Flooring Systems, Inc. v. Staat Const. Co.

Decision Date11 February 2003
Docket NumberNo. ED 80867.,No. ED 80814.,ED 80814.,ED 80867.
Citation100 S.W.3d 835
PartiesFLOORING SYSTEMS, INC., Plaintiff, v. STAAT CONSTRUCTION COMPANY, Respondent/Cross-Appellant, and DLJ Properties, Appellant/Cross-Respondent.
CourtMissouri Court of Appeals

Steven M. Cockriel, St. Louis, MO, for Plaintiff/Respondent/Cross-Appellant.

Craig A. Smith, St. Louis, MO, for Appellant.

GEORGE W. DRAPER III, Judge.

DLJ Properties, Inc. (hereinafter, "DLJ") appeals from the trial court's judgment in favor of Staat Construction Company (hereinafter, "Staat"), and Staat cross-appeals. Following a bench trial, neither party believes that the trial court correctly awarded damages arising from a construction project. Staat also filed a motion to dismiss the trial court's judgment for lack of finality which was taken with the case. We deny the motion taken with the case and affirm the trial court's judgment.

Facts

Daniel L. Jones (hereinafter, "Jones") is the sole owner of an accounting firm. Staat was a client of the accounting firm. Jones decided to build a new office complex to house his firm and lease space to other tenants. After conducting feasibility assessments, Jones began to develop the office complex through DLJ.

DLJ purchased the property for development on December 1, 1997. DLJ secured a loan for $1,681,098.64 for construction of the buildings and site improvements. On February 10, 1998, DLJ executed a contract with Staat for construction on the property with a guaranteed maximum price of $1,600,252.00 pursuant to Exhibit "A" of the contract, which was a series of cost estimates for various phases and subparts of the contract. The abstract planning of the overall site included buildings, parking, utilities, common, areas, and a "white box" finish.1 Additionally, there was $80,000.00 built into the contract for unforeseen contingencies.

Construction began in February 1998 with Staat performing the work or arranging for and supervising all subcontractors. Jones and Staat met regularly to discuss the progress of the project. During these discussions, there were changes made in the original plans addressing issues which arose as the project proceeded. Some of their discussions included changes in the handling of the storm water run-off and detention, the grading on the site, parking, retaining wall, quality of the brick, use of aluminum soffit, and tenant-finishing issues.

As the project neared completion, Jones's accounting firm and several tenants moved into the building. On December 15, 1998, Staat sent DLJ a letter advising that the project had exceeded the original contract budget and summarized the final invoice. As their disputes became irreconcilable, Jones declined to pay more of the costs, and Staat declined to continue work on the project.

Jones acquired a line of credit in order to pay for the remainder of the work to be completed. Eventually, several unpaid subcontractors filed mechanic's liens against DLJ. This suit was commenced by Flooring Systems, Inc. to enforce its lien, and joined by other subcontractors. The subcontractor liens were adjudicated by summary judgment; thus, only DLJ and Staat's claims remain.

DLJ seeks reimbursement of the mechanic lien judgments. Staat seeks payment for the cost of items it claims were agreed to and not covered by the contract. The trial court heard all of the evidence and issued its comprehensive judgment. DLJ was awarded $148,279.00 for the cost of the foundation plus $20,951.00 from the Sauder Plumbing lien and interest, if there is no appeal. Staat was awarded a total of $154,831.06 for "extras" not listed in Exhibit "A," changes, and its construction manager's fee. This appeal and cross-appeal follow.

Motion

As a preliminary matter, on the morning of oral argument, Staat filed with this Court a motion to dismiss the appeal for lack of a final judgment. Staat claims that the trial court no longer retains jurisdiction to modify its judgment regarding the Sauder Plumbing lien. The trial court's judgment reads, "Depending on the outcome of the Sauder Plumbing lien appeal, this judgment may be amended accordingly, without affecting any appeal of the issues in this trial." The trial court's judgment entered a specific award as to the Sauder Plumbing lien which should be entered if there was no appeal regarding that lien. Pursuant to 84.14, this Court shall dispose of the case by making the award for the Sauder Plumbing lien final since there is no appeal pending. The motion taken with the case is denied.

Standard of Review

We will affirm the trial court's award unless there is no substantial evidence to support it, it is against the weight of the evidence, or it erroneously declares or applies the law. Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. banc 1976). Upon review, we accept evidence and inferences that are consistent with the findings of the trial court and disregard all contrary evidence. Artilla Cove Resort, Inc. v. Hartley, 72 S.W.3d 291, 293 (Mo.App. S.D. 2002). This Court defers to the trial court's superior ability to assess the credibility of witnesses. Kassebaum v. Kassebaum, 42 S.W.3d 685, 692 (Mo.App. E.D. 2001). "In a court-tried case, the judgment is presumptively correct, and the appellant has the burden to demonstrate that the judgement is erroneous." Roark Printing, Inc. v. Worm World, Inc., 974 S.W.2d 613, 616 (Mo.App. S.D.1998).

Direct Appeal

In its first point on appeal, DLJ claims that the trial court erred in granting judgment on Staat's cross claim for "extras"2 because Staat had released all claims for work performed prior to September 15, 1998. DLJ believes that all of the "extras" for which Staat recovered were covered by the release of September 15, 1998, and the "extras" were complete at that time. Staat was awarded a judgment on the carport, storm sewers, and stairs.

DLJ states that the work for the "extras" was completed prior to the dated release, and hence, it should not be required to pay any additional amount. "In general, the presumption is that executed releases are valid." City of Kansas City v. Southwest Tracor Inc., 71 S.W.3d 211, 215 (Mo.App. W.D.2002). Upon this Court's review of the September 15, 1998 release, there is no obvious listing for the carport or the stairs. There is a listing for the storm sewer, but the listing is not for the amount which the trial court awarded Staat. After reviewing the exhibits, we note that Staat submitted its final invoice to DLJ on April 30, 1999. In that invoice, Staat listed the amount owed for the storm sewers was $67,542.06, the same amount as the trial court's judgment, and the invoice stated that the sewer detention structure was not complete nor was the final cost included in the balance of the invoice.

When...

To continue reading

Request your trial
10 cases
  • Tribus, LLC v. Greater Metro, Inc.
    • United States
    • Missouri Court of Appeals
    • November 19, 2019
    ...correct, and the appellant has the burden to demonstrate that the judgment is erroneous." Flooring Sys., Inc. v. Staat Constr. Co. , 100 S.W.3d 835, 837 (Mo. App. E.D. 2003) (internal quotations omitted). "Even if we find error, we cannot reverse the judgment unless we determine that the er......
  • Parkway Constr. Servs., Inc. v. Blackline LLC
    • United States
    • Missouri Court of Appeals
    • March 26, 2019
    ...to support it, it is against the weight of the evidence, or it erroneously declares or applies the law." Flooring Svs. v. Staat Constr. Co., 100 S.W.3d 835, 837 (Mo. App. E.D. 2003) (citing Murphy, 536 S.W.2d at 32 ), "In a court-tried case, the judgment is presumptively correct, and the ap......
  • Clippard v. Pfefferkorn, ED 85111.
    • United States
    • Missouri Supreme Court
    • August 30, 2005
    ...it is against the weight of the evidence, or it erroneously declares or applies the law. Flooring Sys., Inc. v. Staat Const. Co. and DLJ Properties, 100 S.W.3d 835, 837 (Mo.App. E.D.2003), citing Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. banc 1976). We do not retry the case but accept as tru......
  • N.M.O. v. D.P.O.
    • United States
    • Missouri Court of Appeals
    • July 15, 2003
    ...light most favorable to the trial court's decision, and disregard all contrary evidence and inferences. Flooring Sys., Inc. v. Staat Constr. Co., 100 S.W.3d 835, 837 (Mo.App. E.D.2003); Fisk, 81 S.W.3d at 1. "The credibility of witnesses and the weight to be given their testimony is a matte......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT