Howard W. Heck and Associates, Inc. v. U.S.

Decision Date23 January 1998
Docket NumberNo. 97-5064,97-5064
Citation134 F.3d 1468
Parties, 28 Envtl. L. Rep. 20,630 HOWARD W. HECK, AND ASSOCIATES, INC., Plaintiff-Appellant, v. The UNITED STATES, Defendant-Appellee.
CourtU.S. Court of Appeals — Federal Circuit

Kevin J. Coakley, Connell, Foley & Geiser LLP, of Roseland, New Jersey, argued for plaintiff-appellant. With him on the brief was Tricia Bevelock O'Reilly.

Thomas L. Halkowski, Attorney, Environment & Natural Resources Division, U.S. Department of Justice, of Washington, D.C., argued for defendant-appellee. With him on the brief were Lois J. Schiffer, Assistant Attorney General, and Martin W. Matzen, Attorney. Of counsel on the brief was Barry E. Gale, Attorney, U.S. Army Corps of Engineers, Philadelphia District, of Philadelphia, Pennsylvania.

Before MAYER, Chief Judge, * RICH and MICHEL, Circuit Judges.

MICHEL, Circuit Judge.

Howard W. Heck, and Associates, Inc. ("Heck") appeals the judgment of the Court of Federal Claims, 37 Fed.Cl. 245 (1997), dismissing its complaint and holding that the court lacked jurisdiction over Heck's Fifth Amendment taking claim 1 because the claim was not ripe for adjudication. Because the Army Corps of Engineers ("Corps") made no decision on the merits of Heck's application for a wetlands dredge-and-fill permit but removed the application from active consideration

due to Heck's unexcused failure to submit the statutorily-required state water quality certificate ("WQC") to support its federal permit application, we affirm.

BACKGROUND

In order to expand Heck's existing residential development in Farmingdale, New Jersey, Heck applied to the Corps for a Clean Water Act ("CWA") section 404 permit 2 on April 5, 1991, to discharge, dredge, and fill 13 acres of wetlands within Heck's 24 acre parcel of property. A WQC from the State of New Jersey, or a waiver by the Corps of such, was a statutory prerequisite for the Corps to issue a section 404 permit. See 33 U.S.C. § 1341 (1994); 33 C.F.R. § 325.2(b)(1)(ii) (1996).

Heck had submitted a WQC application to the New Jersey Department of Environmental Protection ("NJDEP") on January 3, 1989. On February 16, 1989, the NJDEP responded by letter to Heck requesting, among other things, submission of a complete discussion of alternatives (an "alternatives analysis") for the proposed project. 3 Heck responded that

the property could not physically be developed without removal of vegetation, grading and fill for proper drainage purposes. Accordingly, there is no other alternative to the approved residential project, other than to allow the land to remain idle and vacant.

37 Fed.Cl. at 247. In December 1989, the NJDEP again notified Heck that its alternatives analysis was still incomplete and specified that

[a]lternatives are to include both on and off-site considerations. On-site alternatives would include minimizing water quality impact through the minimization of discharge and fill, and/or total avoidance of wetland impact. The consideration of off-site alternatives must also be demonstrated. The Division does not consider ownership of a particular property as reason to reject alternative sites. A complete alternatives analysis must be submitted prior to further review of this application.

Id.

At that point, a disagreement ensued which continued over a three year period between Heck and the NJDEP about the legal basis upon which the NJDEP could require this alternatives analysis. Heck also argued to the NJDEP that because its application had been filed over a year previously, the WQC requirement should be presumed waived. Heck's argument was based on section 401 of the CWA which presumes waiver for purposes of a federal application when a state does not act upon a WQC application within one year. See 33 U.S.C. § 1341(a)(1). On December 16, 1992, however, having not received an alternatives analysis from Heck in over three years, the NJDEP canceled Heck's WQC application.

While trying to secure a WQC from the State of New Jersey, Heck proceeded with the section 404 permit process before the Corps. During the process, the Corps requested and Heck provided additional information, and in October 1992, the Corps notified Heck that the application had been sent out for public notice and reminded Heck of its responsibility to obtain state approval and a WQC from the NJDEP. In response to the public notice, the Corps received comments from the Environmental Protection Agency ("EPA") and the Department of the Interior ("DOI"), both of whom expressed the opinion that Heck's proposed development would violate the CWA.

In November 1992, Heck argued to the Corps that, because NJDEP had failed to act upon its application within one year, the Corps should deem the requirement of a WQC waived by the State of New Jersey. However, because the NJDEP timely reviewed but ultimately canceled Heck's WQC Instead of re-filing a permit application with the Corps, however, Heck filed a Fifth Amendment taking claim in the Court of Federal Claims. The court, in granting the government's motion to dismiss for lack of jurisdiction, held that Heck's claim was not ripe for adjudication. See Heck, 37 Fed.Cl. at 246. The court found that Heck's claim was not ripe because the Corps never issued a final decision on the merits but instead removed Heck's application from active status for failure to include a state WQC. Id. at 250. The court also held that neither the negative comments from the EPA and the DOI nor the requirement of an alternatives analysis rendered the section 404 permit process futile as to Heck within the meaning of the case law because the Corps has issued permits to other applicants despite similar allegedly insurmountable obstacles. See id. at 252.

application, the Corps notified Heck by letter dated January 8, 1993 that the Corps could not waive the requirement of a state WQC 4 and that Heck's section 404 application was being withdrawn from active status until Heck submitted the WQC. The Corps removed the application from active status without prejudice on December 16, 1993.

Furthermore, the court stated that it was the wrong forum to address Heck's challenges under the Administrative Procedure Act to either the NJDEP's decision requiring the alternatives analysis or to the Corps' decision not to waive the WQC requirement. See id. at 255. This timely appeal followed.

DISCUSSION
I.

We review de novo whether the Court of Federal Claims possessed jurisdiction. Wheeler v. United States, 11 F.3d 156, 158 (Fed.Cir.1993). The Supreme Court specifically has held that taking claims arising from the application of government regulations are not ripe until the government entity charged with implementing the regulations has reached a final decision applying the regulations to the property at issue. See MacDonald, Sommer & Frates v. Yolo County, 477 U.S. 340, 351, 106 S.Ct. 2561, 2567, 91 L.Ed.2d 285 (1986) ("[A]ppellant still has yet to receive the Board's 'final, definitive position regarding how it will apply the regulations at issue to the particular land in question.' " (quoting Williamson County Reg'l Planning Comm'n v. Hamilton Bank, 473 U.S. 172, 191, 105 S.Ct. 3108, 3118-19, 87 L.Ed.2d 126 (1985))); see also United States v. Riverside Bayview Homes, Inc., 474 U.S. 121, 127, 106 S.Ct. 455, 459, 88 L.Ed.2d 419 (1985) ("Only when a permit is denied and the effect of the denial is to prevent 'economically viable' use of the land in question can it be said that a taking has occurred."). Accordingly, the dispositive question before us in this appeal is whether the Corps' withdrawal of Heck's section 404 permit application from active status for failure to complete the application by including the statutorily-required state WQC constitutes a merits decision by the Corps. We hold it does not.

II.
A. State Certification Is a Prerequisite For a Final Decision by the Corps and Hence for Judicial Review

The CWA specifically makes submission by the applicant of certification by the state in which the discharge will originate a prerequisite for issuance by the Corps of a section 404 permit. 33 U.S.C. § 1341 (1994). The reason, as the legislative history indicates, is to maintain the particular state's water quality standard which may be higher than that established federally by the CWA. S.Rep. No. 92-414, at 69 (1971), reprinted in 1972 U.S.C.C.A.N. 3668, 3735. Should the state refuse to give its approval, the provisions of 33 C.F.R. § 320.4(j) grant the Corps discretion to deny the permit without prejudice. Here, however, the State of New Jersey did not refuse to give its approval; it canceled the application as incomplete. Similarly, the Corps did not deny the permit. Rather, because Heck failed to obtain a WQC from the State of New Jersey, the Corps removed Heck's application from active status and without prejudice for incompleteness. Nor did the Corps issue a merits-based determination here regarding the proposed development's effect on water quality standards because Heck had not provided the Corps with the information required by law. We therefore hold that the dismissal of the application as incomplete was not a final decision or a decision on the merits. 5

Heck, however, argues that the NJDEP's cancellation of its WQC application constitutes a final decision by the Corps. In order for this argument to succeed, Heck must prove both that (1) the NJDEP made a decision on the merits that denied Heck "economically viable" use of its land, and (2) this state action constitutes a federal taking.

As Heck utterly fails to prove the first requirement, we do not decide the second....

To continue reading

Request your trial
31 cases
  • Chapman v. AI Transport, Nos. 97-8838
    • United States
    • U.S. Court of Appeals — Eleventh Circuit
    • October 2, 2000
    ... ... In July 1985, Chapman began working for Claimsman, Inc., another insurance company, as a senior liability claims ... employer's mental processes," the Supreme Court has told us that "none of this means that trial courts or reviewing ... See Howard, 32 F.3d at 524. In addition to Chapman's testimony in his ... ...
  • Casitas Mun. Water Dist. v. United States
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • February 27, 2013
    ...properly dismissed a complaint for lack of subject matter jurisdiction also is a question of law. Howard W. Heck and Assocs., Inc. v. United States, 134 F.3d 1468, 1471 (Fed.Cir.1998) (citing Wheeler v. United States, 11 F.3d 156, 158 (Fed.Cir.1993)). Finally, the Court of Federal Claims mu......
  • Blue Cross & Blue Shield Carolina v. United States
    • United States
    • U.S. Claims Court
    • April 18, 2017
    ...129 Fed. Cl. 757, 772 (2017); Morris v. United States, 392 F.3d 1372, 1375 (Fed. Cir. 2004) (citing Howard W. Heck & Assocs., Inc. v. United States, 134 F.3d 1468 (Fed. Cir. 1998)). To that end, "[r]ipeness is a justiciability doctrine that prevents the courts, through avoidance of prematur......
  • McGuire v. United States
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • February 20, 2013
    ...with respect to ripeness de novo. See Morris v. United States, 392 F.3d 1372, 1375 (Fed.Cir.2004) (citing Heck & Assocs. v. United States, 134 F.3d 1468, 1471 (Fed.Cir.1998)). The issue of whether McGuire held a compensable property interest is also a “purely legal question” that we review ......
  • Request a trial to view additional results
8 books & journal articles
  • Review of Adverse Decisions
    • United States
    • Wetlands Deskbook Part I. Clean Water Act §404 Programs
    • November 11, 2009
    ...(Fed. Cir. 1991) (tbl.) (even extended time necessary to obtain a permit does not constitute a temporary taking); Heck v. United States, 134 F.3d 1468 (Fed. Cir. 1998) (Corps withdrawal of application for lack of necessary information does not create ripe takings claim); Pax Christi Memoria......
  • List of Case Citations
    • United States
    • Wetlands Deskbook Appendices
    • November 11, 2009
    ...144 Headwaters, Inc. v. Talent Irrigation District, 243 F.3d 526, 31 ELR 20535 (9th Cir. 2001) .......... 31, 32 Heck v. United States, 134 F.3d 1468 (Fed. Cir. 1998) ............................................................... 111 , 114 Hobbs v. United States, 947 F.2d 941, 22 ELR 20331......
  • Wetlands protection
    • United States
    • Introduction to environmental law: cases and materials on water pollution control - 2d Edition
    • July 23, 2017
    ...can become a potent tool to block or force modiications to a proposed § 404 permit. In the following case, Heck v. United States , 134 F.3d 1468 (Fed. Cir. 1998), a developer brought a Fifth Amendment takings claim in the U.S. Court of Federal Claims when the Corps removed his permit applic......
  • List of Case Citations
    • United States
    • Wetlands deskbook. 4th edition Appendices
    • April 11, 2015
    ...176, 190 Headwaters, Inc. v. Talent Irrigation District, 243 F.3d 526 (9th Cir. 2001) ............... 32, 40-41 Heck v. United States, 134 F.3d 1468 (Fed. Cir. 1998) ................................................ 142, 147 Hobbs v. United States, 736 F. Supp. 1406, 20 ELR 21299 (E.D. Va. 1......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT