Hess Die Mold, Inc. v. American Plasti-Plate Corp.

Decision Date02 June 1983
Docket NumberNo. 12-81-0139-CV,PLASTI-PLATE,12-81-0139-CV
Citation653 S.W.2d 927
Parties36 UCC Rep.Serv. 1632 HESS DIE MOLD, INC., Appellant, v. AMERICANCORPORATION, Appellee.
CourtTexas Court of Appeals

James W. Jenkins, Tyler, for appellant.

Richard W. Lottmann, Wilson, Miller, Spivey, Sheehy, Knowles & Hardy, Tyler, for appellee.

McKAY, Justice.

Defendant (Hess) appeals from a judgment wherein plaintiff (American) recovered damages for breach of contract. Trial was to the court. No statement of facts appears in the record, but findings of fact and conclusions of law were requested and filed.

In presenting the nature of the case and the contentions of the parties, we must rely exclusively upon the pleadings and findings of fact made by the trial court, in the absence of a statement of facts. Mial v. Mial, 543 S.W.2d 736, 737 (Tex.Civ.App.--El Paso 1976, no writ); Ives v. Watson, 521 S.W.2d 930, 932 (Tex.Civ.App.--Beaumont 1975, writ ref'd n.r.e.).

American is in the business of injection molding of plastics. Hess manufactures die molds. One of American's molds had become old and worn to the point that it no longer performed satisfactorily, and it solicited bids for a new one. On April 27, 1979, Hess submitted a quote to American to design and build a suitable mold at a price of $23,445.00, one-half in advance and the balance due on delivery. This quote was accepted by American on the same day, and it thereafter sent a purchase order embodying the terms of said quote to Hess. One of these terms provided for delivery of the finished mold within eighteen weeks from April 27, 1979. Pursuant to the terms of the contract, American issued a check to Hess on May 7, 1979, in the amount of $11,722.50 as payment of one-half of the agreed price.

Hess never completed a mold which would perform or operate properly in American's business. As a result, on June 20, 1980, American was forced to contract with another manufacturer for the production of a suitable mold at a contract price of $47,500. Thus the cost to American for this mold, over and above its contract price with Hess, was $24,065.

American thereafter filed suit against Hess for breach of contract, praying for a return of the $11,722.50 down payment and the $24,065.00 excess incurred to procure a similar mold from another manufacturer, among other things. After a nonjury trial, the court rendered judgment awarding the above amounts to American, and Hess appeals.

Appellant's points of error all attack the award of $24,065.00, stated by the trial court to represent the benefit of the bargain for American. Its first three points attack said award on the ground that such losses are "special damages," as opposed to "general damages." Thus points one through three allege that the pleadings of American and the findings of the trial court do not support such an award because there is no allegation or finding that said losses were contemplated by Hess at the time the contract was made.

General damages are those which naturally and necessarily flow from a wrongful act, are so usual an accompaniment of the kind of breach alleged that the mere allegation of the breach gives sufficient notice, and are conclusively presumed to have been foreseen or contemplated by the party as a consequence of his breach of contract. Special damages arise naturally but not necessarily from the breach, are so unusual as to normally vary with the circumstances of each individual case, and must be shown to have been contemplated or foreseen by the parties. Sherrod v. Bailey, 580 S.W.2d 24, 28 (Tex.Civ.App.--Houston [1st Dist.] 1979, writ ref'd n.r.e.); Anderson Dev. Corp. v. Coastal States, etc., 543 S.W.2d 402, 405 (Tex.Civ.App.--Houston [14th Dist.] 1976, writ ref'd n.r.e.); Sterling Projects, Inc. v. Fields, 530 S.W.2d 602, 605 (Tex.Civ.App.--Waco 1975, no writ).

In our opinion, the damage award of $24,065.00 is properly characterized at an item of general damages. Hess contracted to replace an existing mold which American was actively using in its manufacturing process. It should have been clearly foreseeable to Hess that if it failed to supply a suitable new mold to American within the time specified, American would be forced to obtain said mold from another manufacturer in order to meet its commitments to its customers. The time limit specified in the contract was only eighteen weeks, while a period of fourteen months eventually passed before American abandoned its efforts with Hess and contracted with another supplier.

We note that the procurement of substitute goods is a remedy specifically provided a buyer after the seller breaches a contract to deliver goods, under § 2.712, Tex.Bus. & Com.Code Ann. (Vernon 1968). That section provides:

Section 2.712. "Cover"; Buyer's Procurement of Substitute Goods

(a) After a breach within the preceding section the buyer may "cover" by making in good faith and without unreasonable delay any reasonable purchase of or contract to purchase goods in substitution for those due from the seller.

(b) The buyer may recover from the seller as damages the difference between the cost of cover...

To continue reading

Request your trial
9 cases
  • Homes v. Carns
    • United States
    • Texas Court of Appeals
    • 14 Febrero 2001
    ...presumed to have been foreseen or contemplated by the party as a consequence of his breach of contract. Hess Die Mold, Inc. v. American Plasti-Plate Corp., 653 S.W.2d 927, 930 (Tex. App.--Tyler 1983, no writ). Special damages arise naturally but not necessarily from the breach, are so unusu......
  • U.S. ex rel Cmc Steel Fabricators v. Harrop Const.
    • United States
    • U.S. District Court — Southern District of Texas
    • 21 Diciembre 2000
    ...presumed to be foreseen or contemplated by the party as a consequence of his breach of contract." Hess Die Mold, Inc. v. American Plasti-Plate Corp., 653 S.W.2d 927, 929 (Tex.App. — Tyler 1983, no writ); see also Arthur Andersen & Co. v. Perry Equip. Corp., 945 S.W.2d 812, 816 (Tex.1997). C......
  • Akib Constr. Inc. v. Shipwash
    • United States
    • Texas Court of Appeals
    • 1 Agosto 2019
    ...Archer v. DDK Holdings, LLC , 463 S.W.3d 597, 609 (Tex. App.—Houston [14th Dist.] 2015, no pet.) (quoting Hess Die Mold, Inc. v. Am. Plasti-Plate Corp. , 653 S.W.2d 927, 929 (Tex. App.—Tyler 1983, no writ) ); Airborne Freight Corp. v. C.R. Lee Enters., Inc. , 847 S.W.2d 289, 296 (Tex. App.—......
  • Lambert v. Coachmen Industries of Texas, Inc., C14-87-813-CV
    • United States
    • Texas Court of Appeals
    • 3 Noviembre 1988
    ...statement of facts. Goodin v. Geller, 521 S.W.2d 158, 159 (Tex.Civ.App.--Waco 1975, writ ref'd n.r.e.); See Hess Die Mold, Inc. v. American Plasti-Plate Corp., 653 S.W.2d 927, 930 (Tex.App.--Tyler 1983, no writ). The reviewing court must presume that sufficient evidence was introduced to su......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT