Maross Const., Inc. v. Central New York Regional Transp. Authority

Decision Date21 November 1985
Citation66 N.Y.2d 341,497 N.Y.S.2d 321,488 N.E.2d 67
Parties, 488 N.E.2d 67 MAROSS CONSTRUCTION, INC., Respondent, v. CENTRAL NEW YORK REGIONAL TRANSPORTATION AUTHORITY, Appellant.
CourtNew York Court of Appeals Court of Appeals
OPINION OF THE COURT

JASEN, Judge.

The issue dispositive of this appeal is whether a broad arbitration clause in a public construction contract which empowers the architect to resolve all contractual disputes submitted by the parties binds those parties to the architect's determination, notwithstanding a provision in the contract with which the determination conflicts.

Defendant, Central New York Regional Transportation Authority (the Authority), invited bids for a certain liquid handling systems contract as part of a project for the construction of a public bus garage in the City of Syracuse. Prior to the date on which bids were to be submitted, a representative of plaintiff, Maross Construction, Inc. (Maross), informed the Authority's architect of an apparent ambiguity in the bid documents. While certain contract drawings indicated that the responsibility for the supply and installation of two fiberglass tanks belonged to the general contractor, the bid specifications placed that responsibility upon the so-called liquids handling systems contractor. Maross requested that the matter be clarified by means of an addendum to the bid documents. The architect responded that the bid specifications took precedence and that the minor discrepancy in the drawings did not require that an addendum be issued.

Maross submitted a bid which was the lowest of three submitted. The Authority awarded the liquids handling systems contract to Maross and sent an owner-contractor agreement for its signature. Prior to affixing its signature, however, Maross added a paragraph to the agreement at article 2 which is labeled "THE WORK" and which contains a preprinted clause introducing the description of the "Work required by the contract documents". The typed language inserted by Maross provided as follows: "The contractor, Maross Construction, Inc., is not responsible for the supplying and installing of fiber-glass tanks V18 and V28 on page H1.4 of the contract drawings, as the drawings specifically place such responsibility with the general contractor."

Although Maross thus attempted to relieve itself of responsibility for the supply and installation of the tanks, it did not otherwise notify the Authority and, moreover, it did not make any modifications to certain other provisions of the agreement which pertain to the same matter. Article 7 of the owner-contractor agreement, which appears on the signature page and is entitled "Miscellaneous Provisions", contains an itemization of all the "Contract Documents" stated to "constitute the entire agreement between the Owner and Contractor". This itemization lists various specifications and drawings which, in turn, specifically include the tanks in question among the liquid handling systems contractor's responsibilities.

With article 2 thus altered and article 7 and its referenced contract documents left undisturbed, Maross signed the owner-contractor agreement and returned it to the Authority. Without making any protests, corrections or deletions, the Authority added its signature to the agreement and the project eventually commenced. Shortly thereafter, a dispute arose concerning responsibility for the supply and installation of the tanks. When Maross insisted it was not responsible under the provisions of the contract, the Authority requested that the issue be resolved by the architect. Under the "General Conditions of the Contract", a document explicitly incorporated into the owner-contractor agreement, the parties entrusted broad arbitration powers to the architect. At article 2, paragraph 2.01, entitled "Authority and Duties of Architect", the "General Conditions" provide in pertinent part: "To resolve all disputes and to prevent litigation the parties to this Contract authorize the Architect to decide all questions of any nature whatsoever arising out of, under or in connection with, or in any way related to or on account of, this Contract (including claims in the nature of breach of Contract or fraud or misrepresentation before or subsequent to acceptance of the Contractor's Proposal and claims of a type which are barred by the provisions of the Contract), and his decisions shall be conclusive, final and binding on the parties. His decision may be based on such assistance as he may find desirable, including advice of engineering specialists. The effect of his decision shall not be impaired or waived by any negotiations or settlement offers in connection with the question decided, whether or not he participated therein himself, or by any prior decision of others, which prior decisions shall be deemed subject to review, or by any termination or cancellation of this Contract." (Emphasis added.)

Pursuant to the foregoing authority, the architect accepted documentary submissions from both parties and ultimately concluded that the contractual specifications clearly impose the responsibility for the tanks upon Maross. The architect directed Maross to return to work and to provide the tanks in question without extra cost.

