Golden Gate Land Holdings LLC v. E. Bay Reg'l Park Dist., A135593

Decision Date12 April 2013
Docket NumberA135593
PartiesGOLDEN GATE LAND HOLDINGS LLC, Plaintiff and Appellant, v. EAST BAY REGIONAL PARK DISTRICT, Defendant and Respondent.
CourtCalifornia Court of Appeals Court of Appeals

CERTIFIED FOR PARTIAL PUBLICATION*

(Alameda County

Appellant Golden Gate Land Holdings LLC (Golden Gate) owns 140 acres of land straddling the border of Albany and Berkeley, on the east shore of San Francisco Bay. The site includes the Golden Gate Fields racetrack. The East Bay Regional Park District (the District) approved a resolution of necessity to condemn eight shoreline acres of Golden Gate's property to help complete the Eastshore State Park (Eastshore Park), and to construct a segment of the San Francisco Bay Trail (the Bay Trail). The District concluded that the project was exempt from the California Environmental Quality Act (CEQA; Pub. Resources Code, § 21000 et seq.)1 and posted a notice of exemption. Golden Gate petitioned the superior court for a writ of mandate seeking to vacate the District's resolution of necessity, arguing that CEQA required preparation of an environmental impact report (EIR) and that the District had violated eminent domain law.

The trial court granted the petition, but declined to direct the District to set aside its approval of the resolution of necessity. The court instead ordered the District to vacate only its CEQA exemption finding, permitting the District to leave its resolution of necessity intact and proceed with its condemnation action. Golden Gate appeals, arguing that the remedy granted by the trial court improperly allows the District to conduct after-the-fact environmental review of an already approved project. In the published portion of this opinion we address the CEQA issues, and we affirm the judgment.

I. FACTUAL AND PROCEDURAL BACKGROUND

The District is a regional park district formed and existing pursuant to section 5500 et seq. It is charged with developing and operating public parks in Alameda and Contra Costa counties. (See § 5541.)2 It also has the authority to develop recreational trails and acquire land for such purposes. (§ 5541.1.)3 The District is empowered to exercise the right of eminent domain "to take any property necessary or convenient to accomplish [such] purposes . . . ." (§ 5542; see also § 5540.)

In 1992, the Legislature enacted section 5003.03, which provides, in relevant part: "(a) It is the intent of the Legislature, in enacting this section, to provide for the acquisition, planning, and operation of a state park project located on the east shore of theSan Francisco Bay. The state park project shall consist of a contiguous shoreline park and bay trail along the east shore of the San Francisco Bay from the Bay Bridge to the Marina Bay Trail in Richmond, serving as a recreational facility within its natural setting developed in concert with a public planning process agreeable to the state and [the District]. [¶] . . . [¶] (c) For the purpose of the acquisition, planning, and development of the shoreline park, the district shall act as agent for the state and, as the state's agent, shall have the authority to exercise all of the district's powers for the purposes of acquiring, planning, and developing the shoreline park. The district shall be reimbursed by the state for any direct costs that the district incurs in carrying out these activities, upon appropriation therefor by the Legislature. By appointing the district as agent for the state, it is the intent of the Legislature to direct the state and the district to act in an expeditious manner towards the acquisition, planning, and development of the shoreline park." (Italics added.)

The Bay Trail is part of this effort. It is a planned 400-mile recreational corridor intended to ultimately encircle the San Francisco and San Pablo bays, linking nine counties and 47 cities, and providing a continuous network of bicycling and hiking trails along the shoreline. The District has long planned to extend the more than 270 miles of trail already completed. The District is also working to fully establish and develop the Eastshore Park. To that end, the state and the District cooperated in preparing the "Eastshore State Park General Plan." Acting as an agent for the state, the District has acquired and operates lands to the south and north of Golden Gate Fields. Eastshore Park currently consists of open space, walking paths, and pedestrian and bicycle trails (including the Bay Trail).

In 2003, the prior owner of Golden Gate Fields entered into a license agreement with the District allowing the public to use the property for recreational purposes. The license has since expired and has not been extended. Since then, Golden Gate has informally allowed the general public to use its property to bridge the existing gap in the Bay Trail. However, the public is exposed to dangerous traffic conditions in the Golden Gate Fields' customer parking lot, and along the main access road to the racetrack.

In 2006, in connection with the District's attempt to negotiate a voluntary acquisition of a portion of Golden Gate's property, the District contracted with Questa Engineering Corporation to prepare engineering plans and assist with preconstruction work. The concept plans, which were initially completed in 2006 and revised in 2007 and 2008, set forth three alternatives. The District obtained a cost estimate for its preferred trail design, which included demolition, installation of new retaining walls and fences, excavation, pavement restoration, installation of new pavement, and drainage improvements. However, Golden Gate refused to enter into a long-term license agreement.

In 2009, with no voluntary acquisition feasible, the District began preparing legal descriptions and plat maps for appraisal and potential condemnation proceedings. The District offered Golden Gate approximately $1,686,000 to acquire the property rights.

After the offer was not accepted, the District's Board of Directors (Board) noticed a public hearing, for April 5, 2011, to consider a resolution of necessity to authorize eminent domain proceedings.4 At the Board meeting, Assistant District Manager Nancy Wenninger explained: "So, we spent quite a bit of time with engineers looking at how we could make [the Bay Trail] safe, how we could avoid conflicts with the racetrack. Everything we looked at, at first, involved the racetrack losing a lane for their traffic. And that was not just workable for them. So, we finally settled upon this latest strategy, which is to keep the trail outboard and run it along the shoreline all the way . . . . [¶] . . . [¶] . . . We believe it is the best alignment for us to have. . . . And so, in order to be able to spend money to construct a . . . trail, we need land tenure. . . . [¶] . . . [¶] The design, which is still preliminary, basically, puts the trail outboard of the existing road. So it would be along the shoreline, between the shoreline and the road. It would not follow that old road which currently exists. It will require some reconfiguration of the entry intothe Golden Gate Fields property. They will put the trail on the outside, so there will be no point in time at which trail users have to cross through the racetrack [traffic], all along the shoreline all the way. This will be a typical Class I trail, 12 feet wide and at least two-foot shoulders on each side."

The District's staff also issued a report that states: "The District commissioned a feasibility study to determine the best alignment for the Bay Trail segment. A number of alternatives were considered. The alignment selected is physically separated from the racetrack traffic and will provide the safest, most scenic trail experience. It has also been designed with a grade which complies with the Americans with Disabilities Act." The report also states: "The proposed project is exempt from [CEQA] pursuant to CEQA Guidelines, Section 15325."5

Golden Gate objected to the proposed resolution. It asserted that the project was not exempt from CEQA and, thus, the District could not approve the project until after it reviewed and considered the environmental effects of trail construction and other improvements. Golden Gate also maintained that public necessity did not require condemnation because the public already had access to the property for recreationalpurposes, and because the least private injury and environmental harm would be achieved by planning this segment of the Bay Trail in conjunction with anticipated redevelopment of the property, which would also incur less public expense.

The District nonetheless approved the resolution of necessity, which was memorialized in Resolution No. 2011-4-079. The resolution provides: "[The District] wishes to acquire certain real property rights described herein below for District use by the exercise of the power of eminent domain. [¶] . . . The acquisition of such rights is required to help to complete [Eastshore Park] and provide the opportunity to construct an important segment of the . . . Bay Trail. In addition, the acquisition will protect important natural resources and the visual integrity of the existing park. . . . [¶] . . . [¶]The said real property rights are to be acquired for purposes of preservation of open space, habitat and natural conditions, pursuant to the authority granted in California Constitution, Article I, Section 19; . . . Sections 5540, 5541, 5541.1 and 5542; Title 7, Part 3 of the Code of Civil Procedure; and other provisions of law[.] [¶] . . . The public interest and necessity require the real property rights sought to be acquired[.] [¶] . . . The project is planned and located in the manner which will be most compatible with the greatest public good and the least private injury[.] [¶] . . . The real property rights described herein are necessary for the project[.]"

The property described in the resolution includes: (1) an...