Marsh v. Richards

Decision Date31 October 1859
Citation29 Mo. 99
PartiesMARSH, Respondent, v. RICHARDS, Appellant.
CourtMissouri Supreme Court

1. Where a party sues on a special contract to recover compensation due on its performance, he must show performance thereof on his part, or a legal excuse for non-performance.

2. Where a contractor engages to furnish materials and perform certain work for another--as to construct the brick work of buildings--and he does perform the contract, but not in the manner or with the materials required, he may, notwithstanding, if the party for whom the work is done receive and enjoy the same, recover compensation therefor.

3. The value of the work as actually done proportionally to the price fixed in the contract is the measure of damages in such case.

4. Where a contractor engages to construct buildings with pressed brick fronts, and he uses a brick of inferior quality, the relative cost of pressed brick and the kind of brick used is a proper matter to be considered by the jury in ascertaining the compensation to be allowed the contractor.

5. When two causes of action are joined in a petition, they should be stated separately.

Appeal from Hannibal Court of Common Pleas.

The plaintiff in his petition set forth that on the 12th of February, 1857, he entered into a written agreement with the defendant to furnish the materials for and to construct and finish the walls of certain buildings. The stipulations of the contract are set forth, and it is stated that the fronts of the houses were to be built of pressed brick. For the work done plaintiff was to be paid at various rates of $8, $8.50, $9.50 and $10 per thousand bricks. The work was to be completed by the 1st of September, 1857, and to be paid for as it progressed. Plaintiff then alleges that he duly performed the undertakings made incumbent upon him by said agreement “except in the manner hereinafter stated.” He then proceeds to set forth the amount of work done under the contract, together with certain items of extra work; also the particulars in which he failed to comply with the contract. It is admitted that pressed brick were not used as stipulated, and as a justification for not using them it is alleged that defendant consented to modify the agreement in that respect and to allow plaintiff to use “stock” brick. It is also admitted that the stipulated work was not completed at the time agreed upon, September 1, 1857. This failure was charged to be owing to the fault and omission of defendant. The work, it was alleged, was completed about November 1, 1857, and delivered to and accepted by the defendant. The petition then proceeds as follows: Plaintiff says that defendant owes him, for work and labor done and performed and materials furnished him in the construction of said buildings, the following sums.” He then sets the items of work down with their value, being the same items as had previously been set forth in the petition as done under the contract (including the extra work) and charged for at the contract price. He admitted payments amounting to $1,225, and claimed a balance of $960.94.

The answer admitted the execution of the contract as alleged. It denied that the amount of brick work done was asgreat as was stated in the petition; denied the alleged modification of the contract so far as the “pressed brick” were concerned; denied that the failure to complete the work stipulated for at the time agreed upon was owing to the fault or omission of defendant; and set up the noncompliance of plaintiff with the contract by way of counter claim.

At the trial the plaintiff introduced the contract in evidence, and also evidence showing the amount of the brick work done and the value of the extra work done, and rested The defendant then asked the court, among other instructions, to give the following: “1. As to so much of plaintiff's demand as relates to materials and brick work done on the buildings mentioned in the petition, plaintiff can not recover any thing, because it is admitted by the petition that the brick used were not pressed brick as required by the contract, and because there is no evidence tending to show a modification of the contract as to the kind of brick to be used as charged in the petition. 2. As to the demand for materials and brick work, the plaintiff can not recover any thing, because it is admitted by the petition that the work was not completed at the day appointed in the contract for its completion, and because, further, there is no evidence in the cause tending to show the excuse alleged, or any excuse for plaintiff's default. 3. The jury ought not to find for the plaintiff the price agreed in the written contract read in evidence to be paid by defendant for the materials to be furnished, and the work and labor to be performed by the plaintiff in the erection of the walls in said buildings on Centre and Main streets, because it is admitted by the petition that the materials to be used under said contract in the construction of said walls were not used by the plaintiff in the construction of the walls which he did erect; nor can they find for the plaintiff the reasonable value of the materials furnished and the work and labor performed by the plaintiff in the construction of said front walls, because it is not averred in the petition or proved by the evidence what was or is the reasonable value of the same.” The court refused so to instruct. The defendant offered to prove the relative market value in Hannibal, in 1857, of pressed and common and stock brick. The court ruled out the evidence at the instance of plaintiff. Witnesses stated that they could not estimate the difference of market value in Hannibal between a pressed brick front and a stock or common brick front. Evidence was also introduced bearing on the subject of the default of the defendant in obstructing the completion of the brick work at the time stipulated.

The court, at the instance of the plaintiff, gave the following instructions: “1. If the jury find from the evidence that at the time the contract was entered into the cellar walls were not erected, and that it was understood between the parties that defendant should have the cellar walls put up ready for the brick work, the defendant was bound to have the cellar walls ready for the brick work within a reasonable time after the contract between plaintiff and defendant was entered into; and if the jury further find that the defendant failed to have said cellar walls ready for the brick work within a reasonable time, and that plaintiff was ready and able to have put the brick work within the time specified in the contract, but was prevented from doing so by reason of such failure on defendant's part, then defendant is not entitled to any damages by reason of plaintiff's failure to complete the brick work within the time agreed on. 2. The jury ought to allow plaintiff for the quantity of brick laid in the walls of the buildings according to the prices specified in the contract read in evidence, deducting therefrom the sums of money paid by defendant to plaintiff; and if the balance thus ascertained exceeds the amount of damages allowed defendant upon his counter claim, the jury ought to find a verdict for plaintiff for this excess; and the jury ought to allow to defendant the damages he sustained by plaintiff's act in substituting stock brick in the fronts instead of pressed brick. The measure of such damages is the amount the substitution of stock brick in the place of pressed bricks in the fronts would lessen the value of the building in the market as shown in the evidence.”

The court refused the following instruction asked by defendant: “The jury ought to find a verdict for the defendant on his counter claim for the amount of damage it may appear from the evidence he sustained by reason of the failure of the plaintiff to complete his part of the work on said buildings by the first day of September, 1857; and the measure of such damages is the reasonable value of the...

To continue reading

Request your trial
50 cases
  • Coleman v. Fletcher
    • United States
    • Court of Appeal of Missouri (US)
    • July 19, 1945
    ... ... Asbestos Textile Co., 79 F.2d ... 634; Hoffman v. Mastin, 119 S.W.2d 1027, 1030; ... Cook v. Harrington, 54 S.W.2d 439; Marsh v ... Richards, 29 Mo. 99, 104; Charles v. St. Louis ... Basket Co., 271 S.W. 859; Meyers v ... Christopher, 176 Mo. 294. It is elementary ... ...
  • Steele v. Brazier
    • United States
    • Court of Appeal of Missouri (US)
    • December 6, 1909
    ... ... R. S. 1899, ... sec. 593; Henderson v. Dickey, 50 Mo. 161; ... Christal v. Craig, 80 Mo. 367; Scott v ... Robards, 67 Mo. 289; Marsh v. Richards, 29 Mo ... 99; Doan v. Halley, 25 Mo. 357; Childs v ... Bank, 17 Mo. 213; Mooney v. Kennett, 19 Mo ... 552; Waechter v ... ...
  • Tucker v. St. Louis Life Ins. Co.
    • United States
    • United States State Supreme Court of Missouri
    • October 31, 1876
    ...and equitable defenses, as to the joinder of law and equity in the same suit. (38 Mo. 492; 36 Mo. 202; 35 Mo. 483; 34 Mo. 134; 30 Mo. 228; 29 Mo. 99; 25 Mo. 357.) The court below had full power to grant any relief consistent with the petition, answers and proof. (50 Mo. 101; Id. 350; 41 Mo.......
  • Ottumwa Bridge Company v. Corrigan
    • United States
    • United States State Supreme Court of Missouri
    • June 28, 1913
    ... ... contract price where admittedly the contract has not been ... kept. The remedy is in quantum meruit. Marsh v ... Richards, 29 Mo. 99; Donney v. Burke, 23 Mo ... 228; Eyerman v. Cemetery Assn., 61 Mo. 491; ... Keith v. Ridge, 146 Mo. 97; ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT