Lackland v. Renshaw
Decision Date | 17 February 1914 |
Citation | 165 S.W. 314,256 Mo. 133 |
Parties | LACKLAND et al. v. RENSHAW et al. |
Court | Missouri Supreme Court |
Appeal from St. Louis Circuit Court; Jas. E. Withrow, Judge.
Action by Rufus J. Lackland and others, trustees under the will of Henry Shaw, deceased, against Edwin Renshaw and others. From a judgment for defendants, plaintiffs appeal. Reversed and remanded, with directions.
Judson & Green, of St. Louis, for appellants. J. D. Johnson and Loomis C. Johnson, both of St. Louis, for respondent American Surety Co. of New York.
This controversy arises upon a surety bond given to secure plaintiffs against loss by reason of any failure of the defendant contractors to perform their contract to erect a building in St. Louis. The trial court gave judgment for the defendant surety company. The questions presented relate solely to the efficacy of certain facts to release the surety from its obligation. Respondent company is in the business of acting as surety, charging a premium therefor. It had received compensation for becoming surety on the bond in suit.
The defenses and findings upon which the surety was released below will be examined in order. They must be viewed in the light of some applicable general principles.
By the general law of suretyship, evolved at a time when sureties were all of the class whose obligations were entered into from motives of friendship and without pecuniary considerations moving to them, any change in the contract releases the surety, unless made with his consent.
Hill v. American Surety Co., 200 U. S. loc. cit. 202, 26 Sup. Ct. 170, 50 L. Ed. 437.
So far the decisions are in practical accord, though there is a wide divergence of opinion as to the effect and application of those principles.
In this case one ground upon which the surety was held released was that changes had been made in the plans without the surety's consent.
The contract provided: selected in a prescribed manner. The referee's finding on this phase of the case is that alterations in the work were made from time to time but that the architects did not pass upon these changes and determine, before each was made, the sum to be added or deducted on account of it; that the changes were not made upon the written order of the architects, nor was arbitration asked by the contractors. He finds that in July, after the building was nearing completion, the contractors and the representative of plaintiffs, and local superintendent for the architects, went over the building and made a list of changes; having made the list, the parties agreed upon the sums to be added and subtracted. The list of changes and agreed allowances were put in writing and signed by the parties and approved and signed by the architects. The net result was the enhancement of the contract price by $391 and the payment of that additional sum to the contractors. The referee concludes his finding on this branch of the case thus: "So far as the allowances made in this exhibit to the defendants Renshaw, for changes and alterations, are concerned, the referee believes and finds they were fair and reasonable, and not in excess of their true value; but, as already suggested, they were not agreed upon in the manner provided for in the contract." On his view the departures from the contract made were: (1) The failure of the architects to fix the increase or decrease of the contract price before the change was made; (2) that the changes were not made upon the written order of the architect; and (3) that arbitration was not requested by the contractors. By the quoted clause of the contract, the parties had the right to alter the plans, and a fair and reasonable increase or decrease in the contract price was to follow any such alteration. The architects were to determine what increase or decrease was fair and reasonable in each case. That was the extent of the surety's interest. That was done in this case. The contract does not specifically provide that the architects shall make their estimate in advance of the doing of the work under the changed specifications. Such a construction of the first sentence of this paragraph of the contract is merely an inference from the following sentence, the real function of which, however, is to provide a method whereby the contractors can be compelled to proceed in case of a disagreement. In view of the principles above announced, it appears the learned referee applied too strict a rule on this branch of the case. The surety lost nothing, its risk of loss was in no way increased and, in fact, in the end it received the exact protection to which the contract entitled it.
In Chapman v. Eneberg, 95 Mo. App. 127, 68 S. W. 974, there was an express provision in the contract to the effect that "no work of any description is to be considered as extra work unless the same shall have been understood and agreed...
To continue reading
Request your trial-
Southern Surety Co. v. MacMillan Co.
...U. S. Shipping Board (C. C. A. 4) 16 F.(2d) 847; Lakeside Land Co. v. Empire Surety Co., 105 Minn. 213, 117 N. W. 431; Lackland v. Renshaw, 256 Mo. 133, 165 S. W. 314; Aetna Indemnity Co. v. Comer, 136 Ga. 24, 70 S. E. 676; Van Buren County v. American Surety Co., 137 Iowa, 490, 115 N. W. 2......
-
Wiss v. Royal Indemnity Company
... ... Dorr v. Bankers Surety Co., 218 S.W. 398; ... School District of Caruthersville v. McClure et al., ... 224 S.W. 831; Lakeland v. Renshaw et al., 256 Mo ... 133; M. K. & T. R. R. Co. v. American Surety Co., ... 236 S.W. 657. (3) The character of the bond, as to whether ... ...
-
Missouri, Kansas & Texas Railway Co. v. American Surety Company of New York
...reasonable intent of the parties as plainly indicated by their terms. [So. R. & F. Co. v. Bankers Surety Co., 184 S.W. 1033; Lackland v. Surety Co., 256 Mo. 140; Guarantee Co. v. Bank, 183 U.S. 402, 46 L.Ed. 22 S.Ct. 124; Am. Surety Co. v. Pauly, 170 U.S. 133, 42 L.Ed. 977, 18 S.Ct. 552.] T......
-
Maryland Cas. Co. v. Spitcaufsky
...1044; State to Use v. Cochrane, 264 Mo. 581, 175 S.W. 599; State ex rel. v. Detroit Fidelity & Surety Co., 32 S.W.2d 572; Lackland v. Renshaw, 256 Mo. 133, 165 S.W. 314; Newman v. Independence Indemnity Co., 41 S.W.2d State ex rel. v. Shain, 66 S.W.2d 102; State ex rel. v. Shain, 119 S.W.2d......