Marianna Hotel Co. v. Livermore Foundry & Machine Co.
Decision Date | 03 March 1913 |
Citation | 154 S.W. 952,107 Ark. 245 |
Parties | MARIANNA HOTEL COMPANY v. LIVERMORE FOUNDRY & MACHINE COMPANY |
Court | Arkansas Supreme Court |
[Copyrighted Material Omitted]
Appeal from Lee Circuit Court; Hance N. Hutton, Judge; reversed.
STATEMENT OF FACTS.
This is a suit by the appellee against the appellant in the Circuit Court of Lee County to have a judgment for building material furnished by the appellee which it alleged was used in a certain hotel building belonging to the appellant. The complaint set up that the material was furnished to B. M Nelson, the contractor, who had been employed by the appellant to construct the building in the city of Marianna. The complaint was filed on the 27th of July, 1911. It had as an exhibit an itemized account showing a balance due for materials furnished in the sum of $ 412.79. There was a prayer for judgment in this sum, and that same be declared a lien upon the building.
The answer denied the material allegations of the complaint. Denied that the materials were furnished within ninety days before the suit was brought and the lien filed. It set up that all of the material furnished by the appellee under its original contract was sold on November 30, 1910; that the small amount for sash weights, $ 77.87, was furnished on April 29, 1911; and it averred that all except this amount was out of date and barred; that the other material included in the account was furnished under a different contract. The answer also set up that there had been payments made upon the account leaving a balance due January 30, 1911, of $ 334.92. The answer further set up that the contractor abandoned his contract before the building was completed and that the appellant was compelled to complete the building, and did so according to the original plans and specifications, paying therefor a greater sum than the original contract price. It averred that it had paid no part of the contract price to the contractor for his own use. It alleged that it had paid the sum of $ 23,442.48 in strict accordance with the terms of the contract before the contractor abandoned the same, and that it had paid $ 7,346.20 to complete the building according to the original plans and specifications.
The manager of the appellee testified that appellee's account was for structural iron and some other small articles furnished the contractor for appellant's building; that the largest item of the account was for structural iron furnished on November 30, 1910.
The material was all used in the building. The last shipment was made May 2, 1911. The account shows that on April 29 there was furnished sash weights amounting to $ 77.87. Witness testified that the structural iron was furnished under a written proposal made by his company to the contractor, which he accepted on condition that the company would furnish sash weights at a certain price. The company agreed to that and agreed to protect him on the price on a rise in the market. There was nothing said about that in the written proposal nor in the acceptance endorsed on the proposal. There was but one contract; that was in writing, regarding the structural iron. The contractor signed an acceptance and put his name on the proposal and put it there upon that condition. But this condition was not in the proposal or in the acceptance endorsed on the back thereof. The sash weights are not classed as structural iron.
Witness stated that "
The testimony on behalf of the appellant tended to show that it entered into a contract with one B. M. Nelson to construct the hotel building for the price of $ 26,185. The contractor abandoned the contract before the building was completed.
The testimony was voluminous, and without setting it out in detail, it tended to show that the sum of $ 23,342.48 was paid in checks at the time the contractor quit work, and that this amount was paid to the material men and laborers. Most of the checks state on their face for what purpose they were issued. They were made payable to the contractor, but went to the material men and laborers.
The evidence tended to show that the money was paid out by the appellant to the contractor before he quit work, towit, the sum of $ 23,342.48, for the purpose of paying for material and labor that went into the building, and that none of it was paid to the contractor for his own use.
The appellee, over the objection of appellant, introduced testimony tending to show that the contractor on one occasion took $ 62.50 out of the sack that contained the pay roll money and converted it to his own use by paying same on a private debt for money borrowed.
The testimony on behalf of the appellant tended to show that it paid out after the contractor abandoned the contract the sum of $ 7,346.20 for the completion of the building. A witness was asked the following question: "Was that building completed according to the plans and specifications?" and answered,
Witness testified that there was no difference in the cost of the tiling.
There is a stipulation in the record as follows:
"After the court had declared the law as shown by the instructions the defendant offered to introduce a witness W. S. McClintock, for the purpose of showing by the said W S. McClintock that there are now pending the following actions against the hotel company for the purpose of enforcing accounts and claims for liens against the said hotel building, and that liens upon said accounts had been filed as provided by law in the Lee Circuit Court, as follows: W. F. Kershaw $ 569.95, Carl Sutton $ 49.60, and a suit in the United States District Court by Crane Company seeking to enforce a lien amounting to $ 3,013.97."
The court refused to allow the testimony to be introduced, to which appellant duly excepted.
The court, at the request of appellee, granted, among others, the following prayers:
To continue reading
Request your trial-
Western Union Telegraph Company v. Baltz
... ... The jury had no correct guide. Marianna Hotel Co. v ... Livermore F. & M. Co., 107 Ark. 245, ... ...
-
Western Union Telegraph Co. v. Baltz
...of the court was thus made inconsistent, inharmonious, and contradictory. The jury had no correct guide. Marianna Hotel Co. v. Livermore F. & M. Co., 107 Ark. 245, 154 S. W. 952; St. L., I. M. & S. Ry. Co. v. Bright, 109 Ark. 4, 159 S. W. 33; Turquett v. McMurrain, 110 Ark. 197, 161 S. W. 1......
-
Locke v. Murdoch.
...130 App. Div. 548, 115 N. Y. Supp. 46, 48; Holmboe v. Morgan, 69 Or. 395, 138 Pac. 1084, 1085; Marianna Hotel v. Livermore Foundry & Machine Co., 107 Ark. 245, 154 S. W. 952, 955; New York Life Ins. Co. v. Thomas, 47 Tex. Civ. App. 149, 104 S. W. 1074, 1075; Neb. Land & Feeding Co. v. Traue......
-
Ferguson Lumber Company v. Scriber
...the affidavit was sufficient. 90 Ark. 340. A substantial compliance with the statute is sufficient. 119 Ark. 43; 56 Ark. 544; 90 Ark. 108; 107 Ark. 245; 116 Ark. 124 Ky. 251; 14 Ann. Cas. 688; 24 Pa.St. 507; 14 Wyo. 455; 96 Ala. 346; 13 Ind.App. 432; 77 Neb. 833. The lien when filed dates b......