Maross refused to comply with the architect's directives and, instead, commenced this action seeking a declaration that it is not responsible under the contract for supplying and installing the tanks. On cross motions for summary judgment, Special Term granted judgment to the Authority. The court found that Maross knew and understood the terms of the contract as intended and drafted by the Authority, and ruled that Maross had no power to alter a substantial term of a public contract subject to competitive bidding as it had attempted to do. On appeal, the Appellate Division, 107 A.D.2d 1010, 486 N.Y.S.2d 535, reversed and awarded summary judgment to Maross. That court held that the Authority had bound itself to the disclaimer provision added by Maross when it affixed its signature to the contract. The court added, moreover, that the architect's arbitration authority extends only to the resolution of factual disputes and, therefore, that the architect's contrary construction of the parties' contract was not entitled to binding effect. Because we disagree with the Appellate Division's characterization of the architect's arbitral authority under the contract in question, we now reverse.

An agreement to submit contractual disputes to arbitration, once viewed adversely as an improper attempt to preclude judicial review even where such was warranted (see, Meacham v. Jamestown, Franklin & Clearfield R.R. Co., 211 N.Y. 346, 105 N.E. 653), is now well recognized as an effective and expeditious means of resolving disputes between willing parties desirous of avoiding the expense and delay frequently attendant to the judicial process (Matter of Sprinzen [Nomberg], 46 N.Y.2d 623, 629, 415 N.Y.S.2d 974, 389 N.E.2d 456; see also, Matter of Silverman [Benmor Coats], 61 N.Y.2d 299, 307, 473 N.Y.S.2d 774, 461 N.E.2d 1261; CPLR art 75). Indeed wherever the agreement to arbitrate is clearly expressed, a subsequently resistant party will be deemed to have relinquish the right to litigate disputes in the courts and may be compelled, instead, to submit to arbitration. (Matter of Franklin Cent. School [Franklin Teachers Assn.], 51 N.Y.2d 348, 356-357, 434 N.Y.S.2d 185, 414 N.E.2d 685; cf. Matter of Waldron [Goddess], 61 N.Y.2d 181, 183-184, 473 N.Y.S.2d 136, 461 N.E.2d 273.)

Where the parties have expressly agreed to arbitrate their disputes, it remains to be determined whether the subject matter of the dispute is one that may be submitted to arbitration without violation of any law or public policy and, if so, whether it falls within the scope of the arbitration agreement. (See, Matter of Franklin Cent. School [Franklin Teachers Assn.], supra, 51 N.Y.2d at p. 355, 434 N.Y.S.2d 185, 414 N.E.2d 685.) Hence, where jurisdiction over a particular type of dispute is statutorily bestowed exclusively upon the courts (see, e.g., Matter of Knickerbocker Agency [Holz], 4 N.Y.2d 245, 173 N.Y.S.2d 602, 149 N.E.2d 885; cf. Matter of South Colonie Cent. School Dist. [South Colonie Teachers Assn.], 46 N.Y.2d 521, 525-526, 415 N.Y.S.2d 403, 388 N.E.2d 727) or where judicial, as opposed to...

To continue reading

Request your trial
80 cases
  • Hough v. Merrill Lynch, Pierce, Fenner & Smith, Inc.
    • United States
    • U.S. District Court — Southern District of New York
    • 15 février 1991
    ...decision is totally irrational or violative of a strong public policy. See Maross Constr. Inc. v. Central New York Regional Transp. Authority, 66 N.Y.2d 341, 497 N.Y.S.2d 321, 488 N.E.2d 67 (1985); Diaz v. Pilgrim State Psychiatric Center, 62 N.Y.2d 693, 476 N.Y.S.2d 525, 465 N.E.2d 32 (198......
  • Western Elec. Corp. v. New York City Transit Auth.
    • United States
    • U.S. District Court — Southern District of New York
    • 13 avril 1990
    ...Authority's Chief Engineer to be decisionmaker violated public policy); cf., Maross Construction Inc. v. New York Regional Transportation Authority, 66 N.Y.2d 341, 343, 497 N.Y.S.2d 321, 322 (1985) (construing similar clause of regional transit authority providing for decisionmaker employed......
  • In re Galleries
    • United States
    • U.S. Bankruptcy Court — Southern District of New York
    • 18 juillet 2011
    ...than the legal causes of action asserted.” Genesco, 815 F.2d at 846; see also Maross Constr., Inc. v. Central New York Regional Transp. Authority, 66 N.Y.2d 341, 345, 497 N.Y.S.2d 321, 488 N.E.2d 67 (N.Y.1985) (“Where the parties have expressly agreed to arbitrate their disputes, it remains......
  • 159 MP Corp. v. Redbridge Bedford, LLC
    • United States
    • New York Court of Appeals Court of Appeals
    • 7 mai 2019
    ...of avoiding the expense and delay frequently attendant to the judicial process" ( Maross Constr. v. Central N.Y. Regional Transp. Auth. , 66 N.Y.2d 341, 345, 497 N.Y.S.2d 321, 488 N.E.2d 67 [1985] [citations omitted] ). "It has long been the policy of the law to interfere as little as possi......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT