Libbey v. Tidden

Decision Date19 May 1906
Citation192 Mass. 175,78 N.E. 313
PartiesLIBBEY et al. SHEEHAN v. TIDDEN et al. SHEEHAN v. SAME.
CourtUnited States State Supreme Judicial Court of Massachusetts Supreme Court
COUNSEL

Fred L. Norton, for petitioners.

Alfd. Hemenway and Arthur E. Burr, for respondent.

OPINION

HAMMOND, J.

This is a petition to enforce a mechanic's lien upon a lot of land in Brookline, upon which an apartment hotel known as 'Putnam Chambers' has been erected. The petition as amended alleges that the work was done under a contract between the petitioners and the respondent Tidden, by the terms of which the petitioners were to furnish all labor and materials required for the erection and completion of the building, except the foundation, cut stone, gas piping electric wiring, heating, plumbing and painting, for the sum of $71,000; that under this contract the petitioners proceeded to furnish labor and materials actually used in the construction of the building; that without their own fault they were prevented from fully performing the contract by reason of Tidden's failure to perform his part, and that there is due to them a balance of $26,372.65, as shown in an account annexed, for which amount the lien is claimed.

An intervening petition was filed by Sheehan, alleging a contract between him and Tidden, by which Sheehan was to prepare plans and specifications and supervise the erection of the building for $2,500. The intervening petition contained allegations similar to those in the original petition as to the partial performance of the work and the prevention of its completion and as to the ownership of the property; and alleged that there was due as a reasonable compensation for the work done the sum of $975, for which amount a lien is claimed.

Tidden appeared, but filed no answer. The respondent Skinner filed an answer in which he denies generally the allegations of the petition, and alleges that on April 2, 1902, the date of the contract described in the amended petition, Tidden was not the owner of the premises, and did not have any right, title or interest in or to the same until April 14, 1902, on which day the owner conveyed to him and at the same time and as a part of the same transaction he mortgaged the premises to the Massachusetts Title Insurance Company for the sum of $80,000, and that both the deed and mortgage were recorded together, so that Tidden had only an instantaneous seizure of the land; that the mortgage was duly foreclosed and that Skinner purchased at the foreclosure sale, and is now the owner free from all liens which may have accrued subsequent to said mortgage. The answer further alleged that at no time prior to the recording of said mortgage did the petitioner make any contract with the owner, or any person having authority from him; that this labor and materials were not performed or furnished by virtue of any agreement with or by the consent of the owner or any person having authority from him prior to the date of the mortgage, and that no notice was given to the owner prior to the date of the mortgage. A similar answer to the intervening petition was filed by Skinner.

The case was referred to an auditor, who made a report. At the trial in the superior court the case was heard by the court sitting without a jury, the only evidence being the report of the auditor together with nine exhibits. The court found for the original petitioners for the amount claimed, and for Sheehan in the sum of $800, and ordered that liens be established for these respective sums. The case is before us upon certain exceptions alleged by the respondent Skinner to the findings of fact made by the court, and to the orders establishing the liens as well as to certain rulings and refusals to rule. In considering the case the term petitioners will be used to designate only Libbey and Dixon, the original petitioners. Sheehan, as hereinbefore seen, is an intervening petitioner.

1. As to the contract. One of the grounds of the defense is that the contract under which the petitioners claim was not made until after the mortgage under which Skinner held. As to this the court found that, on April 11, 1902, a contract was made between Tidden and the petitioners Libbey and Dixon, 'whereby the firm was to furnish labor and materials necessary to construct the mason work, carpenter work and roofing of' the building in question, 'for the entire price of $71,000. The amounts and times of payments were not agreed upon, but it was agreed in a general way that they were to be made as the floors went on. It was also agreed that Libbey & Dixon were to have later what is known as a 'uniform contract,' being the form of contract adopted and recommended for general use by the American Institute of Architects and the National Association of Builders. The uniform contract was given August 2, 1902, but that instrument did not in any essential particular alter the existing contract of April 11, and was an affirmation of it and not a substitute for it.'

The respondent contends that the above findings are not warranted by the evidence. Inasmuch as the only evidence was the auditor's report and exhibits, this point must be decided by an inspection of the report. Upon this question the auditor reports as follows:

'On April 2, 1902, Tidden and Libbey went to the Putnam lot and had a conversation in regard to the building which Tidden said he was intending to erect upon it, in the course of which Tidden told Libbey that he wished him to see Sheehan and then give him, Tidden, an estimate of the cost of such a building. Another building known as 'Stearns Chambers' was then under construction just across the street, and Libbey & Dixon were the contractors and Sheehan the architect. Libbey went to see Sheehan, got the plans and made figures on the cost, and on April 10th or 11th gave Tidden an estimate of $150,000. Tidden then asked him what he would do the mason work, the carpenter work and the roofing for, and Libbey said he would do it for $71,000, to which Tidden replied, 'All right, I will give you the contract.' The amounts and times of payments were not agreed upon, but it was agreed in a general way that they were to be made as the floors went on. It was also agreed that Libbey & Dixon were to have later what is known as a 'uniform contract,' being the form of contract adopted and recommended for general use by the American Institute of Architects and the National Association of Builders. On April 12th, Libbey went to the lot and drove some stakes to indicate where the excavation for the cellar was to be made, and during the time from April 2d to that date he had frequent interviews with Tidden in regard to the building. The first item in his statement of account is a charge of $80 covering these ten days at $8 a day and including the wages of his son and another young man who went to the lot with him and helped him drive the stakes. He did nothing else in reference to the building until June 21st, when he sent two carpenters there to put up the permanent better-boards. On July 16th, and on five other days in that month he laid 35,000 brick in the building of cross walls in the cellar, at an estimated cost of $700, the mortar being taken from the mortar beds at the Stearns Chambers job. On August 2d the written contract was signed, and it appears in evidence as 'Exhibit 1.' Mr. Libbey said that there was no particular reason why it was not signed before, though he had spoken to Tidden frequently in regard to it. The contract is written upon the uniform contract blank, and provides that 'the contractor shall and will provide all materials and perform all the work mentioned in the specifications and shown on the drawings prepared by the said architects for the erection and completion of that portion of the work included in the specifications of building of the Putnam Chambers, except cut stone and gas piping.' This contract is claimed by the petitioners to cover all the points mentioned in the conversation between Tidden and Libbey, which resulted in Tidden's saying that he would give him the contract, except that the dates for the payments were fixed. The respondents, on the other hand, claim that the petitioners had no contract before August 2d, but only an agreement for, or a promise of, one, and point out that the written contract specifies dates of payments, that the building should be finished by a certain time, that the contractors should allow the owner insurance money, etc., none of which matters were considered or spoken of by the parties when Tidden said that he would give the contract to the petitioners. At that time no agreement was made when the petitioners should have possession of the premises, but the written contract provided that they should have possession on or before August 5th. When Tidden first spoke to Libbey about the Putnam Chambers he said he had bought the lots on which both that and Stearns Chambers were built, but Libbey said he did not know at that time who had the legal title, but he found out later that Tidden did not have it. * * * Upon the question of whether there was any contract between the parties before April 14th, Tidden testified that he made no contract with the petitioners before that date, and had no definite contract with them before August 2d, that he wanted them to have the job if they could meet the estimates of other people, but that he did not remember having such a conversation with Libbey on April 12th, or that the latter proposed to do the mason and carpenter work and the roofing for $71,000. I find, however, that such a conversation did take place, and that Tidden did say to Libbey that he would give him the job, leaving the question of law as to whether such a contractual relation existed between the parties prior
...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT