa for work and labor done, and for the recovery of reasonable attorney's fees.

The action commenced by Bagby never proceeded to trial. Instead, the action was dealt with summarily, as the trial court responded to the parties' respective motions for summary judgment. Bagby made its initial motion for summary judgment on May 26, 1978, requesting judgment on the original claim, for interest thereon, and for an award of reasonable attorney's fees. The motion was based solely upon the pleadings of the parties and requests for admissions made by Bagby and served upon each of the respondents pursuant to the provisions of Rule 36, ARCP. The request for admissions concerned the question whether the terms of the original contract, or the specifications upon which Buzbee was awarded the contract, required Buzbee to furnish a bond in accordance with the provisions of Code 1975, § 39-1-1. That section provides, in part, that a contractor entering into a contract with any public work must execute a bond guaranteeing the payment of materialmen, subcontractors, laborers, etc., and the payment of attorney's fees for successful claimants on the bond. It is uncontradicted that these bond requirements do not apply to the present parties as a matter of law. Although the work performed by Bagby might realistically be classified as a public work, industrial development boards like the Industrial Water Board of the City of Birmingham are not subdivisions of the state. George A. Fuller Co. v. Vulcan Materials Co., 293 Ala. 199, 301 So.2d 74 (1974). Even so, the parties were fully entitled to contract in contemplation of the statute, and with full recognition that any bond to be provided must comply with its terms. If the parties did so contract, it would appear that Bagby would be entitled to recover each of the items it claimed; if not, it is very unlikely that Bagby could establish its entitlement to recover attorney's fees. As a result, an affirmative response to Bagby's requests for admissions would have been highly beneficial to its cause of action.

The responses to the requests for admissions by the respondents were conflicting. Buzbee, the original contractor, failed to respond to the request, thereby admitting the matter by operation of law. Rule 36(a), ARCP. Balboa, on the other hand, entered a conditional denial. It stated that on the basis of those portions of the contract and specifications in its possession, Buzbee was not required to execute a bond of the type referred to in the request for admission. The trial court was thus faced with divergent responses from one in privity of contract and one involved only as a surety.

After reviewing the pleadings and these responses, the Court partially acceded to Bagby's May 26th motion, granting Bagby summary judgment on the original claim for work and labor done. It specifically ordered that issues concerning the award of attorney's fees and the assessment of interest be reserved for trial.

On July 6, 1978, Balboa filed its initial motion for summary judgment, contending that it was entitled to judgment as a matter of law on the attorney's fees issued. This contention was necessarily based on the argument that the provisions of Code 1975, § 39-1-1, did not apply to the parties since the Water Board was not a subdivision of this state. In response to the motion, Bagby revived its previous efforts and filed a counter-motion for summary judgment on both of the remaining issues. Like Bagby's original motion, these motions were based solely upon the pleadings and the requests for admissions. The motions of both parties were overruled on July 20, 1978, and the case was set for trial before a jury on March 21, 1979.

Neither party was content with the July 20th order. As a result, t...

To continue reading

Request your trial
27 cases
  • Sheffield v. Owens-Corning Fiberglass Corp.
    • United States
    • Alabama Supreme Court
    • February 28, 1992
    ...of a summary judgment to "the same factors considered by the trial court in initially ruling on the motion." Ex parte Bagby Elevator & Electric Co., 383 So.2d 173, 176 (Ala.1980). In this case, the plaintiffs and shipowners have produced no evidence that Robinson's interrogatory answer, whi......
  • Federal Ins. Co. v. I. Kruger, Inc.
    • United States
    • Alabama Supreme Court
    • March 15, 2002
    ...294 Ala. 402, 318 So.2d 267 (1975); Bagby Elevator & Elec. Co. v. Buzbee, 383 So.2d 170 (Ala.Civ.App. 1979), rev'd on other grounds, 383 So.2d 173 (Ala.1980). 2. The Watts case is also distinguishable for another reason: the claims asserted in Watts were not asserted pursuant to the little ......
  • Griffin v. Summit Specialties, Inc.
    • United States
    • Alabama Supreme Court
    • June 18, 1993
    ...related to the motion for summary judgment are procedural and are governed by the provisions of Rule 56, Ala.R.Civ.P. Bagby Elevator & Electric Co. v. Buzbee, 383 So.2d 173, 176 (Ala.1980). While the action of the trial court in entering a summary judgment, and the appellate review of that ......
  • WASHINGTON MUT. FINANCE, LLC v. Steele
    • United States
    • Alabama Court of Civil Appeals
    • January 10, 2003
    ...in our review to the same factors considered by the trial court when it initially ruled on the motion, Ex parte Bagby Elevator & Electric Co., Inc., 383 So.2d 173 (Ala.1980), and on such a motion the trial court can consider only the material which is before it at the time of submission of ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT