Glynn v. City of Gloucester

Decision Date27 February 1986
Citation487 N.E.2d 230,21 Mass.App.Ct. 390
PartiesLawrence R. GLYNN, receiver, v. CITY OF GLOUCESTER.
CourtAppeals Court of Massachusetts

Charles P. Burgess, Waltham, for plaintiff.

Edward F. Vena, Boston, for defendant.

Before GREANEY, C.J., and PERRETTA and KASS, JJ.

GREANEY, Chief Justice.

Although we thought that our opinion in Glynn v. Gloucester, 9 Mass.App. 454, 401 N.E.2d 886 (1980), might bring this controversy to an end, we find the case back again, some twelve years after the work on the road construction project involved in the dispute was completed, and more than nine years after the lawsuit was commenced. A good deal of the delay has come about as a result of the reference of the case to a master, an event which, to quote Dickens, bogged the case down "in one of the ten thousand stages of an endless cause." 1 The following recital will bring the reader up to date. The case involves claims by the receiver of a construction contractor, R. & J. Salvucci Corporation, for the recovery of additional compensation which the receiver alleges is due in connection with Salvucci's building of a road at the Cape Ann Industrial Park in Gloucester. The background facts are set forth in our earlier decision, 9 Mass.App. at 455-456, 401 N.E.2d 886. In that decision, we concluded that the original master's report was insufficient to permit a court to decide the case, and we ordered the report recommitted to the master for supplementation. Two recommittals were necessary before a report adequate for judicial review was prepared by the master. Upon receipt of an adequate report, a judge of the Superior Court analyzed its findings and entered a judgment for the city. The receiver has appealed.

As noted in our earlier decision (9 Mass.App. at 455-456, 401 N.E.2d 886), the receiver sought additional compensation for: (1) the imposition of a charge for use of the city dump in violation of a contract provision that promised Salvucci a free disposal site for inorganic debris; (2) the city's refusal to designate a suitable area for the excavation of usable gravel fill for the road's subgrade; and (3) an order that Salvucci rebuild the road's embankments after rocks buried in their sides had caused bulging slopes. 2 The master's findings of fact in connection with each of these claims are essentially uindisputed. "[O]ur function on appeal, like that of the judge who ordered the entry of judgment, is to determine what disposition of the case is legally required by the master's findings. Central Tow Co. v. Boston, 371 Mass. 341, 342 n. 3 (1976)." D. Federico Co. v. Commonwealth, 11 Mass.App. 248, 249, 415 N.E.2d 855 (1981).

1. The disposal claim. The contract required Salvucci to dump surplus inorganic debris "within four (4) miles of the job site as directed by the City of Gloucester, Department of Public Works." The project engineer directed Salvucci to take the unsuitable surplus material to the city dump. At the dump, the city informed Salvucci that it would have to pay $1.00 per cubic yard for all material brought for disposal. Salvucci estimated that it would have cost approximately $30,000 to dispose of the surplus material taken from the job site. As an alternative, Salvucci made arrangements for the use of a private dump by agreeing to improve an old road leading to that dump in exchange for disposal privileges. The master found that, under this arrangement, Salvucci had incurred reasonable expenses of $10,622.70, and he included that sum in his award of damages to the receiver.

Paragraph 7.16 of the "Standard Specifications for Highways, Bridges and Waterways" adopted by the Commonwealth's Department of Public Works (the Bluebook) is set forth in pertinent part in the margin. 3 This, and the other provisions of the Bluebook, were expressly made parts of Salvucci's contract. The city's failure to provide a disposal site, as required by the contract, was an "omission" within the meaning of paragraph 7.16. 4 That omission required Salvucci before "sustaining ... any damage" to follow the specific notice and claim procedures spelled out in paragraph 7.16. 5 That provision further indicates that a failure to follow its procedures mandates that the contractor's "claim for compensation shall be forfeited and invalidated; and he shall not be entitled to payment on account of any such work or damage." See also G.L. c. 30, § 39I, inserted by St.1960, c. 771, § 1A. In Marinucci Bros. & Co. v. Commonwealth, 354 Mass. 141, 144-145, 235 N.E.2d 783 (1968), it was held that a claim against a public agency by a contractor for extra compensation which had not been properly perfected under a provision practically identical to paragraph 7.16 was barred. 6 See also Lawrence-Lynch Corp. v. Department of Environmental Management, 392 Mass. 681, 684-685, 467 N.E.2d 838 (1984).

The master made no finding that Salvucci had complied with paragraph 7.16 and other related contract provisions, see note 5, supra. (It was admitted at oral argument that no such compliance had occurred.) The city did not waive compliance. 7 It follows that "the failure of the contractor to make a timely claim in writing based on [the city's] omission and an itemized statement setting forth the details of ... damage incurred results in a forfeiture of its claim." Marinucci Bros. & Co. v. Commonwealth, supra, 354 Mass. at 145, 235 N.E.2d 783.

2. The road fill claim. Included in the contract was a provision that "approximately 35,000 cubic yards of fill [would] be required in addition to the excavated material within the normal roadway to complete the roadway embankment." This material was to be excavated from areas adjacent to the roadway as designated by the city's engineer. The master found that the site selected by the engineer for excavation of the fill contained material which was unsuitable because of its rocky nature. The engineer refused Salvucci's request to designate a more suitable area and suggested that Salvucci use expensive hand labor to make the fill usable. Instead, Salvucci procured a screening machine, incurring an additional expense of $182,384.35 for the machine's use. The master awarded this sum to the receiver as damages.

This claim was one for extra work, which fell within paragraphs 17 and 22 of the "General Conditions" of the contract. Paragraph 22 provides that "[n]o claim for extra work or cost shall be allowed" unless it had been submitted in writing and approved by the engineer and owner, and processed in accordance with paragraph 17. As we pointed out in Glynn v. Gloucester, 9 Mass.App. at 460, 401 N.E.2d 886: "On a public construction contract, if actions or requirements of the public agency necessitate changes in the work as it progresses, thereby causing the contractor to perform extra work or incur added expense, ... the contractor must follow the procedures spelled out in the contract ... to adjust the price before unilaterally accruing expenses to be pursued later on breach of contract or quantum meruit theories." This is settled law. See Lewis v. Commonwealth, 332 Mass. 4, 5-7, 122 N.E.2d 888 (1954); Chiappisi v. Granger Contr. Co., 352 Mass. 174, 177-178, 223 N.E.2d 924 (1967); Marinucci Bros. & Co. v. Commonwealth, 354 Mass. at 144-145, 235 N.E.2d 783 (1968); State Line Contractors, Inc. v. Commonwealth, 356 Mass. 306, 317-319, 249 N.E.2d 619 (1969); Lawrence-Lynch Corp. v. Department of Environmental Management, 392 Mass. 681, 684-685, 686, 467 N.E.2d 838 (1984); D. Federico Co. v. Commonwealth, 11 Mass.App. 248, 252-253, 415 N.E.2d 855 (1981). The master's finding that Salvucci "submitted no written claim to the [c]ity ... for the extra costs [of the screening machine] .. with the first estimate after such costs were incurred," as was required by paragraph 22, precludes recovery on this claim in the absence of a finding that the city had waived compliance with the contract procedures. There was no such finding. 8

3. The slope grading claim. The master awarded the receiver $50,000 for expenses incurred by Salvucci for reworking the slopes of the road. The reworking became necessary when Salvucci encountered subsurface conditions which differed from those predicted by the test borings furnished by the city to all bidders. The unforeseen materials included large rocks and boulders unearthed during the excavation of the roadway. The engineer told Salvucci to bury the rocks and boulders in the road's embankments. That order resulted in bulging embankments. As a result, Salvucci was compelled to rebuild them to correct this shape.

Although the master found that Salvucci had relied upon the results of the city's test borings, and that the test borings had misrepresented actual subsurface conditions, there was no finding that would support a conclusion that the city had negligently or intentionally misrepresented the conditions. It is conceded that the test borings furnished by the city to all interested parties were properly made and that the results disclosed that the subsurface materials were adequate for use in the project. There is no finding that the city expressly or impliedly warranted the accuracy of the results of the test borings. Salvucci was apparently content to rely on the city's estimates rather than go to the trouble of taking its own test borings.

In these circumstances, there can be no recovery by the receiver on the grounds of deceit, mistake or breach of warranty. Salvucci was, therefore, referred to its remedies under the contract. Paragraph 21 of the "General Conditions" specifically establishes a procedure for relief when "the [c]ontractor encounter[s] subsurface and/or latent conditions at the site materially differing from those shown on the [p]lans or indicated in the [s]pecifications." See also G.L. c. 30, § 39N, inserted by St.1972, c. 774, § 4; Glynn v. Gloucester, 9 Mass.App. at...

To continue reading

Request your trial
12 cases
  • Sutton Corp. v. Metropolitan Dist. Com'n
    • United States
    • United States State Supreme Judicial Court of Massachusetts Supreme Court
    • July 16, 1996
    ...in good faith. Glynn v. Gloucester, 9 Mass.App.Ct. [454, 460-461, 401 N.E.2d 886 (1980) (Glynn I ) ]." Glynn v. Gloucester, 21 Mass.App.Ct. 390, 397, 487 N.E.2d 230 (1986) (Glynn II ). Here, Sutton followed the procedures set out in § 39N (and incorporated in the contract as part of Article......
  • XL Specialty Ins. Co. v. Commonwealth, Massachusetts Highway Dept.
    • United States
    • Massachusetts Superior Court
    • January 3, 2013
    ... ... 5. The project was initially proposed by the City of Waltham ... The City retained Rizzo Associates to develop the design in ... tandem ... Hous. Auth., 11 Mass.App.Ct. 947, 947, 416 N.E.2d 1006 ... (1981); and Glynn v. Gloucester, 9 Mass.App.Ct. 454, ... 461, 401 N.E.2d 886 (1980) ... [ 38 ] The ... ...
  • Sutton Corp. v. Metropolitan Dist. Com'n
    • United States
    • Appeals Court of Massachusetts
    • October 31, 1995
    ...by the master's findings." D. Federico Co. v. Commonwealth, 11 Mass.App.Ct. 248, 249, 415 N.E.2d 855 (1981). Glynn v. Gloucester, 21 Mass.App.Ct. 390, 392, 487 N.E.2d 230 (1986). See also Melrose Hous. Authy. v. New Hampshire Ins. Co., 402 Mass. 27, 31 n. 4, 520 N.E.2d 493 2. We briefly sum......
  • Jrj Construction Co. v. R.W. Granger & Sons, Inc.
    • United States
    • Massachusetts Superior Court
    • July 29, 1999
    ...claim for a true breach, the contractor is required to comply with the written notice and claim provisions of the contract. See Glynn, 21 Mass.App.Ct. at 397-98. "Were otherwise, the contractual and statutory framework for the resolution of disputed claims would be virtually meaningless." I......
  • Request a trial to view additional results
1 books & journal articles

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT