Federal Ins. Co. v. I. Kruger, Inc.
Decision Date | 15 March 2002 |
Citation | 829 So.2d 732 |
Parties | FEDERAL INSURANCE COMPANY and Bill Harbert Construction Company v. I. KRUGER, INC. |
Court | Alabama Supreme Court |
Edward P. Meyerson and Susan S. Wagner of Berkowitz, Lefkovits, Isom & Kushner, P.C., Birmingham; and Edward C. Greene of Frazer, Greene, Upchurch & Baker, L.L.C., Mobile, for appellants.
W. Craig Hamilton and W. Alexander Moseley of Hand Arendall, L.L.C., Mobile, for appellee.
On Application For Rehearing
The no-opinion order of affirmance of December 7, 2001, is withdrawn and the following is substituted therefor.
Bill Harbert Construction Company ("Harbert") and Federal Insurance Company ("Federal") appeal from a summary judgment entered by the Mobile Circuit Court in favor of I. Kruger, Inc. ("Kruger"), awarding Kruger $129,918.03. We affirm.
Harbert and the Board of Water and Sewer Commissioners of the City of Mobile ("the Water Board") entered into a contract, pursuant to which Harbert was to upgrade a wastewater treatment plant owned and operated by the Water Board. Federal Insurance Company acted as the surety and provided a labor and material payment bond ("the payment bond") in connection with this contract, with Harbert acting as the principal.
Harbert subcontracted with Kruger for the purchase from Kruger of a "reactor basin oxygen dissolution system," for the purchase of certain related parts, and for start-up and training services associated with the dissolution system. The total purchase price of the subcontract was $963,200. The subcontract called for Harbert to make monthly progress payments to Kruger during Kruger's performance, but also allowed Harbert to retain 10% of the total purchase price, or $96,320, until the following conditions were met:
"A final payment, consisting of the unpaid balance of the Price, shall be made thirty (30) days after the last of the following to occur, (a) Purchaser's receipt of all Products in satisfactory condition, (b) final payment by Owner to Purchaser on account of the Products including retainage, (c) delivery of all guarantees, certifications and information required under the Contract Documents, and (d) delivery of a general release, in a form satisfactory to Purchaser, executed by Seller running to and in favor of Purchaser and Owner."
Kruger did, in fact, supply the dissolution system and all related parts to Harbert, as required under the subcontract. Subsequent to this delivery, but before the completion of the subcontract, however, a dispute arose between Harbert and the Water Board. Although Kruger repeatedly notified Harbert that it was ready to perform its duties under the subcontract, Harbert never requested any further services or assistance from Kruger. The Water Board subsequently terminated Harbert's contract. Thus, Kruger was unable to fulfill the terms of its subcontract with Harbert.
On September 22, 1998, after more than a year had elapsed without Harbert's requesting Kruger to perform the start-up or training services referenced in the Harbert-Kruger subcontract, Kruger billed Harbert for one-half of the remaining 10% due under the subcontract ("the retainage"). On December 18, 1998, Kruger billed Harbert for the other one-half of the retainage. When Harbert did not pay the amounts billed, Kruger notified Federal, the surety, of its claim under the payment bond.
Kruger later instituted this action against Harbert and against Federal, seeking to collect the $96,320 retainage. Kruger's claims were premised on the language of the payment bond and on Ala.Code 1975, § 39-1-1 et seq., known as Alabama's "little Miller Act."1
Kruger filed a motion for a summary judgment on its claim for payment. Federal filed no opposition to Kruger's motion for a summary judgment. Harbert, however, opposed Kruger's summary-judgment motion on two grounds.
Harbert first contended that Kruger had not fully performed under its subcontract with Harbert. In support of this argument, Harbert submitted the affidavit of Michael E. Lamb, the division manager of Harbert's utility and industrial division. In that affidavit, Lamb attested that "[a]s a result of the Board's wrongful termination of the Upgrade and Modifications Contract, Kruger's obligations under the Kruger Subcontract have not been and cannot be satisfied." In particular, Lamb testified that Kruger had not fully provided the "construction assistance," "testing," "demonstrations," "start-up," and "training," specified in the subcontract and had not met the "requirements for guarantees, certifications and information."
Second, Harbert relied on the "pay-when-paid" clause in the Harbert-Kruger subcontract for the proposition that Kruger was not due payment of the retainage until the Water Board paid Harbert. As authority for this position, Harbert relied upon the cases of James E. Watts & Sons Contractors, Inc. v. Nabors, 484 So.2d 373 (Ala.1985), and A.G. Gaston Construction Co. v. Hicks, 674 So.2d 545 (Ala.Civ.App. 1995). The trial court entered a summary judgment in favor of Kruger against both Harbert and Federal. Harbert and Federal appealed, and we initially affirmed the trial court's judgment without an opinion. Harbert filed an application for rehearing, which we are overruling.
In Jefferson County Commission v. ECO Preservation Services, L.L.C., 788 So.2d 121 (Ala.2000), this Court addressed the standard applicable to our review of a ruling on a summary-judgment motion. The ECO Preservation Services Court stated:
We must determine whether Kruger is entitled to recover under the payment bond. The payment bond states that it was given pursuant to § 39-1-1, Ala.Code 1975, the little Miller Act. The little Miller Act provides, in pertinent part:
The trial court noted that the purpose of a payment bond required under the little Miller Act is to "shift the ultimate risk of nonpayment from workmen and suppliers to the surety." (citing American Sur. Co. v. Hinds, 260 F.2d 366, 368 (10th Cir. 1958)). Thus, Kruger, as a subcontractor and a supplier on the Water Board-Harbert project, is a member of the class the little Miller Act was intended to protect. The Act is to be liberally construed to effect the purpose of the statute. Sparks Constr., Inc. v. Newman Bros., 51 Ala. App. 690, 288 So.2d 749 (1974). Where a payment bond shows on its face that it was executed in compliance with the Act, a court is authorized to read into the bond the provisions of the statute and to give the bond the form and effect the statute contemplated, regardless of the contents of the bond. American Cas. Co. v. Devine, 275 Ala. 628, 157 So.2d 661 (1963); Water Works, Gas & Sewer Bd. of Oneonta, Inc. v. P.A. Buchanan Contracting, Inc., 294 Ala. 402, 318 So.2d 267 (1975).
In A.G. Gaston Construction Co. v. Hicks, 674 So.2d 545 (Ala.Civ.App.1995), the Court of Civil Appeals quoted the United States Court of Appeals for the Eleventh Circuit and identified four elements that must be proven before a supplier or a subcontractor is entitled to recover under a payment bond issued pursuant to the little Miller Act:
"`(1) that materials or labor were supplied for work on the public project at issue; (2) that the supplier was not paid for the materials or labor supplied; (3) that the...
To continue reading
Request your trial-
Evans, Mechwart, Hambleton & Tilton, Inc. v. Triad Architects, Ltd.
...pay-when-paid provisions "are not intended to provide the contractor with an eternal excuse for nonpayment"); Fed. Ins. Co. v. I. Kruger, Inc. (Ala.2002), 829 So.2d 732, 740 (holding that "the majority of jurisdictions construe [a pay-when-paid] * * * provision as allowing payment under the......
-
Johnson Controls, Inc. v. Liberty Mut. Ins. Co.
...895 (Ala.1994), and “to ‘shift the ultimate risk of nonpayment from workmen and suppliers to the surety.’ ” Federal Ins. Co. v. I. Kruger, Inc., 829 So.2d 732, 736 (Ala.2002) (quoting trial court's order).On June 7, 2013, JCI filed a renewed motion for a summary judgment. In its brief in su......
-
Finish Line v. J.F. Pate & Assocs. Contractors, Inc.
...judgment entered thereon.”The statute is patterned after the federal “Miller Act,” 40 U.S.C. §§ 3131–3133, see Federal Ins. Co. v. I. Kruger, Inc., 829 So.2d 732, 734 (Ala.2002), and “[t]he construction given to the federal act has been adopted in Alabama, unless otherwise noted,”Kruger, 82......
-
Board of Com'Rs v. Bill Harbert Constr. Co.
...the contracts that excuses Harbert's future performance, and bars the Board's Counterclaim for completion costs. Federal Ins. Co. v. I. Kruger, Inc., 829 So.2d 732 (Ala.2002) (where contractor prevented subcontractor from performing under subcontract, subcontractor was excused from performa......
-
Subcontractors and Suppliers
...doubt. 66. See, e.g. , Main Elec., Ltd. v. Printz Servs. Corp . , 980 P.2d 522 (Colo. 1999); Federal Ins. Co. v. I. Kruger, Inc ., 829 So. 2d 732 (Ala. 2002). 67. See G.E.I. Recycling, Inc. v. Atl. Envtl., Inc., 821 So. 2d 431 (Fla. Dist. Ct. App. 2002); Lafayette Steel Erectors, Inc. v. Ro......
-
Subcontractors and Suppliers
...doubt. 66. See, e.g. , Main Elec., Ltd. v. Printz Servs. Corp . , 980 P.2d 522 (Colo. 1999); Federal Ins. Co. v. I. Kruger, Inc ., 829 So. 2d 732 (Ala. 2002). 67. See G.E.I. Recycling, Inc. v. Atl. Envtl., Inc., 821 So. 2d 431 (Fla. Dist. Ct. App. 2002); Lafayette Steel Erectors, Inc. v. Ro......