Forman v. Federal Emergency Management Agency, 97-30473

Decision Date09 March 1998
Docket NumberNo. 97-30473,97-30473
PartiesRoland FORMAN, Etc., et al., Plaintiffs, Roland Forman, husband of Rosemary Forman, Plaintiff-Appellant, v. FEDERAL EMERGENCY MANAGEMENT AGENCY, James Lee Witt, Director, Defendant-Appellee. Summary Calendar.
CourtU.S. Court of Appeals — Fifth Circuit

Jim S. Hall, Metairie, LA, for Plaintiff-Appellant.

Marc Philip Richman, William Kanter, U.S. Dept. of Justice, Civ. Div., App. Staff, Washington, DC, for Defendant-Appellee.

Appeal from the United States District Court for the Eastern District of Louisiana.

Before JONES, SMITH and STEWART, Circuit Judges.

STEWART, Circuit Judge:

After their southern Louisiana home was damaged by severe floods in May of 1995, appellants Roland Forman and Rosemary Forman pursued a claim for flood damages with the Federal Emergency Management Agency ("FEMA") under their FEMA-written Standard Flood Insurance Policy ("SFIP"). When their claim was denied for failure to file a Proof of Loss in a timely manner, appellants sued. The district court--faced with FEMA's unopposed motion to dismiss or, in the alternative, motion for summary judgment--entered judgment in favor of FEMA on January 14, 1997. Appellants subsequently filed a motion for a new trial, which the district court denied on the ground that appellants' filing of the Proof of Loss, even if timely, was inadequate. 1 Appellants contest the judgment of the district court, and we affirm. 2

Appellants contend that the Proof of Loss they proffered on December 5, 1995, was sufficient to allow FEMA an opportunity to evaluate the merits of their claim, and therefore the district court erred in finding the Proof of Loss to be inadequate. Under FEMA regulations, 3 strict adherence is required to all terms of the SFIP. 44 C.F.R. §§ 61.13(a), (d), (e). The SFIP, as set forth in the regulations, 4 provides that within 60 days after the loss (or within any extension authorized by FEMA), the claimant must file a signed and sworn Proof of Loss listing, inter alia, (1) "the actual cash value ... of each damaged item of insured property ... and the amount of damages sustained," and (2) "the amount ... claim[ed][as] due under [the] policy to cover the loss...." Id.; 44 C.F.R. Pt. 61 App. A(1), Art. IX, p J(3).

Although we have serious reservations about whether appellants' filing of the Proof of Loss was timely under the facts of this case, we do not decide this appeal on that basis. Rather, we uphold the district court's finding that appellants' Proof of Loss (assuming it was filed in a timely manner) was inadequate. By writing "THESE FIGURES ARE UNACCEPTABLE" next to the listed amounts, appellants in effect nullified any representations as to the "actual cash value loss" or "the net amount claimed" that these figures otherwise would have made. 5 See Rec. 13. Moreover, by failing to provide "acceptable" damage figures of their own, appellants did not provide any sworn information whereby FEMA could evaluate "the merits of their claim." Appellants' presumption that their claim could be processed in these circumstances is simply implausible, if not absurd.

Appellants contend in the alternative that FEMA should be estopped from asserting as a defense their failure to meet the Proof of Loss filing requirement. We disagree. Appellants' claim ignores the Supreme Court's recent holding, made under the Appropriations Clause of the Constitution, Art. I, § 9, cl. 7, that the judiciary is powerless to uphold an "an assertion of estoppel against the Government by a claimant seeking [money from the Public Treasury contrary to a statutory appropriation]." OPM v. Richmond, 496 U.S. 414, 434, 424, 110 S.Ct. 2465, 2476, 2471, 110 L.Ed.2d 387 (1990). The Court recognized that " 'not even the temptations of a hard case' will provide a basis for ordering recovery contrary to the terms of [a] regulation, for to do so would disregard 'the duty of all courts to observe the conditions defined by Congress for charging the public treasury.' " Richmond, 496 U.S. at 420, 110 S.Ct. at 2469 (quoting Federal Crop Ins. Corporation v. Merrill, 332 U.S. 380, 385-86, 68 S.Ct. 1, 3-4, 92 L.Ed. 10 (1947)) (emphasis added).

Payments awarded under FEMA-issued flood insurance policies are indeed "a direct charge on the public treasury." In re Estate of Lee, 812 F.2d 253, 256 (5th Cir.1987). FEMA, acting well within its statutory rule-making authority, 42 U.S.C. § 4013, has established that a claimant must file a Proof of Loss containing certain specified information before his claim may be considered. 44 C.F.R. Pt. 61 App. A(1), Art. IX, p J(3). As established above, appellants failed to satisfy this regulatory requirement in this case. In such circumstances, there can be no estoppel of the Proof of Loss requirement, for we cannot estop "the conditions defined by Congress for charging the public treasury." Richmond, 496 U.S. at 420, 110 S.Ct. at 2469 (quoting Merrill, 332 U.S. at 385-86, 68 S.Ct. at 3-4). Appellants, therefore, have not raised any genuine issues of material fact foreclosing judgment as a matter of law in FEMA's favor. The judgment of the district court is affirmed accordingly.

AFFIRMED.

1 The district court issued its order denying appellants' motion for new trial on April 18, 1997.

2 Appellants' Notice of Appeal purports to challenge the "final judgment" issued by the district court on April 18, 1997. As discussed above, the district court issued its judgment in favor of FEMA on January 14, 1997, not on April 18, 1997. The only action the district...

To continue reading

Request your trial
93 cases
  • Cole v. New Hampshire Ins.
    • United States
    • U.S. Bankruptcy Court — Northern District of Mississippi
    • 9 January 2012
    ...provide a signed and sworn Proof of Loss within 60 days after the loss, "or within any extension authorized by FEMA." Forman v. FEMA, 138 F.3d 543, 545 (5th Cir. 1998). The SFIP additionally plainly requires a claimant to provide certain information in the proof loss, including "[s]pecifica......
  • Eaker v. State Farm Fire and Cas. Ins. Co.
    • United States
    • U.S. District Court — Southern District of Mississippi
    • 17 September 2001
    ...fact "[u]nder FEMA regulations, strict adherence is required to all terms of [the] SFIP. 44 C.F.R. § 61.13(a), (d), (e)." Forman v. FEMA, 138 F.3d 543 (5th Cir.1998). See also Howard v. FEMA, 960 F.Supp. 1095 (S.D.Miss.1996).8 The Plaintiffs submit that State Farm should be estopped from as......
  • Jamal v. Travelers Lloyds of Texas Ins. Co.
    • United States
    • U.S. District Court — Southern District of Texas
    • 22 February 2001
    ...v. Aetna, 143 F.3d 951, 955 (5th Cir.1998) (quoting In re Estate of Lee, 812 F.2d 253, 256 (5th Cir. 1987)); accord Forman v. FEMA, 138 F.3d 543, 545 (5th Cir.1998). "Because flood losses, whether insured by FEMA or by a participating WYO insurer, are paid out of the National Flood Insuranc......
  • Bruinsma v. State Farm Fire and Cas. Co.
    • United States
    • U.S. District Court — Western District of Michigan
    • 23 January 2006
    ...of the Supreme Court's clear holding in the OPM case. See, e.g., Mancini, 248 F.3d at 735; Gowland, 143 F.3d at 955; Forman v. FEMA, 138 F.3d 543, 545-46 (5th Cir. 1998). In Gowland, the Fifth Circuit When federal funds are involved, the judiciary is powerless to uphold a claim of estoppel ......