Glover v. Lewis, 1344

Decision Date19 April 1989
Docket NumberNo. 1344,1344
Citation299 S.C. 44,382 S.E.2d 242
PartiesBobby GLOVER, Respondent, v. Harriett LEWIS, a/k/a Harriett W. Odom, American Savings and Loan Association, and Sanders Supply Company, Inc., Defendants, Of whom American Savings and Loan Association is Appellant. Appeal of AMERICAN SAVINGS AND LOAN ASSOCIATION. . Heard
CourtSouth Carolina Court of Appeals

Susanne A. Hawkins and Louis H. Lang, both of Callison, Tighe, Robinson & Anastasion, Columbia, for appellant.

W.D. Rhoad, Bamberg, for respondent.

CURETON, Judge:

The basic issue presented in this mechanic's lien foreclosure action is the kind of notice required to defeat the priority of a mortgage lien recorded subsequent to the accrual of an unrecorded mechanic's lien. The trial court held the notice sufficient to defeat the priority of the mortgage lien. The mortgagee appeals. We reverse.

The foreclosure of a mechanic's lien being a proceeding for the enforcement of a statutory lien is legal in nature. Adams v. B & D, Inc., 377 S.E.2d 315 (S.C.1989); Metz v. Critcher, 83 S.C. 396, 65 S.E. 394 (1909); Karl Sitte Plumbing Co., Inc. v. Darby Development Co. of Columbia, Inc., 295 S.C. 70, 367 S.E.2d 162 (Ct.App.1988). In a law case, this court will not disturb the trial judge's findings of fact unless found to be unsupported by the evidence. Southeastern PVC Pipe, Mfg., Inc. v. Rothrock Constr. Co., Inc., 280 S.C. 498, 313 S.E.2d 50 (Ct.App.1984). We review the facts against this standard.

In February 1985 Respondent Bobby Glover entered into a contract with homeowner, Harriet Lewis, to remodel her home. Glover began the remodeling job in March 1985 and prosecuted the job through October 1985. Materials for the job were obtained from Sanders Supply Company, Inc.

On May 28, 1985, Lewis mortgaged her home to Appellant American Savings and Loan Association's predecessor to secure the payment of a $25,000 loan. American recorded the mortgage on May 30, 1985.

On June 7, 1985, Sanders Supply filed a $25,088 mechanic's lien for materials furnished. 1 Thereafter, on December 23, 1985, Glover filed a mechanic's lien in the amount of $25,313 for labor provided the job.

Glover brought this action in March 1986 to foreclose his lien and sought priority of his mechanic's lien over American's mortgage lien. The case was referred to a special referee. At a hearing on the claim, Glover testified that after completing 50 to 60 percent of the job Lewis agreed to pay him and Sanders Supply some amount on "her bill". He further testified he drove Lewis to a mortgage company and waited while she completed loan paperwork. He testified a man subsequently came to the property and took pictures when the job was about 75 percent complete, but he did not talk to the man. Glover also testified a second man came to the job site when the job was about 80 to 85 percent complete and asked him when the job would be completed.

Dave Clayton, a Sanders Supply representative, testified he talked to American several times. He claims he initially called American during the summer of 1985 and was assured Lewis had applied for a loan. Clayton also recalled receiving a phone call from American when Lewis requested the lender call him "to assure [him] the check would be made jointly to Sanders Supply Company and to [Lewis]." He could not recall discussing with American the amount then due for outstanding materials.

Clayton recounted that in about his second conversation with American he was told the appraiser had been to the job, but the work had not progressed enough to "make the appraisal they wanted, and that [the appraiser] was going to have to return." He maintained the conversation must have included a discussion of the work in progress.

The special referee found Glover's lien took priority over American's mortgage even though the mortgage had been recorded first because "American had actual notice through its inspections and discussions of the work with Dave Clayton" and thus American cannot claim the protection of Section 30-7-10 of the recording statute.

On appeal, American argues the evidence is insufficient to show it had actual notice of Glover's claim. American asserts that neither the Clayton conversations nor the inspections provided actual notice of Glover's lien. The lender also contends it could not have had notice of Glover's lien when it filed its mortgage because the conversations between Clayton and American and the inspections occurred after the filing of its mortgage. It also argues the notice required to defeat its priority is actual notice of Glover's unrecorded mechanic's lien or his right to a lien, not just notice of the construction in progress. It reasons that since Glover's right to a lien is conditioned upon a debt due from Lewis to him, effective notice must include not only the fact that goods and materials were provided but also the fact that they had not been paid for.

A person who performs labor or furnishes materials in the erection, alteration, or repair of a structure or building and to whom a debt is due for such labor or materials is entitled, as security for payment of the debt, to a mechanic's lien against the property on which the building or structure is situated. Shelley Constr. Co. Inc. v. Sea Garden Homes, Inc., 287 S.C. 24, 336 S.E.2d 488 (Ct.App.1985); Section 29-5-10, Code of Laws of South Carolina, 1976, as amended.

In the noted case of Williamson v. Hotel Melrose, 110 S.C. 1, 96 S.E. 407 (1918), our Supreme Court considered the interrelationship between the mechanic's lien statute and the recording statute. The court concluded that as between a mechanic and a third party mortgage lienor priority is to be determined by reference to the recording statute. Williamson states:

The registry [recording] statute [now Section 30-7-10 of the Code], then by necessary inference, declares that the statutory lien, good betwixt the contracting parties before any "statement" of it is made in writing, shall not affect mortgage liens acquired by third persons (without notice and for valuable consideration) subsequent to the statutory liens, unless the evidences of the statutory liens had been reduced to a "statement" and recorded before the mortgage liens took effect. The statutory lienee, with no recorded statement, is thus in like plight as a mortgagee who, though his unrecorded lien shall be good against the mortgagor, yet it shall not be good against another mortgagee of later date, who had no notice of the unrecorded mortgage.

110 S.C. at 32, 96 S.E. at 415.

Under the logic of Williamson, American must therefore have recorded its lien without notice of any unrecorded lien of Glover in order to claim the protection of the recording statute. See also Willard v. Finch, 123 S.C. 56, 116 S.E. 96 (1923). The question then is whether there is any evidence reasonably supporting the referee's finding that American had notice of Glover's mechanic's lien when its mortgage lien took effect. Glover argues that, at a minimum, American had inquiry notice of his unrecorded lien...

To continue reading

Request your trial
5 cases
  • In re Dunes Hotel Associates
    • United States
    • U.S. Bankruptcy Court — District of South Carolina
    • August 25, 1995
    ...Partnership v. South Carolina Dep't of Highways & Pub. Transp., 311 S.C. 177, 427 S.E.2d 920 (App.1993) (same); Glover v. Lewis, 299 S.C. 44, 382 S.E.2d 242, 245 n. 3 (App.1989) (same); Arceneaux v. Arrington, 284 S.C. 500, 327 S.E.2d 357, 359 (App.1985) (same). However, South Carolina Code......
  • T.W. Morton Builders, Inc. v. von Buedingen
    • United States
    • South Carolina Court of Appeals
    • February 8, 1994
    ...contract. We affirm the finding of a cost plus contract. Foreclosure of a mechanic's lien is an action at law. Glover v. Lewis, 299 S.C. 44, 382 S.E.2d 242, 243 (Ct.App.1989). In an action at law, tried without a jury, the master's findings of fact will not be disturbed on appeal unless fou......
  • The Lite House, Inc. v. J.C. Roy Co., Inc., 1841
    • United States
    • South Carolina Court of Appeals
    • March 11, 1992
    ...work before the recording of the mortgage but filed notice of a lien after the recording of the mortgage); Glover v. Lewis, 299 S.C. 44, 382 S.E.2d 242 (Ct.App.1989) (the Recording Act protected a mortgagee that recorded its lien without notice of any unrecorded lien of a mechanic where the......
  • Archie Bell Const. Co., Inc. v. Norman
    • United States
    • South Carolina Court of Appeals
    • January 19, 1993
    ...Collins & Sons Fine Jewelry, Inc. v. Carolina Safety Systems, Inc., 296 S.C. 219, 371 S.E.2d 539 (Ct.App.1988); see Glover v. Lewis, 299 S.C. 44, 382 S.E.2d 242 (Ct.App.1989) (proceeding to foreclose a mechanic's lien is legal in Viewing the evidence in the light most favorable to the Norma......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT