MATTER OF ARBITRATION BETWEEN KLIMENT & McKINSEY & CO.

Decision Date16 December 2004
Citation821 N.E.2d 952,3 N.Y.3d 538,788 N.Y.S.2d 648
PartiesIn the Matter of the Arbitration between R.M. KLIMENT & FRANCES HALSBAND, ARCHITECTS, Respondent, and McKINSEY & COMPANY, INC., Appellant.
CourtNew York Court of Appeals Court of Appeals

Stroock & Stroock & Lavan LLP, New York City (Brian M. Cogan and Tom A. Hakemi of counsel), for appellant.

Ingram Yuzek Gainen Carroll & Bertolotti, LLP, New York City (Larry F. Gainen and Joan Walter of counsel), for respondent.

Chief Judge KAYE and Judges G.B. SMITH, ROSENBLATT, GRAFFEO, READ and R.S. SMITH concur.

OPINION OF THE COURT

CIPARICK, J.

In 1996, the Legislature amended CPLR 214 (6) to provide that the limitations period in nonmedical malpractice claims is three years, whether the complaint is cast in contract or in tort. In this case we are called upon to determine whether the breach of a provision in an architectural contract requiring that plans, drawings and specifications comply with applicable building codes is governed by the three-year statute of limitations for malpractice claims or the more generous six-year contract limitations period. We hold that the purpose of the statute is best served by applying the three-year statute of limitations applicable to all nonmedical professional malpractice claims.

In January 1998, McKinsey & Company, Inc. entered into an agreement with R.M. Kliment & Frances Halsband, Architects (K&H) through which K&H would perform architectural and interior design services in connection with 13,000-plus square feet of office space McKinsey had leased in Stamford, Connecticut. The parties agreed that disputes arising from the contract would be subject to arbitration.

Upon K&H's completion of the project, the Stamford Building Department issued a certificate of occupancy for the premises dated November 3, 1998. However, four years later, McKinsey claimed K&H failed to provide fire protection in compliance with the Connecticut Building Code and as specified in the parties' agreement and that McKinsey was required to install fire protection at its own expense. Section V (A) of the agreement, entitled "ARCHITECT'S RESPONSIBILITY FOR DOCUMENTS," states that:

"All plans, drawings, specifications and other documents prepared by Architect or its consultants or engineers in connection with the Project . . . shall be in compliance with all laws, codes, ordinances and other requirements applicable to the Project (including, without limitation, the relevant building code, the requirements of the local board of fire underwriters or similar body, and any permits for the work) . . . ."

In April 2002, McKinsey submitted a demand for arbitration. K&H responded by commencing the instant CPLR article 75 special proceeding for a permanent stay of arbitration, arguing that the claim was barred by the CPLR 214 (6) three-year statute of limitations for nonmedical malpractice actions. K&H further sought to dismiss McKinsey's claim with prejudice.1 Supreme Court denied the petition, finding that McKinsey's claim was one for breach of contract rather than malpractice because the architects failed to perform a contractual obligation. Supreme Court determined that the claim was timely under CPLR 213 (2) — the six-year contract statute of limitations — and directed the parties to proceed to arbitration. The Appellate Division reversed, holding that the contract provision did not guarantee code compliance, but was an ordinary contractual term by which the parties agreed K&H would provide services in a professional manner. The Court stated that "whether petitioner's alleged failure to comply with the applicable code provisions was a breach of contract or tortious in nature is immaterial for statute of limitations purposes, since the resulting noncompliance is the same, as is the remedy sought" (3 AD3d 143, 146 [2004]). The Appellate Division held that the claim was barred by CPLR 214 (6) — the three-year statute of limitations. We granted leave to appeal and now affirm.

Analysis

CPLR 214 (6) states that "an action to recover damages for malpractice, other than medical, dental or podiatric malpractice, regardless of whether the underlying theory is based in contract or tort" is subject to a three-year statute of limitations. The Legislature specifically amended this statute in 1996 to counteract the effect of decisions by this Court that "abrogat[ed] and circumvent[ed] the original legislative intent" by allowing actions that were technically malpractice actions to proceed under a six-year contract statute of limitations (Revised Assembly Mem in Support, Bill Jacket, L 1996, ch 623).

Prior to the 1996 amendment, we determined the appropriate statute of limitations in nonmedical malpractice actions based upon the proposed remedy instead of the theory of liability (see e.g. Santulli v Englert, Reilly & McHugh, P.C., 78 NY2d 700, 708 [1992]

; Sears, Roebuck & Co. v Enco Assoc., Inc., 43 NY2d 389, 394-395 [1977]). These cases held that liability would not have existed between the parties without the contractual relationship and that there was an implied agreement to perform professional services using due care (see Santulli, 78 NY2d at 707; Sears, 43 NY2d at 396). Parties were permitted to maintain a malpractice action under a breach of contract theory within the six-year statute of limitations, but were limited to damages available in a contract action if the three-year malpractice limitations period had expired (see Santulli, 78 NY2d at 709).

It is the effect of these decisions that the amendment to CPLR 214 (6) was intended to change. The legislative history makes clear that "where the underlying complaint is one which essentially claims that there was a failure to utilize reasonable care or where acts of omission or negligence are...

To continue reading

Request your trial
67 cases
  • Cunningham v. Insurance Co. of North America
    • United States
    • U.S. District Court — Eastern District of New York
    • August 31, 2006
    ...shorter three-year period governing negligence claims under C.P.L.R. 214(4). Cf. Kliment & Frances Halsband Architects v. McKinsey & Co., Inc., 3 N.Y.3d 538, 542, 788 N.Y.S.2d 648, 821 N.E.2d 952 (2004) (concluding that claim against architects was that of professional malpractice not breac......
  • Jefferson Apartments, Inc. v. Mauceri
    • United States
    • New York Supreme Court
    • July 25, 2016
    ...the underlying theory is based in contract or tort” (CPLR 214[6] ; see, Matter of R.M. Kliment & Frances Halsband, Architects [McKinsey & Co., Inc.], 3 N.Y.3d 538, 541–542, 788 N.Y.S.2d 648, 821 N.E.2d 952 [2004] ; Harris v. Kahn, Hoffman, Nonenmacher & Hochman, LLP, 59 A.D.3d 390, 391, 871......
  • N.Y. State Workers' Comp. Bd. v. Sgrisk, LLC
    • United States
    • New York Supreme Court
    • March 1, 2013
    ...Hoffman, Nonenmacher, & Hochman, LLP, 59 A.D.3d 390, 391, 871 N.Y.S.2d 919 [2d Dept 2009]; see Matter of R.M. Kliment & Frances Halsband, Architects [McKinsey & Co. Inc.], 3 N.Y.3d 538, 542 [2004] ). This is true even where the claimed breach of contract is based upon an express contractual......
  • N.Y. Workers' Comp. Bd. v. Madden, 2988–11.
    • United States
    • New York Supreme Court
    • March 1, 2013
    ...Hoffman, Nonenmacher & Hochman, LLP, 59 A.D.3d 390, 391, 871 N.Y.S.2d 919 [2d Dept 2009]; see Matter of R.M. Kliment & Frances Halsband, Architects [McKinsey & Co. Inc.], 3 N.Y.3d 538, 542 [2004] ). Accordingly, even a claim for breach of an express contractual promise against a professiona......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT