Houdaille-Duval-Wright Co. v. Charldon Const. Co.

Decision Date01 August 1972
Docket NumberNo. 71--956,HOUDAILLE-DUVAL-WRIGHT,71--956
Citation266 So.2d 106
PartiesCOMPANY, a division of Houdaille Industries, Inc., Appellant, v. CHARLDON CONSTRUCTION COMPANY et al., Appellees.
CourtFlorida District Court of Appeals

Rogers, Morris & Ziegler, Fort Lauderdale, for appellant.

Wepman & Wepman, and Hugh F. Quinn III, Miami, for appellees.

Before CHARLES CARROLL, HENDRY and HAVERFIELD, JJ.

PER CURIAM.

Appellant, the plaintiff below, as a subcontractor on an apartment building project, fabricated and delivered concrete roof spans which were incorporated in the building. Claiming a balance of $36,872.96 to be due, of its subcontract price of $86,435.19, the plaintiff filed an action for foreclosure of a lien therefor against the owners and the surety on a bond to which its lien had been transferred, and joined the contractor as a defendant. The plaintiff alleged empoyment of attorneys to prosecute the action and its obligation to pay them reasonable attorney fees, for which plaintiff also sought recovery.

The defendant owners answered, averring they were without knowledge as to the allegations of the complaint and demanding strict proof thereof. The defendant contractor did likewise, and incorporated in his answer a counterclaim alleging delay in delivery of the materials and claiming damages therefor in the amount of $90,700.

When the cause came to trial, the right of the plaintiff to its claimed lien for the amount sought was not further contested and was conceded. On trial of the issues on the counterclaim the court found, in favor of the counterclaimant, that there was a 33-day delay in delivery by plaintiff, and allowed the counterclaimant $43,049.60 damages therefor. Judgment was entered in favor of the counterclaimant against the plaintiff for $6,176.64, representing the excess of its damages over the amount due the plaintiff on its lien claim. Thereupon the judgment discharged the principal and surety on the lien bond. By a later order the court awarded $8,500 to the counterclaimant (contractor) as fees for the services of its attorneys, and $853.59 costs, for which a further judgment was entered in favor of the contractor against the plaintiff for the aggregate sum of $9,353.59.

This appeal by the plaintiff presents a number of contentions, which have been considered by this court in the light of the record and briefs. We find no sufficient reason in law has been shown to disturb the holding of the trial court regarding the delay occasioned by the appellant, and that the counterclaimant was entitled to damages therefor. We find merit in appellant's contention that the damages awarded to the contractor on the counterclaim were excessive, based on the record. The damage figure of $44,549.60 fixed by the trial court was the gross payroll of the contractor (at $1,340 per day) for the period of delay. The principal argument of the appellant in support of its contention that the damages were excessive is that it was shown in evidence that the contractor's employees on the job were productively engaged on the project a substantial part of the period in which delivery of materials by the plaintiff was delayed. Examination of the record shows it sustains the appellant in that regard. Also, as pointed out by appellant, it appears that there was not a total absence of delivery during the 33-day delay period; that some of such materials were delivered and...

To continue reading

Request your trial
6 cases
  • Guthartz v. Lewis
    • United States
    • Florida District Court of Appeals
    • December 8, 1981
    ...(1977). Cf., e.g., Mershon v. Buckles-Thompson, Inc., 383 So.2d 280 (Fla. 5th DCA 1980); Houdaille-Duval-Wright Company v. Charldon Construction Company, 266 So.2d 106 (Fla.3d DCA 1972); Bieley v. Jennings Construction Corporation, 212 So.2d 809 (Fla.3d DCA 1968) (holding that a statute pro......
  • Service Ins. Co. v. Gulf Steel Corp., 81-1419
    • United States
    • Florida District Court of Appeals
    • April 21, 1982
    ...an action which relates to the cause of action to enforce the lien. E.g., Jackson v. Hatch, supra; Houdaille-Duval-Wright Co. v. Charldon Construction Co., 266 So.2d 106 (Fla. 3d DCA 1972). Appellee had no interest in the proceedings after the satisfaction of the final summary judgment. The......
  • Jackson v. Hatch
    • United States
    • Florida District Court of Appeals
    • January 25, 1974
    ...prevailing party should be entitled to collect his attorney's fees for all aspects of the case. See Houdaille-Duval-Wright Co. v. Charldon Construction Co., Fla.App.3rd, 1972, 266 So.2d 106. Applying these principles to the instant case, attorney's fees should be awarded only with respect t......
  • Ferrell v. Ashmore, BN-168
    • United States
    • Florida District Court of Appeals
    • May 14, 1987
    ...and that the owner was therefore the prevailing party and entitled to a fee under the statute. In Houdaille-Duval-Wright Co. v. Charldon Construction Co., 266 So.2d 106 (Fla. 3rd DCA 1972), a subcontractor, who had fabricated and delivered concrete roof spans to the job site, filed a mechan......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT