First Federal State Bank v. Town of Malvern, 2-61248

Decision Date18 October 1978
Docket NumberNo. 2-61248,2-61248
Citation270 N.W.2d 818
Parties25 UCC Rep.Serv. 560 FIRST FEDERAL STATE BANK, Appellee and Cross-Appellant, v. The TOWN OF MALVERN, John F. Kemp, Woodford Byington, N. D. Pierce, Douglas Burchett, Temple Bowers, LeRoy Viner, and Dale L. Stephens, Defendants. TOWN OF MALVERN, Cross-Petitioner, v. UNITED STATES FIDELITY & GUARANTY COMPANY, Appellant and Cross-Appellee.
CourtIowa Supreme Court

Lyle W. Ditmars and Peter J. Peters, of Peters, Campbell & Pearson, P. C., Council Bluffs, for appellant and cross-appellee.

James L. Sayre, of Dreher, Wilson, Adams & Jensen, Des Moines, for appellee and cross-appellant.

Considered en banc.

ALLBEE, Justice.

This is a contest between the surety of a contractor who defaulted in the performance of a public construction project and the bank to which the contractor assigned its contract rights. The prize is a fund consisting of the remainder of progress payments which the contractor had earned but had not received and certain retained percentages.

The parties have stipulated to the facts. On August 29, 1972 the Town of Malvern contracted with South Pacific Pools, Inc. to build a swimming pool for $79,480. Pursuant to the requirements of chapter 573, The Code, United States Fidelity and Guaranty Company became surety for the contractor by providing performance and payment bonds dated August 29. First Federal State Bank entered into security agreements with the contractor on November 9, 1972 and July 13, 1973, taking assignments of the contractor's contract rights, accounts and proceeds arising out the Malvern pool contract. The associated financing statements were filed on October 16, 1972 and July 16, 1973. Notice of the second assignment was given to the town on July 13, 1973.

On August 29, 1972 the contractor began performing the contract. As performance progressed, payments were made, and a percentage of the earned money was retained, according to the provisions of § 573.12, The Code. That section provides:

Payments made under contracts for the construction of public improvements, unless provided otherwise by law, shall be made on the basis of monthly estimates of labor performed and material delivered. In making said payments, there shall be retained ten percent of each said monthly estimate by the public corporation; provided, however, that if the contract is for more than fifty thousand dollars and if the public corporation at any time after fifty percent of the improvement has been completed finds that satisfactory progress is being made, the public corporation may authorize any of such remaining payments to be made in full.

Through July 4, 1973, the town had paid $53,985 on the contract. The contractor had earned another progress payment of $5829, but that payment had not been made prior to default on August 6, 1973. After default, the surety and the town entered into an "Agreement on Contract Funds." The surety then completed the project at a total cost of $65,385.40 and the town paid certain unspecified claims of $4747. After completion the town paid $10,248 to the surety. All parties agreed that the town was entitled to keep $4747 as reimbursement for the claims it paid. Thus $10,500 was left, that amount being the contract price ($79,480) less the following: (1) the amount paid to the contractor before default ($53,985); (2) the amount paid to the surety after completion ($10,248); and (3) the amount set off to the town ($4747). This remaining fund is the subject of dispute. The town paid the $10,500, to which it made no claim, into the clerk of court, leaving only the bank and the surety as parties to this controversy.

The bank claimed the remaining fund as the assignee of the contractor's rights in the contract. The surety made claim to the fund solely on the theory that it is subrogated to the rights of the town because it completed the project and expended a sum far in excess of the amount now in controversy. Trial court awarded $5829 to the bank because that amount was due the contractor prior to default. The remaining $4671 was found to be the balance of the funds retained under § 573.12, The Code, for payment of material and labor claims and was therefore awarded to surety. From that judgment the surety appealed and the bank cross-appealed.

It is first necessary to establish what is and is not involved in this case. The surety has the possibility of assuming several different roles, for, as was pointed out by the leading case, National Shawmut Bank v. New Amsterdam Cas. Co., 411 F.2d 843, 845 (1st Cir. 1969):

(T)he surety in cases like this undertakes duties which entitle it to step into three sets of shoes. When, on default of the contractor, it pays all the bills of the job to date and completes the job, it stands in the shoes of the contractor insofar as there are receivables due it; in the shoes of laborers and material men who have been paid by the surety who may have had liens; and, not least, in the shoes of the government, for whom the job was completed.

Here, the surety asserts only its rights as subrogee to the town. See Toll v. Toll, 201 Iowa 38, 41, 206 N.W. 117, 118 (1925); See also Ohio Cas. Co. v. Galvin, 222 Iowa 670, 672, 269 N.W. 254, 256 (1936).

Because the surety does not claim as subrogee to the contractor's rights, Monona County v. O'Connor, 205 Iowa 1119, 1125-26, 215 N.W. 803, 806 (1927) does not apply. That case placed the surety, by its right of subrogation to its principal's rights, prior to the claim of the contractor's assignee who had rented horses and equipment to the contractor.

Nor does the surety base its claim on the rights it has as subrogee to the claims of laborers and materialmen. Therefore, Hercules Mfg. Co. v. Burch, 235 Iowa 568, 16 N.W.2d 350 (1944) and Sinclair Refining Co. v. Burch, 235 Iowa 594, 16 N.W.2d 359 (1944) have no direct application. The surety in those cases relied entirely upon its rights as subrogee to laborers and materialmen, without asserting any rights as subrogee of the owner. Hercules, 235 Iowa at 578, 16 N.W.2d at 355.

The surety makes no claim under any assignment which might be included in either bond. Therefore, we find no assistance in Coon River Co-op Sand Assoc. v. McDougall Const. Co., 215 Iowa 861, 244 N.W. 847 (1932), which subordinated the assignee-surety to the assignee-bank because the surety's assignment was conditioned on the contractor's breach and therefore attached after the bank's assignment.

Finally, no one contends that priorities are governed by Article 9 of the Uniform Commercial Code (UCC). It seems to be settled in other jurisdictions that Article 9 does not govern where a surety asserts subrogation rights. See, E. g., Canter v. Schlager, 358 Mass. 789, 267 N.E.2d 492 (1971); Jacobs v. Northeastern Corp., 416 Pa. 417, 206 A.2d 49 (1965).

Article 9 of the UCC is not entirely irrelevant, however, for the bank's assignment is a perfected security interest. The bank's position is thus defined by § 554.9318(1)(a), The Code. Its rights are essentially the same as what existed under prior law. See Associates Discount Corp. v. Goetzinger, 245 Iowa 326, 62 N.W.2d 191 (1954); Monona County v. O'Connor, 205 Iowa 1119, 1125-26, 215 N.W. 803, 806 (1927). That is to say that the assignee acquired only such rights as the contractor had in the fund. "The claims of the assignee are no higher or greater than those of the contractor." Monona County, 205 Iowa at 1126, 215 N.W. at 806.

An examination of the parties' positions in light of the foregoing discussion indicates that, when stripped to its essentials, this dispute may be resolved as though it involved the town against the contractor. Having established the boundaries of the contest, we now turn to the parties' specific complaints.

I. The Bank's Cross-Appeal.

Because the issue raised by the cross-appeal is relatively simple, we take up this subject first. The bank asserts it has a right to the entire $10,500 fund, even including the portion beyond that which was made up of earned but unpaid progress payments. In other words, the bank is attempting to collect money which the contractor has not earned. Relying upon Sinclair Refining Co. v. Burch, 235 Iowa 594, 16 N.W.2d 359 (1944), which holds that only the 10% Retainage fund is available for payments to laborers and materialmen, the bank points out that the surety has already received more than 10% Of the entire contract price. Therefore, the bank reasons, it must be entitled to everything else. This argument fails to take into account the rights of the...

To continue reading

Request your trial
5 cases
  • Accurate Controls, Inc. v. Cerro Gordo County Bd., C 08-3021-MWB.
    • United States
    • U.S. District Court — Northern District of Iowa
    • June 18, 2009
    ...a subcontractor. Accurate also points out that, in a fourth— and earlier—case not cited by the defendants, First Federal State Bank v. Town of Malvern, 270 N.W.2d 818, 822 (Iowa 1978), the Iowa Supreme Court expressly held that § 573.15 "refers only to the claims of Accurate also argues t......
  • Matter of Don's Elec., Inc.
    • United States
    • U.S. Bankruptcy Court — Western District of Wisconsin
    • July 23, 1986
    ...Gould, supra, 257 Wis. at 112-13. See also Allison v. Manzke, 118 Wis. 11, 94 N.W. 659, 662 (1903). Accord First Federal State Bank v. Town of Malvern, 270 N.W.2d 818 (Iowa 1978) (bank to which a defaulting contractor had assigned its rights prior to default acquired only such rights as the......
  • Employers Mut. Cas. v. United Fire & Cas.
    • United States
    • Iowa Court of Appeals
    • February 11, 2004
    ...the bond. Granite Computer Leasing Corp. v. Travelers Indem. Co., 894 F.2d 547, 551 (2d Cir.1990); see also First Fed. State Bank v. Town of Malvern, 270 N.W.2d 818, 819 (Iowa 1978) (noting surety had completed the project after principal defaulted); Winnebago County State Bank v. Davidson,......
  • Lennox Industries, Inc. v. City of Davenport
    • United States
    • Iowa Supreme Court
    • June 16, 1982
    ...In our two most recent chapter 573 cases, Dobbs v. Knudson, Inc., 292 N.W.2d 692, 695 (Iowa 1980), and First Federal State Bank v. Town of Malvern, 270 N.W.2d 818, 820 (Iowa 1978), we have looked to the federal Miller Act cases. That Act, 40 U.S.C. §§ 270a--d (1976 & Supp. IV 1980), is the ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT