Hannum v. Board of Environmental Protection

Decision Date15 October 2003
Citation2003 ME 123,832 A.2d 765
PartiesAnne S. HANNUM v. BOARD OF ENVIRONMENTAL PROTECTION et al.
CourtMaine Supreme Court

Edmond J. Bearor (orally), Timothy A. Pease, Rudman & Winchell, L.L.C., Bangor, for plaintiff.

G. Steven Rowe, Attorney General (orally), Lucinda E. White, Asst. Attorney General, Margaret B. McCloskey, Asst. Attorney General, Augusta, for BEP, defendant.

James S. Nixon (orally), Gross Minsky & Mogul, P.A., Bangor, for Friends of Acadia, defendants.

Douglas B. Chapman (orally), Eileen McGlinchey Fahey, Fenton, Chapman & Kane, P.A., Bar Harbor, for Millicent Guptill Higgins and Ruth Higgins Horsman, defendants.

Panel: SAUFLEY, C.J., and CLIFFORD, DANA, ALEXANDER, CALKINS, and LEVY, JJ.

SAUFLEY, C.J.

[¶ 1] Anne S. Hannum, individually and in her capacity as trustee of the Anne Stroud Hannum Trust, appeals from the judgment of the Superior Court (Hancock County, Jabar, J.) affirming a decision of the Board of Environmental Protection in which the Board denied Hannum's application for a permit to construct a dock on her property in Bar Harbor on Long Cove. Hannum argues that the Board (1) applied regulatory standards that were unconstitutionally vague and represented an impermissible delegation of legislative authority, and (2) made findings not supported by facts in the record. Because we conclude that specific factual findings relied upon by the Board in reaching its conclusions were unsupported by evidence in the record, we vacate the Superior Court's judgment and remand for reconsideration by the Board.

I. INTRODUCTION
A. Statutes and Rules

[¶ 2] Before building the dock, Hannum was required, among other things, to obtain a permit pursuant to the Natural Resources Protection Act, 38 M.R.S.A. §§ 480-A to 480-Z (2001 & Supp.2002). The Act is designed to address a legislatively identified need to "prevent the degradation of and encourage the enhancement of" critical water-related state resources. 38 M.R.S.A. § 480-A (2001). One of the Legislature's key findings in enacting the Natural Resources Protection Act was "that the cumulative effect of frequent minor alterations and occasional major alterations of these [natural] resources poses a substantial threat to the environment and economy of the State and its quality of life." Id.

[¶ 3] The Act requires a permit from the Department of Environmental Protection for any construction, repair, or alteration of any permanent structure "if the activity is located in, on or over any protected natural resource." 38 M.R.S.A. § 480-C(1) & (2)(D) (2001 & Supp.2002).1 The Act authorizes the Board of Environmental Protection to assume jurisdiction over the approval or denial of a permit application in a variety of circumstances, including upon request by the Commissioner of the Department of Environmental Protection if the application "generate[s] substantial public interest." 38 M.R.S.A. §§ 341-D(2)(D), 344(2-A)(A) (2001).

[¶ 4] The Act establishes nine standards that any applicant for a permit must meet before a permit can be granted. 38 M.R.S.A. § 480-D (2001 & Supp.2002). The standards in controversy in this case are those listed in section 480-D(1), requiring an applicant to demonstrate that there will be no unreasonable interference with existing scenic, aesthetic, recreational, or navigational uses, and section 480-D(3), requiring an applicant to demonstrate that a project will cause no unreasonable harm to significant wildlife habitat, aquatic habitat, marine fisheries, or other aquatic life.2 Id. In evaluating compliance with section 480-D(3), the Department may consider steps to mitigate or minimize the impact of a proposed activity. 38 M.R.S.A. § 480-D(3)(A) & (B) (Supp.2002).

B. Case History

[¶ 5] Anne S. Hannum is a trustee and beneficiary of a private trust that owns a sixty-two-acre parcel of property in Bar Harbor. The land includes twelve hundred feet of frontage on Long Cove. The abutting property to the west of the Hannum property contains a seasonal residence with a dock. Several seasonal cottages, without docks, are located easterly of the Hannum property. One other dock is visible and located approximately four hundred yards from the site of Hannum's proposed dock.

[¶ 6] In 1999, Hannum applied to the DEP for a permit to build a ninety-foot-long and five-foot-wide dock extending from her property into Long Cove. The dock was projected to extend to the low water mark, with a seasonal ramp and float extending from the dock to permit use of boats tied to the float at all tide levels. Hannum received approval to construct the dock from the U.S. Army Corps of Engineers, the U.S. Environmental Protection Agency, the U.S. Fish and Wildlife Service, the National Marine Fishery Service, and the Maine Department of Inland Fisheries and Wildlife.

[¶ 7] Because of the significant public interest generated by Hannum's application, the DEP recommended that the Board assume jurisdiction over the application and hold a public hearing. See 38 M.R.S.A. §§ 341-D(2)(D), 344(2-A)(A). The Board began the hearing on June 15, 2000, and reconvened the hearing on July 6, 2000. The Board received a significant volume of testimony and evidence in support of, and in opposition to, the application. It considered the application at a March 2001 meeting, after receiving the DEP's staff recommendation that the application be approved. The Board voted to deny the requested permit. A written denial issued in May 2001.

[¶ 8] At the heart of the Board's decision to deny the application was its finding

that the proposed pier, by itself, might not have an unreasonable adverse impact on marine life. However, the cumulative impact of this large pier, together with the increased boat traffic from this and other piers which would likely follow if this pier were approved, both on the Applicant's property and on two neighboring properties subject to easements which do allow docks, poses a substantial threat to do unreasonable and irreversible harm to the aquatic life in this special cove.

(Emphasis added.) The Board's order went on to find

that permanent piers will necessarily increase boat traffic in the quiet and relatively undeveloped cove, which will disturb the existing tern and seal colonies, both of which are very unusual, if not rare in Maine. The fact that other boat traffic unrelated to the applicant may also come into the cove does not preclude the Board's finding that the probable cumulative impacts of this project on significant wildlife and aquatic habitat are unacceptable.

With these findings stated, the Board concluded that "the project would have an unreasonable adverse impact on significant wildlife habitat, aquatic habitat, and other aquatic life." Relying on this finding, the Board also concluded that "the project will unreasonably interfere with existing scenic and aesthetic uses pertaining to the viewing of wildlife."

[¶ 9] Beyond these findings, the Board also based its denial of the application on a conclusion that "[t]he proposed activity does not meet the avoidance and minimal alteration standards of the Wetland Protection Rules, Chapter 310, Sections 5(A) and 5(B), in that the applicant has reasonable and practicable alternatives to constructing a permanent pier."3 The Board's order did not specify what the practicable alternatives might be.4

[¶ 10] Hannum appealed the Board's denial of her permit application to the Superior Court, which affirmed the Board's decision. This appeal followed.

II. DISCUSSION

[¶ 11] When the Superior Court acts as an intermediate appellate court, reviewing a decision of a state or local administrative agency, we review directly the decision of the administrative agency. See Connolly v. Bd. of Soc. Work Licensure, 2002 ME 37, ¶ 6, 791 A.2d 125, 127. Accordingly, we review directly the decision of the Board of Environmental Protection to determine if its findings and conclusions are supported by evidence in the record, and if the decision is affected by any abuse of discretion or error of law. Id.; see also Downeast Energy Corp. v. Fund Ins. Review Bd., 2000 ME 151, ¶ 13, 756 A.2d 948, 951.

[¶ 12] Hannum did have the burden of proving that her pier project would meet the standards addressed by the Natural Resources Protection Act. 38 M.R.S.A. § 480-D (requiring an applicant to demonstrate that the proposed activity will not "unreasonably interfere" with or cause "unreasonable harm" to the natural resources protected by the Act); Murphy v. Bd. of Envtl. Prot., 615 A.2d 255, 258 (Me.1992) (requiring a permit applicant to demonstrate that his proposed activity complied with statutory criteria set forth in 38 M.R.S.A. § 480-D). However, the Board could not simply determine that Hannum's burden of proof was not met. By statute, the Board had an affirmative obligation to set out in a decision its reasons for the denial of the application and to state its reasons with sufficient specificity to permit understanding and meaningful appellate review. 5 M.R.S.A. § 9061 (2002); 1 M.R.S.A. § 407(1) (1989); Christian Fellowship & Renewal Ctr. v. Town of Limington, 2001 ME 16, ¶ 15, 769 A.2d 834, 839 (stating that "there cannot be meaningful judicial review of agency decisions without [adequate] findings of fact").

[¶ 13] In this case, the Board fulfilled its responsibility to detail its findings regarding the effect on natural wildlife. In so doing, it found that Hannum's "proposed pier, by itself, might not have an unreasonable adverse impact on marine life." Nonetheless, it concluded that the cumulative impact of intrusions, from both boats and other docks, would combine to result in an unreasonable impact on the local marine life.

[¶ 14] The Board did not, however, limit its analysis of cumulative impacts to the facts found in the record, such as the impact of the Hannum dock, other existing docks, and the reasonably anticipatable boat traffic attendant to...

To continue reading

Request your trial
24 cases
  • State v. Rabon, Docket: Oxf-05-518.
    • United States
    • Maine Supreme Court
    • 14 Agosto 2007
    ...evidence, not speculation, in fact-finding, and we must vacate decisions where fact-finding was unsupported by evidence." Hannum v. Bd. of Envtl. Prot., 2003 ME 123, ¶ 15 n. 6, 832 A.2d 765, 770. When a party has the burden of proof by a preponderance of the evidence, the "mere possibility"......
  • Uliano v. Board of Environmental Protection
    • United States
    • Maine Supreme Court
    • 13 Agosto 2009
    ...understanding and meaningful appellate review. Schwartz v. Unemployment Ins. Comm'n, 2006 ME 41, ¶ 10, 895 A.2d 965, 970; Hannum v. Bd. of Envtl. Prot., 2003 ME 123, ¶ 12, 832 A.2d 765, 769. See also 5 M.R.S. § 9061 (2008); 1 M.R.S. § 407(1) (2008). In fact, we said the same thing in our pr......
  • Bates v. Department of Behavioral and Developmental Services
    • United States
    • Maine Supreme Court
    • 17 Diciembre 2004
    ...requires that we first determine whether the issue may be resolved on a basis that does not implicate the constitution. Hannum v. Bd. of Envtl. Prot., 2003 ME 123, ¶ 18, 832 A.2d 765, 770; Rideout v. Riendeau, 2000 ME 198, ¶¶ 14-15, 761 A.2d 291, 297-98. Because the court employed an incorr......
  • Puritan Med. Prods. Co. v. Copan Italia S.P.A.
    • United States
    • Maine Supreme Court
    • 3 Julio 2018
    ...a constitutional violation. Bates v. Dep't of Behavioral & Developmental Servs., 2004 ME 154, ¶ 85, 863 A.2d 890 ; Hannum v. Board of Environmental Protection, 2003 ME 123, ¶ 18, 832 A.2d 765.[¶ 39] Because the trial court rejected Puritan's claim by its grant of Copan's motion for summary ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT