Landscape Design and Const., Inc. v. Harold Thomas Excavating, Inc., 20352

Decision Date23 July 1980
Docket NumberNo. 20352,20352
Citation604 S.W.2d 374
PartiesLANDSCAPE DESIGN AND CONSTRUCTION, INC., Appellant, v. HAROLD THOMAS EXCAVATING, INC., Appellee.
CourtTexas Court of Appeals

John A. George, Dallas, for appellant.

James S. Munson, Wharton, for appellee.

Before GUITTARD, C. J., and AKIN and HUMPHREYS, JJ.

AKIN, Justice.

This litigation concerns a dispute with respect to a subcontract to build a lake at Eastfield College in Mesquite, Texas. Defendant, a general contractor, entered into a written subcontract with plaintiff, a subcontractor, to excavate for the lake. Plaintiff completed the excavation but defendant refused to pay him, claiming that the work was not performed within ten days as required by the written agreement. Defendant claimed offsets for payments made and for damages due to plaintiff's failure to complete excavation within ten days. From a judgment for the plaintiff, allowing a portion of the defendant's claim for offsets, the defendant has appealed. We affirm on the ground that the ten day requirement for performance is a covenant rather than a condition precedent to payment.

Plaintiff completed the excavation required under the subcontract, although not within ten days of the commencement of the work, and plaintiff's excavation work was accepted by the defendant in completion of the general contract. Defendant contends that it is not obligated to pay plaintiff for the excavation work because the work was not completed in ten days. The correctness of defendant's contention depends upon whether the ten day requirement in the contract is a condition precedent or a covenant. A condition precedent is a fact which must exist before a duty of immediate performance of a promise arises. Andretta v. West, 318 S.W.2d 768, 773 (Tex.Civ.App. Texarkana 1958, writ ref'd n. r. e.). A covenant, as distinguished from a condition precedent, is an agreement to act or refrain from acting in a certain way. A breach of a covenant which is a part of a legally enforceable contract gives rise to a cause of action for damages rather than affecting enforceability of the provisions of the agreement. Reinert v. Lawson, 113 S.W.2d 293, 295 (Tex.Civ.App. Waco 1938, no writ). Thus plaintiff's recovery cannot stand if the contract is construed as making performance within ten days a condition precedent to the enforceability of the defendant's obligation to pay for the excavation work performed by plaintiff. If completion within ten days is a covenant or promise, then defendant has a legal obligation to pay for the excavation work under the contract but may bring an action against plaintiff for any damages suffered because of a breach of the ten day provision.

The contract upon which plaintiff relies for recovery provides:

SUBCONTRACT

This agreement made this 8th day of February in the year Nineteen Hundred and Seventy Seven by and between Harold Thomas Excavating, P. O. Box 595, Richardson, Texas 75080 hereinafter called the Subcontractor and Landscape Design & Construction, Inc., hereinafter called the Contractor.

ARTICLE I

The Subcontractor agrees to furnish all material and perform all work as described in Article II hereof for Dallas County Community College District's Eastfield Park at Eastfield College, Mesquite, Texas, for Landscape Design & Construction, Inc., in accordance with this agreement.

ARTICLE II

Description of work: Subcontractor agrees to form lake area in accordance to information and drawing of the Architect, Myrick, Newman, Dahlbert, Inc. All work shall be done subject to the final approval of the Architect or Owner's authorized agent, and his decision in matters relating to artistic effect shall be final, if within the terms of the Contract Documents.

ARTICLE III

Time is of the essence and the subcontractor agrees to complete the work as described in Article II within 10 working days of commencement.

ARTICLE IV

The Contractor agrees to pay Subcontractor for the performance of this work on a per unit, per hour, basis (As per schedule A attached) not to exceed the sum of Five Thousand Five Hundred and No/100 Dollars ($5,500.00) in current funds, subject to additions and deductions for changes as may be agreed upon in writing, within 10 days of receipt of monies from Owner.

ARTICLE V

Full payment shall be due when the work described in this contract is fully completed and performed consistent with Article II and Article IV.

ARTICLE VI

Prior to starting work the insurance required to be furnished shall be obtained from a responsible company or companies to provide proper and adequate coverage and satisfactory evidence will be furnished to the Contractor that the Subcontractor has complied with the requirements as stated in the General Conditions of Bid Document # 3469.

The general rule of delineation between covenants and conditions is set out in Hohenberg Brothers Co. v. George E. Gibbons & Co., 537 S.W.2d 1, 3 (Tex.1976). Normally a term such as "if", "provided that", "on condition that", or some phrase of conditional language must be included that makes performance specifically conditional. Otherwise the language will be construed as a covenant in order to prevent a forfeiture. More specifically, as stated in Shwartz-Jordan, Inc. v. Delisle Construction Co., 569 S.W.2d 878, 881 (Tex.1978), language will not be construed as a condition precedent when another reading of the contract is possible. In view of these rules of construction, we note that Paragraph V of the contract provides that full payment shall be due upon completion of the excavation consistent with Article II, which refers to specifications of the architect. The ten day provision of Article III is not mentioned in Article V. Thus Article V makes completion of the work according to Article II the only condition precedent to plaintiff's right to full payment. Consequently, we hold that Article III is a covenant or promise by plaintiff that the work will be completed within ten days, and as such it is enforceable by defendant in a damage action, but is not a condition precedent to plaintiff's right to payment. Thus, the trial judge correctly concluded that plaintiff is entitled to payment for the excavation work even though it was undisputed that it was not completed within ten days.

Defendant also contends that the trial court erred in failing to find $9,449.50 as offsets against plaintiff's claim. No counterclaim was pleaded for damages incurred because of the plaintiff's failure...

To continue reading

Request your trial
31 cases
  • Paj, Inc. v. Hanover Ins. Co.
    • United States
    • Texas Supreme Court
    • 11 janvier 2008
    ...M.A. McCAULIFF, CORBIN ON CONTRACTS § 30.12 (Joseph M. Perillo ed., 1999); Landscape Design & Constr., Inc. v. Harold Thomas Excavating, Inc., 604 S.W.2d 374, 376 (Tex.Civ.App.-Dallas 1980, writ ref'd n.r.e.). Conditions are not favored in the law; thus, when another reasonable reading that......
  • 5300 Memorial Investors, Ltd., Matter of
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • 16 septembre 1992
    ...is a "condition precedent" or a "covenant." The difference is explained well in Landscape Design & Constr., Inc. v. Harold Thomas Excavating, Inc., 604 S.W.2d 374 (Tex.Civ.App.--Dallas 1980, writ ref'd n.r.e.): A condition precedent is a fact which must exist before a duty of immediate perf......
  • Howe v. Howe
    • United States
    • Texas Court of Appeals
    • 11 avril 2018
    ...failure to make the additional findings was not prejudicial to the appellant. Landscape Design & Const., Inc. v. Harold Thomas Excavating, Inc., 604 S.W.2d 374 (Tex.Civ.App.—Dallas 1980, writ ref'd n.r.e.). Refusal of the court to make a requested finding is reviewable on appeal if error ha......
  • Arbor Windsor Court, Ltd. v. Weekley Homes, LP
    • United States
    • Texas Court of Appeals
    • 17 mars 2015
    ...landscaping subcontractor's promise to complete its work within ten days. See Landscape Design & Constr., Inc. v. Harold Thomas Excavating, Inc., 604 S.W.2d 374, 377 (Tex.Civ.App.–Dallas 1980, writ ref'd n.r.e.). In that case, Article III of the parties' contract provided that “[t]ime is of......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT