Levinson v. Linderman, 33974
Decision Date | 07 March 1958 |
Docket Number | No. 33974,33974 |
Citation | 322 P.2d 863,51 Wn.2d 855 |
Parties | Dave LEVISON and Victor Osina, d/b/a Victor Osina Company, a partnership; and The National Bank of Commerce of Seattle, Respondents, v. C. R. LINDERMAN et al., Defendants, United States Fidelity and Guaranty Company, a corporation, Appellant. |
Court | Washington Supreme Court |
Lester T. Parker, Aberdeen, Ralph E. Franklin, Seattle, for appellant.
Zelasko & Zelasko, Aberdeen, Nordquist & Schnatterly, Centralia, for respondents.
The United States Fidelity and Guaranty Company appeals from a judgment subordinating its claim to moneys in the court's registry, representing the final payment on school construction contracts, to the claims of respondent Victor Osina Company, a judgment creditor, and respondent The National Bank of Commerce of Seattle, a contract creditor, whose assignment caveat was filed in the office of the secretary of state.
On March 22, 1953, the Grays Harbor County Consolidated School District No. 97 executed separate contracts for the construction of a school building and teachers' cottage with the L. & L. Construction Company, a partnership. On the same day, the contractor filed separate statutory performance bonds (RCW 39.08.010), on which the United States Fidelity and Guaranty Company was surety. Thereafter, the contractor started the construction.
On July 29, 1953, respondent, The National Bank of Commerce of Seattle, filed in the office of the secretary of state a statutory notice (RCW 63.16.020) that the contractor intended to assign accounts receivable to it. On April 19, 1954, the bank loaned the contractor fifteen thousand dollars upon its promissory note, secured by an assignment of a single progress payment. Neither the school district nor the surety was advised of the assignment. The note remains unpaid.
On July 7, 1954, the school board's architect advised the board that the contractor had breached its contract in four particulars. On the following day, July 8, 1954, the school board, by resolution, found the contractor in default in the particulars specified by the architect and gave the contractor written notice thereof, and, at the expiration of the contractual ten-day grace period, demanded the completion of the buildings by the surety under its bond, which it did at a cost of $89,159.70.
The application for the performance bond provides, among other things, that in case of the default of the contractor, the surety shall have the right to complete the contract at the expense of the principal.
The supplemental special conditions of the contract 1 require the contractor to furnish proof of payment of all bills before final payment; otherwise, the school district may itself pay the bills. Both construction contracts, which are in identical form, provide, in the event of the contractor's default, the school district may itself complete the work or employ others to do it, and take and use the contractor's equipment and materials for that purpose, in which event no further money shall be due the contractor unless a surplus exists after payment of all expenses. 2
Respondents Dave Levinson and Victor Osina, doing business as the Victor Osina Company, obtained a judgment against the contractor for $3,413.54, and thereafter, on October 24, 1955, served a writ of garnishment upon the school district which answered; but, by stipulation of the parties, the unpaid balance on the construction contracts of $62,200.29 was deposited in the court's registry, and the school district dismissed.
By stipulation of the parties, the court retained sufficient funds in its registry to satisfy the claims of both respondents, but released the balance to the surety.
Briefs were submitted, and, subsequently, the trial court, in a memorandum opinion, determined that the respondents had priority. The court's thesis was that, while the plans and specifications prohibited the assignment to the bank in very specific terms, such were not part of the contract; therefore, having filed its caveat in the office of the secretary of state to accept assignments from the contractor under the accounts receivable act, and because the surety failed to do so, the bank's claim was adjudged superior to that of the surety. The decision is fundamentally erroneous because the act has no application.
The contracts for both the construction of the school building and the teachers' cottage contain the following provision:
(Italics ours.)
The performance bond itself makes the contract and the plans and specifications a part of the bond by reference.
It is beyond cavil that the contractor defaulted in the performance of his contract because of which the school board terminated the contract and called upon the surety to complete the buildings pursuant to the performance bond, which it did at a very substantial loss.
The general conditions of the contract and the supplemental special conditions contained in the plans and specifications prohibit the assignment in unmistakable terms; but the respondents contend, and the trial court found, that such were not part of the contract. We hold otherwise, and that all the documents were executed simultaneously and are but one contract.
Although there were separate documents, the two contracts, the two performance bonds, and the plans and specifications were all executed at the same time as part of one transaction and constitute a single contract. The bank and the judgment creditor contend that the reference to the plans and specifications in the two contracts is insufficient to make the plans and specifications a part of the contract. We decide otherwise. The applicable rule of law is stated in 17 C.J.S. Contracts § 298, p. 714, as follows:
* * *'
Our decisions are in accord. Paine-Gallucci, Inc. v. Anderson, 41 Wash.2d 46, 246 P.2d 1095; Standring v. Mooney, 14 Wash.2d 220, 127 P.2d 401; State ex rel. Noble v. Bowlby, 74 Wash. 54, 132 P. 723.
This is not an ordinary contract, but a printed form copyrighted by the American Institute of Architects, designed for the specific purpose of making all documents one contract. The definition is unmistakable:
Under such circumstances, although the documents are physically separate, they constitute a single contract. This conclusion was reached under the identical form of contract in Valley Construction Co. v. City of Calistoga, 72 Cal.App.2d 839, 165 P.2d 521.
We said in Young v. Borzone, 26 Wash. 4, 18, 66 P. 135, 139, 421:
Such is the uniform tenor of judicial decision. 3
The bank could not fail to know that the contract was for the construction of school buildings and that a performance bond was required by RCW 39.08.010 at the time of the execution of the contract. Inquiry would have shown that the contract prohibited the assignment in question, and that the school district had the right under the contract, in the event of the contractor's default, to complete the buildings and to use all sums unpaid for that purpose.
The applicable rule of law 4 is well stated In A. Farnell Blair Co., Inc., v. Hollywood State Bank, 102 Cal.App.2d 418, 427, 227 P.2d 529, 534:
* * *'
The assignment is void under Indemnity Ins. Co. of North America v. Nelson, 173 Wash. 294, 296, 22 P.2d 984, in which we held:
The supreme court of Connecticut recently passed upon the same issue and held in Lewin and Sons, Inc. v. Herman, 143 Conn. 146, 120 A.2d 423, 425, as follows:
The funds...
To continue reading
Request your trial-
Lambert v. Maryland Cas. Co.
... ... Northeastern Corporation, 416 Pa. 417, 206 A.2d 49; Levinson v. Linderman, 51 Wash.2d 855, 322 P.2d 863; Scarsdale Nat'l. Bank & Trust Co. v. U. S. Fidelity & ... ...
- Pelly v. Panasyuk
- State Constr., Inc. v. City of Sammamish
-
Rocks v. Brosius
... ... 407, 110 A.2d 186 (1955); Doss Oil Royalty Co. v. Lahman, Okl., 302 P.2d 157 (1956); Levinson v. Linderman, 51 Wash.2d 855, 322 P.2d 863 (1958); Neville v. Scott, 182 Pa. Super. 448, 127 A.2d ... ...
-
§67.6 Analysis
...the court any retained funds or contract balance while the parties adjudicate the right to the funds. See, e.g., Levinson v. Linderman, 51 Wn.2d 855,858,322 P.2d 863 (1958) (depositing unpaid contract balance by stipulation). Third, some cases suggest that depositing disputed funds may stop......