Goodell v. K. T. Enterprises, Ltd., TT-242

Decision Date10 March 1981
Docket NumberNo. TT-242,TT-242
Citation394 So.2d 1087
Parties31 UCC Rep.Serv. 129 John L. GOODELL et al., Appellants, v. K. T. ENTERPRISES, LTD., Appellee.
CourtFlorida District Court of Appeals

William H. Jeter, Jr., of Adams & Adams, Jacksonville, for appellants.

No appearance for appellee.

PER CURIAM.

Better Baked Foods, Inc. (Better Baked) appeals a judgment holding appellee is not liable to Better Baked as a third party beneficiary of a breached contract between appellee and Goodell. Goodell also appeals, advocating that instead of awarding him only his deposit on the contract, the trial court should have allowed Goodell "cover" under Section 672.712, Florida Statutes (1977). We agree with both contentions. 1

Goodell initially contracted with appellee to build a continuous belt conveyor system. 2 The agreement provided that appellee would ship the unit to Better Baked and install it according to its direction. Tyler, appellee's president, admitted knowing the conveyor was for Better Baked's pizza freezing business. It was undisputed that the president of Better Baked discussed the design of the unit at length with Tyler. The record further indicates that in pre-contract negotiations, the sale was going to be directly with Better Baked. However, in the contract, Goodell indicated that "we" (obviously Better Baked and Goodell) had decided that Goodell would take title. Goodell paid $10,900 as a deposit on the contract. However, as the trial court found, the conveyor built by appellee did not meet the specifications. When it became apparent that satisfactory modifications could not be made, Goodell sent a mailgram to appellee informing Tyler that "we" decided to cancel the contract. 3 Goodell informed Tyler that if he returned the deposit money, the contract would be cancelled, and no other damages would be claimed. After approximately three weeks, Goodell sent another mailgram warning that if the deposit was not returned by December 15th, Goodell would "... sue for the deposit and for damages because of lost jobs, rent, extra expense because of delay, and the additional cost of another conveyor." However, the deposit was not returned. Goodell bought another continuous conveyor belt which was installed about five months later at a cost of $12,820 over Goodell's contract price. At trial, Better Baked presented evidence concerning its damages, including additional rental, overtime paid employees to fill orders for frozen pizzas, lost profits, and more.

The trial court found that Goodell was to purchase the equipment for use by Better Baked; that appellee breached the contract by failing to timely deliver and furnish the conveyor in compliance with the specifications; and that Goodell rescinded the contract and was entitled to return of his down payment with interest. The trial court ruled against Better Baked on the common law theory of third party beneficiary.

First, we think Goodell presented an unrebutted prima facie case for "cover" under Section 672.712 which provides:

(1) After a breach within the preceding section the buyer may "cover" by making in good faith and without unreasonable delay any reasonable purchase of or contract to purchase goods in substitution for those due from the seller.

(2) The buyer may recover from the seller as damages the difference between the cost for cover and the contract price together with any incidental or consequential damages as hereinafter defined (s. 672.715), but less expenses saved in consequence of the seller's breach.

(3) Failure of the buyer to effect cover within this section does not bar him from any other remedy.

There was no unreasonable delay in the purchase of the new unit because the unit had to be specially ordered. The unit clearly was bought as a substitute for appellee's unit. The testimony showed that the new unit and the unit contracted for were of the same...

To continue reading

Request your trial
11 cases
  • Masonite Corp. Hardboard Siding Prods. Litigation
    • United States
    • U.S. District Court — Eastern District of Louisiana
    • September 16, 1998
    ...established a clear intent to sell a specific ring for the benefit of a particular woman. Id. at 872; see also Goodell v. K.T. Enter., Ltd., 394 So.2d 1087 (Fla.Dist.Ct.App.1981) (finding plaintiff was third-party beneficiary where defendant built conveyor system specifically for plaintiff'......
  • Diaz v. FCA U.S. LLC
    • United States
    • U.S. District Court — District of Delaware
    • September 2, 2022
    ...v. Church & Tower, Inc., 814 So.2d 522, 525-26 (Fla. Dist. Ct. App. 2002) (citation omitted); cf. also Goodell v. K. T. Enters., Ltd., 394 So.2d 1087, 1089 (Fla. Dist. Ct. App. 1981) (“We also find that appellee is liable to Better Baked as a third party beneficiary. As shown in the facts a......
  • Belik v. Carlson Travel Grp., Inc.
    • United States
    • U.S. District Court — Southern District of Florida
    • June 6, 2011
    ...of the parties.” Fla. Power & Light Co. v. Mid–Valley, Inc., 763 F.2d 1316, 1321 (11th Cir.1985) (citing Goodell v. K.T. Enters., Ltd., 394 So.2d 1087 (Fla. 1st DCA 1981)). Both contracting parties must intend to benefit third parties; it is insufficient if only one party unilaterally inten......
  • Belik v. Carlson Travel Group Inc.
    • United States
    • U.S. District Court — Southern District of Florida
    • June 6, 2011
    ...of the parties." Fla. Power & Light Co. v. Mid-Valley, Inc., 763 F.2d 1316, 1321 (11th Cir. 1985) (citing Goodell v. K.T. Enters., Ltd., 394 So. 2d 1087 (Fla. 1st DCA 1981)). Both contracting parties must intend to benefit third parties; it is insufficient if only one party unilaterally int......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT