Hartline-Thomas, Inc. v. H. W. Ivey Const. Co., Inc.
Decision Date | 27 January 1982 |
Docket Number | No. 62713,HARTLINE-THOMA,INC,62713 |
Parties | v. H. W. IVEY CONSTRUCTION COMPANY, INC. |
Court | Georgia Court of Appeals |
William A. Wehunt, Atlanta, for appellant.
Joe G. Davis, Jr., Frank L. Wilson, III, William T. McKenzie, Atlanta, for appellee.
Appellant Hartline-Thomas, Inc., seeking recovery of $17,292.80, brought this contract action against appellee H. W. Ivey Construction Co., Inc. Appellee filed a motion for summary judgment on the basis of accord and satisfaction. Appellant brings this appeal from the trial court's grant of that motion.
Appellee was the general contractor for the construction of a garage facility for the City of East Point. Appellant and appellee entered into a subcontract under the terms of which appellant was to perform all painting and coating work required under the general contract "specified in but not limited to Section 9G of the Specifications." Following the completion of performance under the subcontract, a dispute arose concerning certain work which had been performed by appellant--appellee contending the work had been specified under the terms of the subcontract, and appellant contending that it had been extra work in addition to that required by the subcontract.
As is here pertinent Section 9G of the contract specifications provided that two (2) coats of "Sanders 'Permacrete' " were to be applied to exterior surfaces at a thickness of a given number of square feet per gallon. In addition to incorporating the above specifications the subcontract provided: (Emphasis supplied.) The subcontract also provided: "This Sub-contract contains the entire agreement between the parties, and all additions thereto or changes therein shall be in writing and shall not be binding unless same are in writing." (Emphasis supplied.)
The evidence of record shows without dispute that appellant applied two coats of permacrete on the exterior surfaces of the project. Appellant contends that the application of the second coat was extra work performed pursuant to an oral agreement made between it and the project's architect. The oral agreement was apparently meant to alter the subcontract so as to provide for the application of only one coat of permacrete at a thickness of 10 mils. 1 Test results taken after this application indicated a thickness of between 6 and 10.5 mils. Also subsequent to the first permacrete application, a different subcontractor was required to replace parts of the exterior surface because the material used did not meet contract specifications. Following this replacement of a portion of the exterior, appellant applied the second coat of permacrete. Appellant contended that the second coat was necessitated by the foregoing replacement of a portion of the exterior and was, in the light of its oral agreement, extra work for which it was entitled to compensation in addition to that provided in the subcontract. Appellee countered that, notwithstanding the replacement of a portion of the exterior, the second application of permacrete would have been required because the first coat did not meet the required thickness.
"... Bagley v. Firestone Tire etc. Co., 104 Ga.App. 736, 739, 123 S.E.2d 179 (1961); Code Ann. § 81A-156(c). However, " " Summer-Minter & Assoc. v. Giordano, 231 Ga. 601, 604, 203 S.E.2d 173 (1974); Code Ann. § 81A-156(e). Appellant contends that material questions of fact remain on the issue of its oral agreement to apply a second coat of exterior permacrete on the project.
Appellant asserts that because of its oral agreement with the architect, its application of the second coat of permacrete constituted a new contractual arrangement which was separate and distinct from the subcontract; however, this assertion is not supported by any facts of record. The undisputed facts in this case show that the subcontract specified the application of two (2) coats of permacrete on the exterior surfaces of the project. Indeed, appellant applied two coats of permacrete on the exterior surfaces of the project. The subcontract provided that a specification...
To continue reading
Request your trial-
Burke Co. v. Hilton Development Co.
...condition also, notwithstanding any protest he may make to the contrary. Id. at 1511 (quoting, Hartline-Thomas, Inc. v. H.W. Ivey Construction Co., 161 Ga.App. 91, 289 S.E.2d 296, 299 (1982)). Basic contract law, therefore, afforded the plaintiff in this case the option of accepting the che......
-
Rhone v. State Auto Mut. Ins. Co.
...2 The Restrictive Endorsement Dr. Allen altered the restrictive language on the draft. In Hartline-Thomas, Inc. v. H.W. Ivey Construction Co., 161 Ga.App. 91, 289 S.E.2d 296 (1982), the court noted that "erasure or alteration of the condition expressed in a check by a creditor, without noti......
-
Clark v. General Motors Acceptance Corp.
...the seller." Such a provision is enforceable, thereby rendering any subsequent oral modifications void. Hartline-Thomas v. H.W. Ivey & Co., 161 Ga.App. 91, 93, 289 S.E.2d 296 (1982). Moreover, "parol evidence is not admissible to vary the terms of a binding written agreement, even to establ......
-
Neal H. Howard & Associates v. Carey & Danis, 4:02-CV-51-3.
...the creditor, "the acceptance of the payment carries with it the acceptance of the condition." Hartline-Thomas, Inc. v. H.W. Ivey Constr. Co., Inc., 161 Ga.App. 91, 94, 289 S.E.2d 296, 299 (1982) (internal citations omitted). Furthermore, the rule applies whether or not the creditor protest......