HRL Union Ave. Corp. v. New York City Housing Authority

Decision Date25 January 1996
Citation636 N.Y.S.2d 792,223 A.D.2d 486
PartiesHRL UNION AVENUE CORPORATION, Plaintiff-Appellant, v. NEW YORK CITY HOUSING AUTHORITY, Defendant-Respondent.
CourtNew York Supreme Court — Appellate Division

T.D. Bradbrooke, for plaintiff-appellant.

S. Krieg, for defendant-respondent.

Before ROSENBERGER, J.P., and NARDELLI, WILLIAMS, TOM and MAZZARELLI, JJ.

MEMORANDUM DECISION.

Order, Supreme Court, New York County (Edward Greenfield, J.), entered January 31, 1995, which granted defendant New York City Housing Authority's motion for summary judgment dismissing the complaint, unanimously affirmed, without costs.

The IAS court, in granting summary judgment in defendant's favor, properly determined that defendant did not anticipatorily breach the parties' contract by advising plaintiff that it would not have the funds necessary to close on April 15, 1987, the closing date projected by plaintiff. The record reveals that plaintiff failed to raise an issue of fact as to a clear and unequivocal intention by defendant not to perform or to abandon the contract, as would be required for a claim of anticipatory breach (see, Tenavision, Inc. v. Neuman, 45 N.Y.2d 145, 150, 408 N.Y.S.2d 36, 379 N.E.2d 1166). In any event, a mere delay in the receipt by defendant of the closing funds from HUD or a late payment does not constitute a refusal to perform or support a finding of abandonment of contract (see, Staebell v. Bennie, 83 A.D.2d 765, 766, 443 N.Y.S.2d 487).

We find that the IAS court also properly granted summary judgment dismissing the causes of action seeking monetary damages for defendant's alleged delay in closing title because plaintiff failed to expressly reserve those delay claims at the closing as specifically required by section 13.06 of the parties' contract (see, Ferran Concrete Co. v. Facilities Dev. Corp., 61 A.D.2d 1061, 402 N.Y.S.2d 651).

Nor was summary judgment in defendant's favor precluded by plaintiff's claim seeking additional compensation for waterproofing. Where, as here, tests by an independent laboratory established that, by reason of water penetration into apartments and public areas, the buildings constructed by plaintiff were not suitable for occupancy, as specifically required by section 1.04 of the parties' contract, plaintiff was therefore required to waterproof the buildings prior to closing, without entitlement to additional compensation, in order to fulfill its contractual obligation to deliver the...

To continue reading

Request your trial
2 cases
  • Partners v. Ajw Qualified Partners Llc
    • United States
    • New York Supreme Court — Appellate Division
    • 12 Abril 2011
    ...( see R.I. Is. House, LLC v. North Town Phase II Houses, Inc., 51 A.D.3d at 895, 858 N.Y.S.2d 372; HRL Union Ave. Corp. v. New York City Hous. Auth., 223 A.D.2d 486, 487, 636 N.Y.S.2d 792; Rachmani Corp. v. 9 E. 96th St. Apt. Corp., 211 A.D.2d at 266–267, 629 N.Y.S.2d 382). Accordingly, the......
  • HRL Union Ave. Corp. v. New York City Housing Authority
    • United States
    • New York Court of Appeals Court of Appeals
    • 7 Mayo 1996
    ...N.E.2d 416 HRL Union Avenue Corporation v. New York City Housing Authority NO. 362 Court of Appeals of New York May 07, 1996 --- A.D.2d ----, 636 N.Y.S.2d 792 MOTION FOR LEAVE TO GRANTED OR DENIED. Denied. ...

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT