Flagstaff Enterprises Const. Inc. v. Snow

Decision Date09 November 1995
Docket NumberNo. 94CA1205,94CA1205
Citation908 P.2d 1183
PartiesFLAGSTAFF ENTERPRISES CONSTRUCTION, INC., Plaintiff-Appellee, v. Theodore P. SNOW and Constance M. Snow, Defendants-Appellants. . IV
CourtColorado Court of Appeals

Hutchinson Black & Cook, L.L.C., C. Brad Peterson, Boulder, for Plaintiff-Appellee.

Stone, Sheehy, Rosen & Byrne, P.C., Andrew Rosen, Boulder, for Defendants-Appellants.

Opinion by Judge NEY.

In this construction contract dispute, defendants, Theodore P. and Constance M. Snow (owners), appeal the judgment entered after a trial to the court in favor of plaintiff, Flagstaff Enterprises Construction, Inc. (builder). We affirm.

The parties entered into an oral agreement for builder to sell the owners land and build a home for them on the land. It is undisputed that the original price of the land and the home was $210,000, which later increased to $215,020. It is also undisputed that owners paid a portion of the total purchase price and that the parties orally agreed that the owners would pay the balance over a thirty-year period. However, the parties dispute the amount of the final purchase price and the amount of the unpaid balance.

Builder brought this action when owners ceased making payments on the balance. Owners asserted, as an affirmative defense, a setoff related to an allegedly defective roof.

At trial, builder introduced testimony that owners requested construction changes totalling an additional $18,900, thus increasing the total purchase price from $215,020 to approximately $234,000. Builder introduced evidence that the parties orally agreed that there was an unpaid balance due builder of $30,000, which would be paid over thirty years at 10% interest, with monthly payments of $275. Builder's evidence included a thirty-year amortization schedule hand-written by owner Theodore Snow showing a beginning balance of $30,000, as well as copies of owners' monthly checks to builder, or its assignee, showing uniform payments for five years in accordance with this amortization schedule.

Builder presented evidence that it had received $187,890 of the price from the owners' bank and a $15,000 payment directly from the owners, for a total of $202,890. Builder also testified that the parties agreed the unpaid balance was $30,000 after the owners had made the $15,000 payment. Builder testified that the total amount owed by owners, with unpaid interest, was $34,000.

Owners testified that the final price did not increase above $216,000. They disputed there were changes that increased the price of the home, stating that some of the changes described by builder had been included in the original plans for the home. They also testified that they had paid for some of the contract items themselves.

The owners acknowledged they had agreed with builder that there was an unpaid balance of $30,000. However, they testified they made this agreement in the belief that they had only paid $185,000 at that time. They testified that after the parties reached the amortization agreement relating to the $30,000 balance, they made a lump sum pre-payment of $15,000 towards this balance. They also testified that seven years after this agreement, they concluded they had paid for the home's building permit at the start of construction, which reduced their unpaid balance by $16,000. They testified that this reduction, together with the payment of $15,000, left no unpaid balance.

After a bench trial, the trial court found that the purchase price had increased to $234,000 because of construction changes requested by the owners and that the owners had only paid builder $202,890. The trial court found that the parties had taken these figures into account when they agreed the unpaid balance was $30,000. Thus, the trial court ruled that the owners breached their agreement to make monthly payments on the $30,000 balance and owed builder $34,722.40.

I.

The owners contend the trial court's finding that owners had paid builder only $202,890.07 was contrary to the undisputed evidence. We disagree.

There is a presumption that a judgment entered by the trial court is correct. Colorado National Bank--Boulder v. Zerobnick & Sander, P.C., 768 P.2d 1276 (Colo.App.1989).

The trial court's determination of the sufficiency, probative effect, and weight of the evidence, as well as the credibility of the witnesses must be accepted on appeal unless the findings are so clearly erroneous as not to find...

To continue reading

Request your trial
23 cases
  • First Interstate Bank of Denver, N.A. v. Central Bank & Trust Co. of Denver
    • United States
    • Colorado Court of Appeals
    • August 22, 1996
    ...issue on appeal when argument in trial court gives notice on what basis the party is defending); cf. Flagstaff Enterprises Construction, Inc. v. Snow, 908 P.2d 1183 (Colo.App.1995) (statute of limitations first raised in post-trial motion not addressed on appeal since other party unable to ......
  • Perfect Place, Ltd. v. Semler
    • United States
    • Colorado Court of Appeals
    • October 20, 2016
    ...compliance under § 38–33.3–213(2)(d) and (e), C.R.S. 2016, we need not address these provisions. See Flagstaff Enters. Constr. Inc. v. Snow , 908 P.2d 1183, 1185 (Colo. App. 1995) (declining to address an issue not properly raised on appeal).7 We also note that the dimensions for space E in......
  • Grohn v. Sisters of Charity Health Services Colorado
    • United States
    • Colorado Court of Appeals
    • May 28, 1998
    ...to respond, and the trial court made no findings or conclusions with respect to that contention. See Flagstaff Enterprises Construction, Inc. v. Snow, 908 P.2d 1183 (Colo.App.1995). It is not dispositive that defendants did not designate the argument as a Supremacy Clause argument. It is su......
  • Patterson v. BP Am. Prod. Co.
    • United States
    • Colorado Court of Appeals
    • March 12, 2015
    ...do not challenge that ruling on appeal. Therefore, we need not address the discovery request. SeeFlagstaff Enters. Constr. Inc. v. Snow,908 P.2d 1183, 1185 (Colo. App. 1995)(declining to address an issue not properly raised on appeal).5 Fraudulent concealment also requires that the plaintif......
  • Request a trial to view additional results
3 books & journal articles
  • RULE 59
    • United States
    • Colorado Bar Association C.R.S. on Family and Juvenile Law (2022 ed.) (CBA) Colorado Rules of Civil Procedure
    • Invalid date
    ...that issues will not be considered when raised for the first time in reply briefs on appeal. Flagstaff Enters. Constr. Inc. v. Snow, 908 P.2d 1183 (Colo. App. 1995). Court may limit issues to be retried. When error exists as to only one or more issues and the judgment is in other respects f......
  • COLORADO RULES OF CIVIL PROCEDURE
    • United States
    • Colorado Bar Association C.R.S. on Family and Juvenile Law (CBA) Colorado Rules of Civil Procedure
    • Invalid date
    ...that issues will not be considered when raised for the first time in reply briefs on appeal. Flagstaff Enters. Constr. Inc. v. Snow, 908 P.2d 1183 (Colo. App. 1995). Court may limit issues to be retried. When error exists as to only one or more issues and the judgment is in other respects f......
  • Rule 59 MOTIONS FOR POST-TRIAL RELIEF.
    • United States
    • Colorado Bar Association Colorado Rules of Civil and Appellate Procedure (CBA)
    • Invalid date
    ...that issues will not be considered when raised for the first time in reply briefs on appeal. Flagstaff Enters. Constr. Inc. v. Snow, 908 P.2d 1183 (Colo. App. 1995). Court may limit issues to be retried. When error exists as to only one or more issues and the judgment is in other respects f......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT