Hall v. Carl G. Ek & Son Const. Co.

Decision Date17 January 1963
Citation236 N.Y.S.2d 555,17 A.D.2d 558
PartiesJerry Ray HALL, d/b/a Lakewood Supply Co., Respondent, v. CARL G. EK & SON CONSTRUCTION CO., Inc., The Travelers Indemnity Company, Appellants, and County of Chautauqua, Defendant.
CourtNew York Supreme Court — Appellate Division

Gerace & Lodestro, Jamestown, for respondent (Francis V. Dow, Jamestown, of counsel).

Vedder & Crowley, Olean, for appellants (James F. Crowley, Olean, of counsel).

Before WILLIAMS, P. J., and GOLDMAN, HALPERN, McCLUSKY and HENRY, JJ.

WILLIAMS, Presiding Justice.

The question presented is whether an assignee of the claim of a person who has furnished labor and materials in the construction of a public improvement has the right to file a notice of lien under section 5 of the Lien Law. For purposes of clarity, we note at this point that the assignment was of a claim for labor and materials furnished, as distinguished from an assignment of a lien already perfected by the filing of notice thereof.

The assignment of the claim was made to the plaintiff-respondent after all of the work had been performed and the materials furnished to the project by the assignor. The defendant-appellant Ek & Son Construction Co., Inc. was the general contractor and the defendant-appellant Travelers Indemnity Company was the surety on a bond given to discharge the so-called lien filed by plaintiff. The present action was brought to foreclose the so-called lien. Answers were served, after which the plaintiff moved for summary judgment. The defendants resisted the motion and took the position that the plaintiff was not entitled to file a lien under said section 5 of the Lien Law. The justice at Special Term construed section 5 as authorizing the filing of a lien by the plaintiff.

Since 1871, when Rollin v. Cross, 45 N.Y. 766, was decided, it has been the law of this state that the assignee of a claim may not file a lien. That case has never been overruled. We call attention to the fact that the Rollin case dealt with a lien against a private, as distinguished from a public, improvement. Chapter 478 of the Laws of 1862, which controlled the Rollin decision, was similar in substance and effect to the present section 3, which relates to liens against private improvements.

The Rollin case was followed in Tisdale Lumber Co. v. Read Realty Co., 154 App.Div. 270, 271, 138 N.Y.S. 829, 830, also an action to foreclose a mechanic's lien on a private improvement. The plaintiff was the assignee of one Tisdale, who had furnished materials in the construction of the improvement. The Court stated:

'It seems to be true * * * that a valid mechanic's lien cannot be created by filing the statutory notice by the assignee of a claim. The right to file a mechanic's lien is a personal right, limited to the person performing the labor or furnishing the material, and is not assignable. The transfer of the claim in suit, therefore, did not carry with it the assignor's right to acquire a valid lien. This has been the construction given to similar statutes for many years.'

The court then reasoned that the definition of a lienor in section 2 of the Lien Law, 'any person having a lien upon property * * * and includes his successor in interest,' did not include an assignee of a claim.

'A 'successor in interest,' within the meaning of this term as used in the statute, is one who succeeds to a lienor's rights under a valid notice of lien already filed, by assignment or otherwise. In other words, the assignor must have an existing lien before he can have a 'successor in interest."

The court went on (pp. 271-272, 138 N.Y.S. p. 831) to reject the contention by the plaintiff that he was the 'successor in interest' under an 'inchoate lien'.

'There is no such thing as an 'inchoate' mechanic's lien. The sole right given by the statute is to create a lien, which has no existence, inchoate or otherwise, unitl the notice is filed, and until this is done no priority among the claims of creditors is recognized. The lien and a consequent priority originates with the notice when duly filed. Mack v. Colleran, 136 N.Y. 617, 620, 32 N.E. 604.'

Unless an assignee of a claim arising out of a public improvement has rights under the language of section 5, not available to an assignee under section 3, the plaintiff's contentions must fail. We now turn to specific language of section 5, which is the section under which the present case must be decided:

'A person performing labor for or furnishing materials to a contractor, his subcontractor or legal representative, for the construction * * * of a public improvement * * * shall have a lien * * * upon the moneys of the state or of such corporation * * * upon filing a notice of lien as prescribed in this article * * *.' (Italics added.)

Special Term found that the words 'or legal representative' referred to the person performing or furnishing and included an assignee of such person. It is obvious, however, that the words 'or legal representative' do not refer back to the person performing labor or furnishing materials but relate to the contractor or subcontractor to whom such labor or materials were furnished. Any other construction is contrary to the clear language of the section. (Cf. Dorn v. Arthur A. Johnson Corp., 16 A.D.2d 1009, 1010, 229 N.Y.S.2d 266, 268; Wynkoop v. People, 1 A.D.2d 620, 622, 153 N.Y.S.2d 836, 838.) The fact that the words 'or legal representative' do not appear in section 3 does not affect in any way the construction of section 5 because neither section indicates that a person who performs labor or furnishes materials, or his assignee, may file a claim. Nor is such a construction warranted. Liens on private improvements and on public improvements are in the same category so far as the right of an assignee of a claim is concerned (Blanc, Mechanics' Liens, paras. 9g, 71c, pp. 17, 435 (1949)).

The case of Ogden v. Alexander (140 N.Y. 356, 35 N.E. 638), at first glance, seems to be contrary to the holding in Rollin v. Cross; but the court very carefully pointed out the distinction between that case and the Rollin case where it is said at page 361, 35 N.E. at page 643:

'We may grant that Oliver [a former partner] lost all ownership of the claim, and retained no equity against or interest in, the partnership assets, at least after all its debts had been paid; but that fact does not make Ogden a mere assignee, or put him outside of the intended purpose and scope of the statute.' (Italics added.)

There is no question that, after a lien has been created by filing of a notice thereof, it may be assigned (Tisdale Lumber Co. v. Read Realty, 154 App.Div. 270, 138 N.Y.S. 829, supra; Lien Law, § 14). In fact, a reading of section 14 clearly sets forth the distinction that we make. The section commences: 'A lien, filed as prescribed in this article, may be assigned by a written instrument * * *'. If an assignee of a claim had had the right to file a lien, there would have been no need for the enactment of section 14 which was added by Chapter 418 of the Laws of 1897. It must also be remembered that section 16, which pertains to the assignment of funds, has no bearing whatsoever upon the problem here involved.

It follows that, inasmuch as the plaintiff has no lien, the foreclosure features of the action must fall; and it, in turn, follows that the complaint must be dismissed as to Travelers Indemnity Company. The alleged lien was discharged and the bond took the place of the fund in accordance with section 21(5), Lien Law. The right of recovery on that bond is not personal but could be had only after a judgment of foreclosure had been procured. (Berger Mfg. Co. v. City of New York, 206 N.Y. 24, 99 N.E. 153; Security Trust Co. of Rochester v. Seaboard Surety, 15 A.D.2d 993; Johnson v. Thomas Breen Co., 143 Misc. 908, 257 N.Y.S. 718, affd. 235 App.Div. 651, 653, 254 N.Y.S. 1043; Simonelli v. A. L. Guidone & Son, 201 App.Div. 44, 194 N.Y.S. 104. See, also, Jensen on Mechanics' Liens, 3rd ed., p. 408, § 353.)

The Special Term justice directed that the matter be referred to a referee for a determination only of the amount due as to Ek & Sons and Travelers. The portion of the order that directs the assessment of the amount due from Ek & Sons to the plaintiff should be affirmed. We see no reason to compel the plaintiff to commence a simple action for money damages merely because a judgment in foreclosure may not be granted. But inasmuch as Ek & Sons has asked for a jury trial of the issues relating to amount, and inasmuch as that defendant has not waived the right to a jury trial, the determination of the amount due should be had before the court and a jury. Rule of Civil Practice, rule 113, subdivision 3, states that if there is only a triable issue of fact as to damages '* * * the court shall order an immediate hearing before a referee, before the court, or before the court and a jury, whichever may be proper, to assess * * *.' In this case a court and jury is the proper forum.

Order modified by dismissing the complaint on the merits as to the defendant-appellant Travelers Indemnity Company and by directing that the amount of damages which the plaintiff is entitled to recover from the defendant-appellant Ek & Son Construction Co., Inc. be determined by an assessment before the court and a jury and, as so modified, affirmed, without costs of this appeal to any party.

All concur except HALPERN, J., who dissents and votes to affirm, in a separate opinion.

HALPERN, Justice (dissenting).

I do not believe that the case of Rollin v. Cross, 45 N.Y. 766, decided in 1871, relied upon by the majority, would be followed today, even with respect to a mechanic's lien upon private property. That case was decided upon the theory that the right to file a mechanic's lien under the local lien law (L.1862, Ch. 478) applicable to Kings and Queens Counties, was a personal right of the person furnishing the labor or material and that the...

To continue reading

Request your trial
8 cases
  • EklecCo v. Iron Workers Locals 40, 361, & 417 Union Sec. Funds
    • United States
    • U.S. Court of Appeals — Second Circuit
    • March 22, 1999
    ... ... Corp. v. P & R Elec. Corp., 76 A.D.2d 540, 543-44, 431 N.Y.S.2d 586, 589 (2d Dep't 1980); Hall v. Carl G. Ek & Son Constr. Co., 17 A.D.2d 558, 559-60, 236 N.Y.S.2d 555, 556 (4th Dep't 1963) ... ...
  • Bernardo v. Steelco, Div. of Metropolitan Steel Industries, Inc., 1
    • United States
    • New York Supreme Court
    • September 10, 1982
    ... ... and The Travelers Indemnity Co ...         M. Carl Levine, Morgulas & Foreman, New York City, for P.J. Carlin Const. Co. and Atlas Tile & Marble ... Berger Mfg. Co. v. City of New York, 206 N.Y. 24, 30, 99 N.E. 153 (1912); Hall v. Carl G. Ek & Son Constr ... Co., 17 A.D.2d 558, 236 N.Y.S.2d 555, 558-559 (4th Dept. 1963), ... ...
  • United States v. Certified Industries, Inc.
    • United States
    • U.S. Court of Appeals — Second Circuit
    • June 3, 1966
    ... ... Berger Mfg. Co. v. City of New York, 206 N.Y. 24, 30, 99 N.E. 153 (1912); Hall v. Carl G. Ek & Son Constr. Co., 17 A.D.2d 558, 236 N.Y. 361 F.2d 861 S.2d 555, 558-559 (4th ... ...
  • Gould, Inc. v. Dynalectric Co.
    • United States
    • Delaware Superior Court
    • July 23, 1981
    ... ... M. Davis and Sons, Inc., Del.Supr., 412 A.2d 939 (1980); Silverside Home Mart, Inc. v. Hall, Del.Super., 345 A.2d 427, 428 (1975); Heitz v. Sayers, Del.Super., 113 A. 901, 902 (1921) ... 192, 322 P.2d 1044 (1958). The leading decision reflecting that view is Hall v. Carl G. Ek & Son Construction Co., N.Y.App.Div., 17 A.D.2d 558, 236 N.Y.S.2d 555; aff'd., N.Y.Ct.App., ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT