Kapourales v. Summit Corp.

Decision Date12 November 1992
Docket NumberNo. 20852,20852
Citation423 S.E.2d 641,188 W.Va. 238
CourtWest Virginia Supreme Court
PartiesSam G. KAPOURALES, d/b/a Kapourales Enterprises, Plaintiff Below, Appellee, v. SUMMIT CORPORATION, Defendant Below, Appellant.

Syllabus by the Court

1. " 'The judgment of a trial court in setting aside a verdict and awarding a new trial is entitled to peculiar weight and its action in this respect will not be disturbed on appeal unless plainly unwarranted.' Syllabus point 3, Young v. Duffield, 152 W.Va. 283, 162 S.E.2d 285 (1968). Syllabus Point 4, Kesner v. Trenton, 158 W.Va. 997, 216 S.E.2d 880 (1975)." Syllabus Point 1, Morris Associates, Inc. v. Priddy, 181 W.Va. 588, 383 S.E.2d 770 (1989).

2. " ' "Questions of negligence, due care, proximate cause and concurrent negligence present issues of fact for jury determination when the evidence pertaining to such issues is conflicting or where the facts, even though undisputed, are such that reasonable men may draw different conclusions from them." Syl. pt. 1, Ratlief v. Yokum , 280 S.E.2d 584 (W.Va.1981), quoting, syl. pt. 5, Hatten v. Mason Realty Co., 148 W.Va. 380, 135 S.E.2d 236 (1964).' Syllabus Point 6, McAllister v. Weirton Hosp. Co., 173 W.Va. 75, 312 S.E.2d 738 (1983). Syl. Pt. 17, Anderson v. Moulder, 183 W.Va. 77, 394 S.E.2d 61 (1990)." Syllabus Point 1, Waugh v. Traxler, 186 W.Va. 355, 412 S.E.2d 756 (1991).

3. " 'A verdict will not be disturbed for want of a proper instruction, unless it was requested and refused....' Syl. pt. 5, Henry C. Werner Company v. Calhoun, 55 W.Va. 246, 46 S.E. 1024 (1904)." Syllabus Point 1, McAllister v. Weirton Hosp. Co., 173 W.Va. 75, 312 S.E.2d 738 (1983).

S. Douglas Adkins, Mundy and Adkins, Huntington, for appellee.

Johnnie E. Brown, Christopher J. Heavens, McQueen and Brown, Charleston, for appellant.

PER CURIAM:

Summit Corporation appeals the order of the Circuit Court of Mingo County, which, after a jury verdict in favor of Summit, granted Sam Kapourales, d/b/a Kapourales Enterprises, a new trial. On appeal, Summit argues that the circuit court erred in granting a new trial because the jury verdict was not against the weight of the evidence and the jury's failure to consider strict liability was not an error because the jury instruction on strict liability was withdrawn. Because the circuit court should not have granted a new trial, we reverse and reinstate the jury verdict in favor of Summit.

In September 1986, Summit, as part of the City of Williamson's project to improve its water and sewer system, began to install a lift station near the intersection of Third Avenue and Dickerson Street. The lift station, a device used to collect and pump the sewage to a treatment plant, was constructed approximately thirty (30) feet from a building owned by Mr. Kapourales. The building, which was purchased by Mr. Kapourales in July 1986, was about 80 years old and was used mainly as a warehouse.

Mr. Kapourales alleges that shortly after the start of the lift station's construction, cracks developed or worsened in the building's walls closest to the lift station. Mr. Kapourales filed suit alleging that the negligent construction of the lift station disturbed the water table, causing the building's foundation to shift, which in turn caused the walls to crack.

During the trial Mr. Kapourales and an employee testified that in July 1986 they inspected the building before Mr. Kapourales purchased it and except for a hairline crack at the top of the building, there were no cracks in the outside walls. Both also testified that shortly after the lift station's construction began, cracks developed in certain places and worsened in others. Mr. Kapourales also said that the ground was severely shaken by pile driving that was part of the lift station's construction. John Messerian, a civil engineer, testified for Mr. Kapourales that the cracks were caused when the construction of the lift station disturbed the water table under the building's foundation. Mr. Messerian said that before starting construction Summit should have tested the soil by core drilling to determine how the lift station would affect the water table and the soil.

Summit maintained that the building's cracks pre-existed the lift station's construction. Summit produced photographs showing that paint from 1983, the last time the building was painted, had dripped into the cracks and the paint extended inside the cracks. One photograph showed a mortar bridge that had been painted crossing the crack. An employee of Summit testified that he had examined the building before the construction began and saw the cracks. The employee also took before and after construction photographs showing that the cracks remained unchanged. Larry Nottingham, Ph.D., a civil engineer specializing in geo-technical engineering, testified that the area's soil was not susceptible to erosion caused by a shifting water table. Noting the paint inside the building's cracks, Dr. Nottingham said that the cracks occurred sometime before the building was painted in 1983. Based on his soil testing and the paint in the cracks, Dr. Nottingham concluded that the construction of the lift station did not cause the building's cracks.

After the jury returned a verdict in favor of Summit, Mr. Kapourales made a motion for a new trial. In considering the motion for a new trial, the circuit court voiced his concerns that "this is a strict liability case" and that an instruction on strict liability was withdrawn because of "off-the-record arm twisting on my [the circuit court's] part." Concluding that the verdict was against the evidence and that an instruction on strict liability should have been given, the circuit court ordered a new trial. Summit then appealed to this Court.

I

An order of the circuit court awarding a new trial will not be reversed unless it is clearly unwarranted. In Syllabus Point 1, Morris Associates, Inc. v. Priddy, 181 W.Va. 588, 383 S.E.2d 770 (1989), we stated:

" 'The judgment of a trial court in setting aside a verdict and awarding a new trial is entitled to peculiar weight and its action in this respect will not be disturbed on appeal unless plainly unwarranted.' Syllabus point 3, Young v. Duffield, 152 W.Va. 283, 162 S.E.2d 285 (1968)." Syllabus Point 4, Kesner v. Trenton, 158 W.Va. 997, 216 S.E.2d 880 (1975).

Summit maintains that the order of the circuit court granting a new trial was clearly...