George Robertson for appellant.

(1) The evidence of the plaintiff was too indefinite and uncertain upon which to base a verdict. (2) The title of the bridge was not in the county. (Session Acts, 1851, page 337). (3) Plaintiff's cause of action was barred by the statutes of limitations. R. S. 1889, sec. 6775; Powers v. Council Bluffs, 45 Iowa 652; James v. Kansas City, 83 Mo. 567; Peden v. Railroad, 73 Iowa 328.

Sam C Major and Draffen & Williams for respondent.

(1) The appellant makes three points for the reversal of this case. The first is that the evidence is too indefinite and uncertain to base a verdict upon. It is sufficient to say that there was substantial evidence to support each allegation of the petition. The trial court, under the declarations of law given, must have found that the facts were as alleged by plaintiff, and this is now no longer an open question. The weight of the evidence was for the court below. Skinker v. Haagsma, 99 Mo. 208; Pike v Martindale, 91 Mo. 268. (2) The objection, that the title to the bridge was not in Howard county, is not well taken. The county had been in possession, claiming ownership for more than twenty-five years before this suit. It had made repairs upon this bridge, and had been using it as part of the public road. This suit was brought for damages to the pier that was built and paid for by the county. This was certainly sufficient against a wrongdoer. Hazard Powder Co. v. Volger, 7 C. C. A. 130. (3) While the obstructions were thrown into the stream, and the current of the creek thereby changed, in 1885, so that the waters then began to flow against the pier of plaintiff's bridge, yet the actual and material injury was not suffered by the plaintiff until within five years before the suit was brought. The court below properly ruled that the statute did not begin to run until actual and substantial damages were sustained. The period of limitation does not begin to run until actual injury is suffered. 2 Wood on Limitations, p. 457, sec. 180; 3 Sutherland on Damages [2 Ed.], p. 2273; Wells v. Railroad, 23 N.E. 724; Dickinson v. Railroad, 71 Mo. 575; Mangold v. Railroad, 24 Mo.App. 52; Culver v. Railroad, 38 Mo.App. 130; McElroy v. Goble, 5 Ohio St. 187; Gould on Waters, sec. 210, et seq.

Brace P. J. Robinson, J., absent.

OPINION

Brace, P. J.

This is an action for damages instituted by the plaintiff on the twentieth of June, 1893, in the Howard county circuit court, in which the plaintiff obtained judgment for $ 599 and the defendant appeals.

The gravamen of the charge contained in the petition, is that the defendant, on or about the fifteenth day of August, 1885, threw large quantities of rock and other substances into the bed of Doxey creek in said county, over which the plaintiff had a bridge, at a point in said stream a short distance above said bridge and thereby deflected the current of said stream from the natural course in which it was accustomed to flow, to and against the north pier of plaintiff's bridge, thereby undermining said pier, whereby said bridge was in the year 1892 greatly injured and damaged and plaintiff was compelled to lay out and expend a large sum of money in repairing the injuries thereto so caused by defendant. The answer was a general denial and a plea of the statute of limitations.

The defendant asks a reversal of the judgment on three grounds: First, that the title of the bridge was not in the county; second, that the evidence of the plaintiff was too indefinite and uncertain on which to base a verdict; and, third, that plaintiff's cause of action was barred by the statute of limitations.

It appears from the evidence that the bridge in question was originally built and owned by the Glasgow and Huntsville Plank Road Company; that in July, 1865, the company transferred its road and bridges in Howard county to said county, and the evidence tends to prove, that ever since such transfer the bridge in question has been used, controlled and managed as a county bridge by said county as a part of one of its county roads; that in the year 1885 the bridge became out of repair, and the county rebuilt the pier in question at the expense of the county; that this pier was some distance from the natural channel of the stream; that about the same time, the defendant was engaged in building a bridge across said stream a short distance above the county bridge; that in doing so its servants deposited rock, and other obstructions in the stream that caused the channel to change from its natural course so that the current ran against the pier of the county bridge, which but for such obstructions it would not have done; that this change in the current became apparent soon after the pier was completed in August 1885; that substantial injury to the pier therefrom was noticed in 1890, and...