Hospital Mortg. Group v. First Prudential Development Corp., 60156

Decision Date04 March 1982
Docket NumberNo. 60156,60156
Citation411 So.2d 181
PartiesHOSPITAL MORTGAGE GROUP, etc., Petitioner, v. FIRST PRUDENTIAL DEVELOPMENT CORP., et al., Respondents.
CourtFlorida Supreme Court

Edward A. Perse of Horton, Perse & Ginsberg; and the Law Offices of Malspeis, Lococo, Brown & Schwartz, Miami, for petitioner.

John H. Lewis, and Stanley J. Mann of Mann, Dady, Corrigan & Zelman, Miami, for respondents.

McDONALD, Justice.

This case is before us on a petition to review a decision of a district court, reported at 390 So.2d 767 (Fla. 3d DCA 1980). Because that decision conflicts with Thomson v. Kyle, 39 Fla. 582, 23 So. 12 (Fla.1897), we have jurisdiction. Art. V, § 3(b)(3), Fla.Const. We disapprove the district court decision.

The issue here is whether a prospective borrower, in an action for damages against a lender for its premature withdrawal of a commitment to loan funds, must prove that it had, or could have, fulfilled the conditions required under the contract to close the loan.

Petitioner, Hospital Mortgage Group, a trust, is in the business of lending money. It was the defendant and appellee below. Respondents are real estate developers who were the plaintiffs and appellants below. On November 27, 1973 the parties entered into two agreements, identical mortgage commitments, to provide financing for the construction of motels in Augusta, Georgia, and Rock Hill, South Carolina.

The commitments contained a number of requirements to be met by respondents and stated that the commitments "expired" on December 12, 1973. The documents that respondents were responsible for were to meet the approval of the lender's attorney.

The December 12th expiration date passed without the respondents complying. The parties met on December 31, 1973 and agreed to extend the commitments although they did not set a new expiration date. Work on the closing continued until April 27, 1974 when petitioner advised the respondents that the commitments were terminated. By letter dated May 7, 1974 petitioner outlined respondents' failure to comply in furnishing the documents and the passage of time as the reasons for termination. The documents that had been furnished by the respondents were returned.

Unable to find another lender, respondents leased the properties and brought suit for breach of contract damages. The trial was on liability only, and the trial court found that the lender "did not effectively terminate the two commitments" and that the borrower had not complied with the conditions precedent to the contracts. The court then granted the respondents thirty days to complete submission of the documents or else the lender's commitments would be terminated.

The respondents appealed stating that because five years had passed since the termination it was impossible to comply. The district court reversed, finding that an anticipatory repudiation by petitioner obviated the respondents' duty to tender all of the documents. The petitioner asserts that the termination was due to the respondents' inability to obtain the required documents, and, therefore, respondents were not "ready, willing and able" to comply. The original commitment was for sixteen days, and the extended time ran for almost nineteen weeks.

The district court correctly found that the petitioner-lender had committed an anticipatory repudiation when it unequivocally terminated the two agreements. The correct way to terminate a contract after an extension to which no new termination date is fixed is to give the parties notice and a reasonable amount of time to attempt compliance. See Felt v. Morse, 80 Fla. 154, 85 So. 656 (Fla.1920); Sound City, Inc. v. Kessler, 316 So.2d 315 (Fla. 1st DCA 1975).

In dealing with anticipatory repudiations the law is clear that a repudiation gives rise to a claim for damages by the nonbreaching party. As stated in Restatement (Second) of Contracts § 253 (1979):

(1) Where an obligor repudiates a duty before he has committed a breach by non-performance and before he has received all of the agreed exchange for it, his repudiation alone gives rise to a claim for damages for total breach.

(2) Where performances are to be exchanged under an exchange of promises, one party's repudiation of a duty to render performance discharges the other party's remaining duties to render performance.

Therefore, the nonbreaching party is relieved of its duty to tender performance and has an immediate cause of action against the breaching party. Poinsettia Dairy Products, Inc. v. Wessel Co., 123 Fla. 120, 166 So. 306 (Fla.1936). This alone, however, does not entitle the nonbreaching party to damages. Anticipatory repudiation obviates the requirement that the conditions be performed, but not that they be performable.

As stated in the Restatement (Second) of Contracts § 254 (1979):

(1) A party's duty to pay damages for total breach by repudiation is discharged if it appears after the breach that there would have been a total failure by the injured party to perform his return promise.

The term "total failure" is defined in the comment to this section as:

A failure is total in this context if it would have been sufficient to have discharged any remaining duties of the party in breach to render his performance. See § 242. The result follows even if it appears that the failure would have been justified and not a breach. Cf. § 244.

Id. at comment a (1979).

This reasoning is in accord with Thomson v. Kyle, 39 Fla. 582, 23 So. 12 (Fla.1897), and Slaughter v. Barnett, 114 Fla. 352, 154 So. 134 (Fla.1934), requiring compliance with the contract provisions. In those decisions performance or...

To continue reading

Request your trial
58 cases
  • In re Standard Jury Instructions—Contract & Business Cases
    • United States
    • Florida Supreme Court
    • June 6, 2013
    ...is excused from establishing performance if the defendant anticipatorily repudiated the contract. Hosp. Mortg. Grp. v. First Prudential Dev. Corp., 411 So.2d 181, 182–83 (Fla.1982). Repudiation constituting a prospective breach of contract may be evidenced by words or voluntary acts but ref......
  • Robinson v. State Farm Fire & Cas. Co., 90-367
    • United States
    • Florida District Court of Appeals
    • July 3, 1991
    ...coverage, State Farm's anticipatory repudiation obviated the necessity that Lockley tender payment. Hospital Mortgage Group v. First Prudential Development Corp., 411 So.2d 181 (Fla.1982). * * * * * Genuine issues of material fact and conflicting inferences exist in this case as to whether ......
  • IN RE MAXKO PETROLEUM, LLC
    • United States
    • U.S. Bankruptcy Court — Southern District of Florida
    • March 12, 2010
    ...to perform under the contract and creates an immediate cause of action for breach of contract. Hospital Mortgage Group v. First Prudential Development Corp., 411 So.2d 181, 182 (Fla.1982); Twenty-Four Collection, Inc. v. M. Weinbaum Construction, Inc., 427 So.2d 1110, 1111 (Fla. 3d DCA 1983......
  • U.S. Home Corp. v. Suncoast Utilities, Inc.
    • United States
    • Florida District Court of Appeals
    • June 29, 1984
    ...became liable to Suncoast for damages for its anticipatory breach of these latter projects. See Hospital Mortgage Group v. First Prudential Development Corp., 411 So.2d 181, 182 (Fla.1982); Mori v. Matsushita Electric Corp., 380 So.2d 461, 465 (Fla. 3d DCA), cert. denied, 389 So.2d 1112 (Fl......