Leonard Concrete Pipe Co. v. C. W. Blakeslee & Sons, Inc.

Decision Date07 August 1979
Citation424 A.2d 277,178 Conn. 594
CourtConnecticut Supreme Court
PartiesLEONARD CONCRETE PIPE COMPANY v. C. W. BLAKESLEE & SONS, INC.

James N. Royster, Hartford, with whom, on the brief, was William M. Mack, Hartford, for appellant (third-party plaintiff C. W. Blakeslee & Sons, Inc.).

Bernard D. Gaffney, New Britain, for appellee (third-party defendant Mattabassett District).

Before COTTER, C. J., and LOISELLE, BOGDANSKI, LONGO and PETERS, JJ.

COTTER, Chief Justice.

The indemnitor on a construction contract appeals from a judgment rendered in favor of the indemnitee in an impleader action. The trial court findings, which are not subject to material correction, include the following facts: The third-party plaintiff C. W. Blakeslee & Sons, Inc., and the third-party defendant Mattabassett District entered into a construction contract pursuant to which Blakeslee agreed to construct a sanitary sewer line in the towns of Berlin and Cromwell in accordance with plans and specifications provided by Mattabassett. In furtherance of its obligation to Mattabassett, Blakeslee executed a contract with the Leonard Concrete Pipe Co. which provided that Leonard would manufacture and supply the concrete pipe required for the sewer construction project. During the construction of the sewer project, engineers hired by Mattabassett inspected the pipe manufactured by Leonard to determine whether the pipe complied with the specifications contained in the construction contract.

Following the project's completion, Leonard sued Blakeslee alleging damages as a result of Blakeslee's refusal to accept pipe that had been manufactured in accordance with the specifications. Blakeslee impleaded Mattabassett alleging in its third-party complaint that if in fact pipe meeting the contract specifications had been rejected, it was rejected by the engineers employed by Mattabassett and that Mattabassett should therefore be liable for any losses sustained by Leonard. Mattabassett, the third-party defendant, filed a counterclaim against Blakeslee asserting a contractual right to indemnification for all costs which Mattabassett might incur as a result of any liability to Leonard and as a result of defending itself in the third-party action. 1 After overruling Blakeslee's demurrer to Mattabassett's counterclaim, the court, after a trial, concluded that Mattabassett was within its contractual rights when it rejected those pipes which were found not to comply with the contract specifications and accordingly rendered judgment in favor of Blakeslee as to Leonard's complaint and in favor of Mattabassett as to the third-party complaint. In addition, the trial court construed the indemnification provision of the Blakeslee-Mattabassett contract to include the third-party action and rendered judgment in favor of Mattabassett on its counterclaim awarding the costs it incurred in defending the third-party suit. Blakeslee appeals from the court's ruling on the counterclaim and asserts that the indemnification provision is void as against public policy or, alternatively, that the provision should not be construed to include the costs of defending the third-party action.

Indemnification agreements have long been recognized as a valid method of allocating the risks inherent in construction projects. See Fairfield v. D'Addario, 149 Conn. 358, 179 A.2d 826; Buscaglia v. Owens-Corning Fiberglas, 68 N.J.Super. 508, 172 A.2d 703. The plaintiff contends, however, that the indemnification agreement in the present case is void as against public policy insofar as it purports to indemnify Mattabassett against its own breach of the contract. The validity of a contract is determined not according to what may possibly happen but according to what has actually happened as between the contracting parties. Collins v. Sears, Roebuck & Co., 164 Conn. 369, 377, 321 A.2d 444. The question then is whether the enforcement of the contract in this particular case would bring about a result which is contrary to public policy. The trial court determined, and the plaintiff does not dispute, that Mattabassett did not, in fact, breach its construction contract with Blakeslee when Mattabassett rejected pipe which it determined did not conform to the specification requirements. There being no breach of contract by the indemnitee Mattabassett, we need not consider the question posed by Blakeslee whether, under other circumstances, the indemnification of Mattabassett for its own breach of the contract with Blakeslee would be contrary to the public policy of this state.

The determinative issue in this appeal, then, is whether the court correctly construed the indemnification provision to require indemnification of Mattabassett for all expenses incurred by it in successfully defending...

To continue reading

Request your trial
27 cases
  • Sturman v. Socha
    • United States
    • Connecticut Supreme Court
    • 9 Agosto 1983
    ...light of the situation of the parties and the circumstances connected with the transaction.' " Leonard Concrete Pipe Co. v. C.W. Blakeslee & Sons, Inc., 178 Conn. 594, 598, 424 A.2d 277 (1979), quoting Ives v. Willimantic, 121 Conn. 408, 411, 185 A. 427 (1936). In situations where the parti......
  • Ceci v. National Indem. Co.
    • United States
    • Connecticut Supreme Court
    • 23 Marzo 1993
    ...[of the parties] to that policy and the circumstances connected with the transaction.' " Leonard Concrete Pipe Co. v. C.W. Blakeslee & Sons, Inc., 178 Conn. 594, 598, 424 A.2d 277 (1979), quoting Ives v. Willimantic, 121 Conn. 408, 411, 185 A. 427 This policy was prepared for the defendant ......
  • PMI Shares, Inc. v. SIMA International, Inc.
    • United States
    • Connecticut Superior Court
    • 3 Abril 2017
    ... ... Leonard Concrete Pipe Co. v. C.W. Blakeslee & Sons, ... Inc ... ...
  • Burr v. Lichtenheim
    • United States
    • Connecticut Supreme Court
    • 14 Junio 1983
    ...in light of the situation of the parties and the circumstances connected with the transaction. Leonard Concrete Pipe Co. v. C.W. Blakeslee & Sons, Inc., 178 Conn. 594, 598, 424 A.2d 277 (1979); Powel v. Burke, 178 Conn. 384, 387, 423 A.2d 97 (1979). In accordance with these principles of co......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT