Sacor Financial, Inc. sued Harry A. Houghton III, alleging that Houghton owed it monies stemming from unpaid credit card charges. Sacor filed a motion for summary judgment, which the trial court granted. In this appeal, Houghton contends that the trial court erred because, inter alia, there was evidence that suit was not timely commenced. We agree with Houghton that, given such evidence, summary judgment was not authorized. Therefore, we reverse.

Summary judgment is properly granted “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law[.]1 “In our de novo review of the grant of a motion for summary judgment, we must view the evidence, and all reasonable inferences drawn therefrom, in the light most favorable to the nonmovant.”2

On June 15, 2012, Sacor filed a two-paragraph complaint against Houghton, alleging therein that Defendant is indebted to Plaintiff in the sum of $16,295.88 principal, plus interest, on an account.” More than a year later, Sacor filed an affidavit that service of process had been effected upon Houghton on September 10, 2013. Amongst the defenses raised by Houghton in his answer was that Sacor's suit was time-barred.

In April 2015, Sacor filed a motion for summary judgment. In its supporting brief, Sacor expressly identified its cause of action as breach of contract, outlining its theory of liability as follows:

[Houghton] applied for and received a [Circuit City Rewards] credit card account from [Sacor's] Assignor, Chase Bank USA, N.A. This credit card account was opened and activated for [Houghton's] use and benefit and was designated as Account No. **9044. Upon receipt of the Circuit City Rewards credit card, [Houghton] proceeded to make charges on the account for an extended period of time. Pursuant to the underlying cardholder agreement, [Sacor's] Assignor would send monthly statements to [Houghton] detailing the status and history of the account, as well as the balance owed at the end of each monthly billing cycle . Upon receipt of the statement, [Houghton] would be required to at least submit the minimum payment, which fluctuated depending on the balance owed and other factors. The credit extended by [Sacor's] Assignor was done so with the express intent that [Houghton] would make at least the minimum payment due each month and that [Houghton] would eventually pay the debt in full. Despite [Sacor's] Assignor's policy concerning the minimum payment due at the end of each monthly billing cycle, [Houghton] failed to make these payments, constituting a material breach of the underlying cardholder agreement and rendering [Houghton] in material default of the contract . As a result of the default, [Houghton's] account was formally declared in default and charged-off by the original creditor. At the time of the charge-off, [Houghton's] entire balance in default became immediately due and payable. At the time of the charge-off, the unpaid balance in default on the credit card account was $16,295.88, please see [Sacor's] Affidavit of Claim and Exhibit “A” attached thereto.[3 ] Since the time of the charge-off, interest was accrued on this principal balance at the rate of 26% per annum, through the time of the filing of this Motion, in the amount of $15,985.95.... [Houghton's] contract and account with Chase Bank USA, N.A. was validly and completely assigned to [Sacor], and [Sacor] has been assigned all rights, title, and interest to the contract. A true and correct copy of the Assignment charting the chain of title is attached to [Sacor's] Affidavit of Claim as Exhibit “B,” filed herewith.[4 ]

Sacor stated in its brief, “With this Motion for Summary Judgment, [Sacor] seeks the principal balance of $16,295.88 as damages, along with interest of $15,985.95 and court costs of $178.00.”

Opposing Sacor's motion, Houghton advanced, inter alia, his statute of limitation defense. According to Houghton, Sacor's breach of contract action was subject to either a four-year or a six-year statute of limitation;5 and even if the longer period applied, Houghton argued, Sacor's own evidence authorized a finding that the action was untimely.

But three days after Houghton filed his response, the trial court entered an order drafted by Sacor's counsel, summarily finding “no genuine issues of material fact,” thus granting Sacor's motion, and thereby holding Houghton liable “for the principal sum of $16,295.88, interest of $15,985.95, and court costs of $178.00.”

1. Houghton contends that, in light of evidence that suit was time-barred, the trial court erred in granting Sacor's motion.

(a) “The elements for a breach of contract claim in Georgia are the (1) breach and the (2) resultant damages (3) to the party who has the right to complain about the contract being broken.”6 Citing

Hill v. American Express

,7 Sacor asserts that [t]he statute of limitations in a credit card action is six (6) years.”

In Hill

,8 American Express sued one of its cardholders to recover unpaid credit card charges.9 At issue there was whether such claim was subject to a four-year limitations period (set forth in OCGA § 9–3–25 ) or to a six-year limitations period (set forth in OCGA § 9–3–24 ).10 Determining that the claim was subject to the latter, Hill noted that “American Express has submitted a copy of the contract between the cardholder and the Bank”;11

Hill went on to explain, “In this case, there is a simple contract in writing. That the contract was agreed to [by the cardholder], not by signature, but by use of the card does not take it out of OCGA § 9–3–24.”12

According to Sacor's theory of liability, [Houghton] applied for and received a [Circuit City Rewards] credit card account from [Sacor's] Assignor, Chase Bank USA, N.A. But Sacor has cited nothing in the record as the underlying written contract between Houghton and Chase Bank USA, N.A.—or any other bank. Even accepting arguendo Sacor's apparent assertion that its breach of contract action is governed by OCGA § 9–3–24

, we agree with Houghton that the evidence of record demonstrates that summary judgment was not proper.

“Under OCGA § 9–3–24

, an action for breach of a written contract must be brought within six years of the breach.”13 Notably, Sacor did not allege any precise date when Houghton breached the underlying credit card contract he made with Chase Bank USA, N.A. Notwithstanding, as Sacor outlined in its theory of liability, it was Houghton's failure to make payments as demanded in monthly billing statements that “constitut[ed] a material breach of the underlying cardholder agreement and render[ed] [Houghton] in material default of the contract.” As Houghton described in opposing Sacor's motion, Sacor presented “a smattering of account statements” that demanded payments from Houghton—the most recent of which set forth a payment due date of May 5, 2006.14 To the extent that the record authorized a finding that Houghton did not make that payment,15 the record further authorized a finding that Houghton was then in breach of the underlying credit card contract. Sacor's complaint was not filed, however, until June 2012. Given such evidence that Sacor's breach of contract action was not commenced within six years of the breach, the trial court was not authorized to hold Houghton liable as a matter of law.16

(b) Although Sacor advanced two arguments in an effort to preserve its favorable ruling, neither has merit.

(i) First, Sacor argues that it adduced evidence establishing that the applicable six-year period did not begin to run until April 4, 2012. Specifically, Sacor cites that after being assigned rights with respect to Houghton's credit card contract,17 it sent Houghton a billing statement advising him that he owed to it $16,295.88 and that the full amount was due on April 4, 2012.18 Relying on other evidence that Houghton did not comply with its demand, Sacor posits, “the statute of limitation did not begin to run until, at the earliest, April 4, 2012,” and that its action was thereafter timely commenced.

Sacor's argument disregards applicable law of assignments: “The assignee acquires all of the rights and remedies possessed by the assignor at the time of the assignment, and takes the obligation, contract, chose, or other thing assigned subject to the same restrictions, limitations, and defects as it had in the hands of the assignor .”19 Simply stated, “an assignee ‘stands in the shoes' of the assignor and obtains no greater rights than the assignor possessed at the time of assignment.”20 Accordingly, Sacor did not obtain—by designating a later date for Houghton to pay it a certain amount—a new limitations period that would commence upon Houghton's failure to comply.21

(ii) Sacor next argues that it was entitled to prevail on its motion because Houghton presented neither an “affidavit [n]or any other evidence in support of [his] opposition to Sacor's claim and Motion.”

This argument disregards applicable law of summary judgment: There is “no such thing as a default summary judgment.”22 Although Houghton did not file any responsive material, it did not “automatically follow that [Sacor's] motion should be granted.”23 “A motion for summary judgment should not be granted unless it affirmatively appears from the pleadings and evidence that the party so moving is entitled to prevail.”24Summary judgments enjoy no presumption of correctness on appeal, and an appellate court must satisfy itself de novo that the requirements of OCGA § 9–11–56(c)

have been met.”25 As explained above, the record reveals that summary judgment was not...

To continue reading

Request your trial
10 cases
  • Roberts v. JP Morgan Chase Bank, Nat'l Ass'n, A17A0138
    • United States
    • Georgia Court of Appeals
    • June 27, 2017
    ...right to complain about the contract being broken." (Citation, punctuation, and footnotes omitted.) Houghton v. Sacor Financial, Inc ., 337 Ga. App. 254, 256 (1) (a), 786 S.E.2d 903 (2016). The security deed Roberts executed in favor of Chase contained a power of sale and was thus "a contra......
  • Callaway Blue Springs, LLLP v. W. Basin Capital, LLC.
    • United States
    • Georgia Court of Appeals
    • June 5, 2017
    ...behalf of someone else.30 Golshani, 334 Ga.App. at 181 (1) (b), 778 S.E.2d 805 (emphasis supplied).31 Houghton v. Sacor Fin., Inc., 337 Ga.App. 254, 258 (1) (b) (i), 786 S.E.2d 903 (2016) (punctuation omitted); accord S. Telecom, Inc. v. TW Telecom of Ga. L.P., 321 Ga.App. 110, 114 (3), 741......
  • Cohen v. Rogers
    • United States
    • Georgia Court of Appeals
    • July 14, 2016
    ...so moving is entitled to prevail.” (Punctuation and footnote omitted.) Houghton v. Sacor Financial , 337 Ga.App. 254, ––––, 786 S.E.2d 903, 2016 WL 3068407, *4 (1) (b) (ii) (Case Number A16A0009, decided May 31, 2016). See also Hall v. Massally , 329 Ga.App. 136, 138, 764 S.E.2d 161 (2014) ......
  • In re Deotare
    • United States
    • U.S. District Court — Northern District of Georgia
    • March 26, 2018
    ...damages (3) to the party who has the right to complain about the contract being broken." Houghton v.Page 12 Sacor Financial, Inc., 786 S.E.2d 903 (Ga. Ct. App. 2016) (internal citations omitted). Whether Wells Fargo breached the Account Agreement turns on the duties imposed by the agreement......