F. D. Borkholder Co., Inc. v. Sandock

Decision Date12 December 1980
Docket NumberNo. 1280S450,1280S450
Citation413 N.E.2d 567,274 Ind. 612
PartiesF. D. BORKHOLDER COMPANY, INC., Appellant (Defendant below), v. Melvin SANDOCK, Betty Sandock, Sam Sandock, Ruby Sandock and B. & S. Sandock, Inc., Appellees (Plaintiffs below).
CourtIndiana Supreme Court

Sam Mirkin, South Bend, for appellant.

Myron J. Hack, Myron J. Hack & Associates, South Bend, for appellees.

HUNTER, Justice.

This case is before this Court upon the petition to transfer of plaintiffs-appellees B. & S. Sandock, Inc., et al. The trial court awarded the plaintiffs compensatory and punitive damages arising out of a breach of contract by the defendant-appellant F. D. Borkholder Company, Inc. The Court of Appeals, Third District, affirmed the award of compensatory damages but reversed the punitive damages award in an opinion authored by Judge Staton. Sandock v. F. D. Borkholder Co., (1979) Ind.App., 396 N.E.2d 955. Judge Garrard dissented from the majority's treatment of the punitive damages issue.

Transfer is now granted, and the decision and opinion of the Court of Appeals are hereby vacated. The relevant facts were summarized by Judge Staton as follows:

"B. & S. Sandock, Inc. (Sandock) and F. D. Borkholder Company, Inc. (Borkholder), entered into a contract for the construction by Borkholder of a concrete block addition to Sandock's pre-existing structure. The addition was to be used as a retail showroom and warehouse in furtherance of Sandock's furniture and carpet business. Sandock was unable to use the addition for its intended use, however, because of a recurring moisture problem on the inside of one of the walls. Sandock filed suit seeking both compensatory and punitive damages. After trial by the court, Sandock was awarded compensatory damages in the amount of $8,711.69 and punitive damages in the amount of $6,500.00."

On appeal, Borkholder contended that:

1. The judgment was not supported by sufficient evidence;

2. The trial court erred in not granting Borkholder's motion for an involuntary dismissal; and

3. The trial court erred in awarding punitive damages.

We adopt the opinion of the Court of Appeals which affirms the trial court on the first two issues, as follows:

"I.

"Sufficiency of the Evidence

"Borkholder's argument with respect to the sufficiency of the evidence is twofold. First, Borkholder argues that because Sandock has been able to use certain areas of the addition for storage, Sandock was not damaged at all. This argument is without merit. Because of the unsightliness of one of the walls, Sandock was not able to use the addition as a showroom. Because of the dampness, Sandock was only able to use part of the addition for storage. Additionally, the useful life of the addition was less than it would have been had the construction proceeded pursuant to the plans and specifications embodied in the contract. Sandock proved that it had been damaged.

"Borkholder's second attack on the sufficiency of the evidence concerns testimonial conflicts as to the cause of the moisture problem. Several witnesses testified that the moisture problem was not attributable to Borkholder's work, while others testified that it was. Borkholder maintains that because of that conflict, the judgment was not supported by sufficient evidence. In propounding this argument, Borkholder has misconstrued the trial court's function as the finder of facts and our function as a court of appellate review. The case was heard below without the intervention of a jury. Accordingly, it was the function of the trial court to weigh the evidence and assess credibility in an effort to resolve the factual disputes. When, as here, the sufficiency of the evidence is raised as an issue on appeal, our function is to determine if there is substantial evidence of probative value to support the judgment based on an examination of the evidence most favorable to the party that prevailed below together with the reasonable inferences that can be drawn therefrom. Peters v. Davidson, Inc., (1977), Ind.App., 359 N.E.2d 556. Such an examination in the instant case discloses that the judgment is supported by sufficient evidence.

"II.

"Involuntary Dismissal

"At the close of Sandock's case-in-chief, Borkholder moved for an involuntary dismissal. Involuntary dismissals are provided for in TR. 41(B), which reads in pertinent part as follows:

" 'After the plaintiff or party with the burden of proof upon an issue, in an action tried by the court without a jury, has completed the presentation of his evidence thereon, the opposing party, without waiving his right to offer evidence in the event the motion is not granted, may move for a dismissal on the ground that considering all the evidence and reasonable inferences therefrom in favor of the party to whom the motion is directed, to be true, there is no substantial evidence of probative value to sustain the material allegations of the party against whom the motion is directed. The court as trier of the facts may then determine them and render judgment against the plaintiff or may decline to render any judgment until the close of all the evidence ....'

"Borkholder contends that there was no substantial evidence of probative value concerning the amount of the damages that were incurred by Sandock and that the trial court therefore erred in not granting the motion. 2 (Footnote 1 is omitted.) "Sandock offered testimony from which the trial court could reasonably have concluded that the addition was not suitable for the purposes contemplated by the contract. Sandock offered further testimony that the amount required to remedy the defects would be slightly in excess of $17,000. There was, therefore, sufficient evidence to overcome Borkholder's motion for an involuntary dismissal."

The Court of Appeals also determined that Borkholder's contention that the judgment was contrary to law was waived for failing to comply with Ind.R.Ap.P. 8.3(A)(7) and denied Sandock's request for an assessment of damages against Borkholder pursuant to Ind.R.Ap.P. 15(G) for bringing a frivolous appeal. We concur in those dispositions.

III.

Punitive Damages

The Court of Appeals cited our decision in Hibschman Pontiac, Inc. v. Batchelor, (1977) 266 Ind. 310, 362 N.E.2d 845, for the proposition that punitive damages are recoverable in breach of contract actions only when a separate tort accompanies the breach or tort-like conduct mingles in the breach. Here, prior to the execution of the contract, Sandock representatives expressed their concern about moisture on the walls. Under the terms of the contract, they were to pay $200 for plans to be drawn up by Borkholder's architect. The contract provided that all labor and material would be furnished in accordance with specifications. Sandock was given a copy of the plans. However, contrary to these plans, the top and bottom courses of block forming the one wall were not filled with concrete, thus constituting latent variances. Furthermore, the roofline was shortened which represented an additional deviation from the plans.

There was testimony that the cut-off roofline enabled water to leak down into the top of the block wall. Other evidence indicated that the wetness problem resulted from this water percolating down through the inside of the wall, collecting at the bottom, and then rising again by capillary action. Sandock made numerous complaints but was constantly reassured by several Borkholder representatives that the problem was caused by simple condensation, a theory ultimately disproved by an on-site test conducted by the Borkholder firm. Sam Sandock testified that Freeman Borkholder, president of the company, promised that the situation would be remedied whereupon Sandock tendered all but $1,000 of the contract price. The problem was never corrected. The Borkholder people knew, of course, that the blocks in the wall were not filled with concrete. Also, Borkholder himself conceded that the roofline adjustment increased the likelihood of water running down into the core of the wall.

We believe that there is cogent and convincing proof that the Borkholder firm engaged in intentional wrongful acts constituting fraud, misrepresentation, deceit, and gross negligence in its dealings with Sandock. Hibschman Pontiac, Inc., supra. Accordingly we agree with the Court of Appeals that the trial court could have concluded that separate torts accompanied the breach. Next, relying on Hibschman, the Court of Appeals attempted to identify the public interest to be served by imposing punitive damages. However, the majority could not perceive any such interest and refused to let the award stand. We disagree. As Ju...

To continue reading

Request your trial
30 cases
  • In re Tomsic
    • United States
    • U.S. Bankruptcy Court — Northern District of Indiana
    • March 19, 1987
    ...in breaching his contract also independently establishes the elements of common law tort in the case of F.D. Borkholder Co. Inc. v. Sandock, 274 Ind. 612, 413 N.E.2d 567 (Ind.App.1980). See also, Art Hill Ford v. Callander, 423 N.E.2d 601 (Ind. 1981). The Plaintiffs also pointed out that th......
  • Miller Brewing Co. v. Best Beers of Bloomington, Inc.
    • United States
    • Indiana Supreme Court
    • February 11, 1993
    ...(1982), Ind., 442 N.E.2d 349, 362; Art Hill Ford, Inc. v. Callender (1981), Ind., 423 N.E.2d 601, 602; F.D. Borkholder Co., Inc. v. Sandock (1980), 274 Ind. 612, 616, 413 N.E.2d 567, 570; Hibschman Pontiac, Inc. v. Batchelor (1977), 266 Ind. 310, 314, 362 N.E.2d 845, 847; Vernon Fire & Casu......
  • Western Smelting & Metals v. Slater Steel, Inc.
    • United States
    • U.S. District Court — Northern District of Indiana
    • November 12, 1985
    ...damages may be awarded for the tort." Art Hill Ford, Inc. v. Callender, 423 N.E.2d 601, 602 (Ind. 1981); F.D. Borkholder Co., Inc. v. Sandock, 274 Ind. 612, 413 N.E.2d 567 (1980); Hibschman Pontiac v. Batchelor, 266 Ind. 310, 362 N.E.2d 845 (1977). Even if an independent tort cannot be esta......
  • Tacket v. General Motors Corp. Delco Remy Div., IP 89 162-C.
    • United States
    • U.S. District Court — Southern District of Indiana
    • February 26, 1993
    ...(1982), Ind., 442 N.E.2d 349, 362; Art Hill Ford, Inc. v. Callender (1981), Ind., 423 N.E.2d 601, 602; F.D. Borkholder Co., Inc. v. Sandock (1980), 274 Ind. 612, 616, 413 N.E.2d 567, 57- sic; Hibschman Pontiac, Inc. v. Batchelor (1977), 266 Ind. 310, 314, 362 N.E.2d 845, 847; Vernon Fire & ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT