Lexington Ins. Co. v. Entrex Communication
Decision Date | 16 May 2008 |
Docket Number | No. S-06-1452.,S-06-1452. |
Citation | 749 N.W.2d 124,275 Neb. 702 |
Parties | LEXINGTON INSURANCE COMPANY, et al., Appellants, v. ENTREX COMMUNICATION SERVICES, INC., et al., Appellees. |
Court | Nebraska Supreme Court |
Dean Suing, of Katskee, Henatch & Suing, Omaha, for appellee Dudutis Erection & Maintenance, Inc.
Hearst-Argyle Properties, Inc., and the Hearst Corporation (collectively Hearst) owned a television broadcast tower in Omaha, Nebraska. In February 2003, Hearst contracted with Entrex Communication Services, Inc. (Entrex), to upgrade the antenna on the tower. After the tower collapsed in July 2003, Hearst sued Entrex. Hearst alleged that Entrex's gross negligence caused the collapse. Entrex moved for summary judgment. Entrex claimed that a waiver of subrogation in the parties' agreement barred Hearst's claims to the extent insurance proceeds covered the damages. The district court granted the motion and dismissed Hearst's claims for damages that had been compensated by insurance. Hearst's insurer appeals.
This appeal presents two issues. The first is whether enforcing a waiver of subrogation provision to bar a gross negligence claim violates public policy. The second is whether the waiver of subrogation is limited to damages to "the Work" (as defined in the agreement), or whether it also applies to damages to "non-Work" property. We conclude that the waiver of subrogation is effective against claims for gross negligence. We further conclude that the waiver applies to damages to both the Work and the non-Work property. We affirm.
The facts are not in dispute. Hearst owns and operates a television station in Omaha. In February 2003, Hearst contracted with Entrex to modify a 1,234-foot television broadcast tower by removing the analog antenna and replacing it with a digital antenna. Entrex subcontracted with Communication Structures & Services, Inc., which hired Dudutis Erection & Maintenance, Inc., to assist (hereinafter collectively Entrex).
The parties' contract required Hearst to obtain property insurance to cover "the Project" (as defined in the agreement). Instead of obtaining a specific property insurance policy to cover the Project, Hearst relied upon existing "all-risk" property insurance policies. These policies were issued by Lexington Insurance Company; Allied World Assurance Company, Ltd.; CNA Insurance Company; Everest Reinsurance (Bermuda) Limited; and Firemen's Fund Insurance Company (collectively Lexington). These all-risk policies collectively provided Hearst with $25 million in coverage.
The tower collapsed in July 2003, allegedly causing over $6 million in damages to the antenna, tower, transmission building, and personal property in the transmission building. Lexington compensated Hearst for its losses, less a $250,000 deductible. Hearst sued Entrex, alleging that the tower collapse occurred because of Entrex's gross negligence.
Entrex moved for partial summary judgment. It argued that a waiver of subrogation clause in the parties' agreement barred Hearst's claims against Entrex to the extent insurance proceeds were available to cover the damages. Hearst responded with two arguments: (1) The waiver of subrogation was unenforceable because Hearst had alleged gross negligence and enforcing a waiver of subrogation against a claim for gross negligence would violate public policy and (2) the waiver barred only claims for damage to the Work (as defined in the agreement), and thus, Entrex's motion should be denied as to damage claims involving non-Work property.
Regarding Hearst's first argument, the court concluded that enforcing a waiver of subrogation to bar a claim for gross negligence did not violate public policy. In deciding the second argument, the court concluded that Hearst had waived all claims covered by its all-risk insurance policies, including damages to the Work and non-Work property. The district court granted Entrex's motion and dismissed Hearst's claims for damages covered by insurance.
Hearst appealed, but the Nebraska Court of Appeals dismissed the appeal for lack of jurisdiction. It determined that although the court's order disposed of all subrogation claims by Lexington, Hearst's claims for uninsured losses remained pending. Thereafter, Lexington was substituted as the named plaintiff in this lawsuit and Hearst's claims were dismissed without prejudice and refiled under a different case number. The court then entered a final order (consistent with its earlier order), granting Entrex's motion for summary judgment on Lexington's claims. Lexington appeals.
The contract between Hearst and Entrex was an American Institute of Architects (AIA) standard form of agreement, document A101-1997. The agreement incorporated another AIA standard form of general conditions of the contract for construction, document A201-1997.
Pivotal to our analysis are two words used in the parties' agreement — "Work" and "Project." Subparagraph 1.1.3 of the agreement defined "Work" as "the construction and services required by the Contract Documents, whether completed or partially completed, and includes all other labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor's obligations." Simply put, the Work is the construction and services to be provided by the contractor to fulfill the contractor's obligations under the contract. Subparagraph 1.1.3 also explains that the Work may constitute the whole or a part of the "Project."
Subparagraph 1.1.4 of the agreement defines the "Project" as "the total construction of which the Work performed under the Contract Documents may be the whole or a part and which may include construction by the Owner or by separate contractors." Stated more simply, the Project incorporates all the construction to be done, whether it be by the contractor, the owner, or other contractors. Here, the only construction being done was that by Entrex, so the terms "Work" and "Project" are interchangeable.
Article 11 of the agreement allocated insurance responsibilities among the parties. Subparagraph 11.1.1 of that article required Entrex, as the contractor, to obtain liability insurance covering claims for damages to non-Work property:
The Contractor shall purchase ... and maintain ... such insurance as will protect the Contractor from claims set forth below which may arise out of or result from the Contractor's operations under the Contract and for which the Contractor may be legally liable....
. . . .
.5 claims for damages, other than to the Work itself, because of injury to or destruction of tangible property, including loss of use resulting therefrom[.]
(Emphasis supplied.)
Subparagraph 11.4.1 of the agreement required Hearst to obtain property insurance covering the Project:
Unless otherwise provided, the Owner shall purchase and maintain ... property insurance written on a builder's risk "all-risk" or equivalent policy form in the amount of the initial Contract Sum, plus value of subsequent Contract modifications and cost of materials supplied or installed by others, comprising total value for the entire Project at the site on a replacement cost basis without optional deductibles.... This insurance shall include interests of the Owner, the Contractor, Subcontractors and Sub-subcontractors in the Project.
(Emphasis supplied.)
The agreement's critical provision is set out in subparagraph 11.4.7. It contains a waiver of subrogation, which forms the basis of this appeal, and states in relevant part:
The Owner and Contractor waive all rights against ... each other and any of their subcontractors ... for damages caused by fire or other causes of loss to the extent covered by property insurance obtained pursuant to this Paragraph 11.4 or other property insurance applicable to the Work, except such rights as they have to proceeds of such insurance held by the Owner as fiduciary.
Lexington assigns, restated, that the district court erred in holding that (1) the contractual waiver of subrogation barred gross negligence claims and (2) the waiver barred claims for damage to non-Work property.
Summary judgment is proper when the pleadings and evidence admitted at the hearing disclose no genuine issue regarding any material fact or the ultimate inferences that may be drawn from those facts and that the moving party is entitled to judgment as a matter of law.1 In reviewing a summary judgment, an appellate court views the evidence in the light most favorable to the party against whom the judgment is granted and gives such party the benefit of all reasonable inferences deducible from the evidence.2
The meaning of a contract is a question of law.3 The determination of whether a contract violates public policy is a question of law.4 When reviewing questions of law, an appellate court has an obligation to resolve the questions independently of the conclusions reached by the trial court.5
Lexington contends that the district court erred in deciding that the waiver of subrogation in...
To continue reading
Request your trial-
State v. Henderson
...note 11. 37. Eastern Associated Coal Corp., supra note 19. 38. Misco, Inc., supra note 11. 39. See, e.g., Lexington Ins. Co. v. Entrex Comm. Servs., 275 Neb. 702, 749 N.W.2d 124 (2008); Stewart v. Bennett, 273 Neb. 17, 727 N.W.2d 424 (2007); Myers v. Nebraska Equal Opp. Comm., 255 Neb. 156,......
-
Empress Casino Joliet Corp. v. W.E. O'Neil Constr. Co.
...the plaintiffs. See Board of Commissioners v. Teton Corp., 30 N.E.3d 711, 716 (Ind.2015) ; Lexington Insurance Co. v. Entrex Communication Services, Inc., 275 Neb. 702, 749 N.W.2d 124, 135 (2008) ; Federal Insurance Co. v. Woodruff Construction, No. 12–0821, 2012 WL 5954588 (Iowa Ct.App. No......
-
Hemingway v. Constr. By Design Corp.
...] the need for lawsuits,” by placing the risk of loss on the insurance company providing coverage. Lexington Ins. Co. v. Entrex Commc'n Servs., Inc., 275 Neb. 702, 749 N.W.2d 124, 135 (2008) ; see also Walker Eng'g, Inc. v. Bracebridge Corp., 102 S.W.3d 837, 841 (Tex.App.2003).5 ¶ 11 The “t......
-
BLB Aviation S.C., LLC v. Jet Linx Aviation LLC
...is not subject to interpretation or construction and must be enforced according to its terms.” Lexington Ins. Co. v. Entrex Commc'n Servs., Inc., 275 Neb. 702, 749 N.W.2d 124, 132 (2008). “A breach is a nonperformance of a duty.” Id. “In any damage action for breach of contract, the claiman......
-
Georgia Law Needs Clarification: Does it Take Willful or Wanton Misconduct to Defeat a Contractual “exculpatory” Clause, or Will Gross Negligence Suffice?
...No. C 08-02035 JW, 2009 WL 2031782, at *5-6 (N.D. Cal. July 9, 2009) (California law); Lexington Ins. Co. v. Entrex Commc’n Servs., Inc., 749 N.W.2d 124, 131 (Neb. 2008); Reliance, 868 A.2d at 226; Behr v. Hook, 787 A.2d 499, 504 (Vt. 2001); see also Marc M. Schneier, AIA Waiver of Subrogat......