McDonald v. Welch

Decision Date05 May 1970
Docket NumberNo. 53951,53951
PartiesThomas J. McDONALD d/b/a M & M Construction Company, Appellant, v. John WELCH and Margaret Welch, Appellees.
CourtIowa Supreme Court

Peddicord, Simpson & Sutphin, Des Moines, for appellant.

Dan Johnston, Des Moines, for appellees.

LeGRAND, Justice.

This is an action to foreclose a mechanic's lien against defendants' residence, which was extensively damaged by fire on December 12, 1968. Shortly thereafter defendants entered into an oral agreement with plaintiff to repair the house for a total price of approximately $6600.00, of which $6000.00 was to be paid by defendants' insurance carrier.

Plaintiff started the repair work on December 21, and worked intermittently until January 2, 1969, when defendants refused to permit him to continue. Although the evidence is in dispute as to the reason for the termination, we agree with plaintiff that the trial court decree--from which defendants have not appealed--establishes the termination of contract was without fault on the part of plaintiff. The trial court made no such specific finding; but we believe it was a prerequisite to the holding that plaintiff is entitled to his mechanic's lien. 36 Am.Jur., Mechanics' Liens, sections 35--36, pages 38--39; Keys v. Garben, 149 Iowa 394, 395, 128 N.W. 337; Annotation, 51 A.L.R.2d 1009.

Plaintiff's petition as amended asks for $3306.00 as the reasonable value of services rendered and materials furnished between December 21, 1968 and January 2, 1969. The trial court awarded him only $1365.00. Plaintiff asks us to allow him the full amount he claims. We affirm the trial court.

I. We start with the assumption that plaintiff is entitled to a mechanic's lien and that the work done was performed in a workmanlike manner, an issue hotly contested at trial but which we take as a final adjudication because of defendants' failure to appeal. See Hanson Lumber Co. v. De Moss, 253 Iowa 204, 208, 111 N.W.2d 681, 685. We further accept the rule that the proper measure of recovery is the reasonable value of the services rendered and materials furnished up to the date the contract was terminated. Both plaintiff and defendants urge this rule, relying on Knudson v. Bland, 253 Iowa 614, 619, 113 N.W.2d 242, 245, and citations; Parker v. Holmes, 79 Ariz. 82, 284 P.2d 455, 457, 51 A.L.R.2d 1005; Jacobs v. Jones, Colo., 423 P.2d 321, 322. See Annotation, 51 A.L.R.2d 1010(2)(a) for other cases supporting this view.

We are confronted, then, with a single issue to be decided on this de novo appeal. What is the reasonable value of the services rendered and materials furnished by plaintiff?

We point out the authorities heretofore cited, including our Knudson v. Bland opinion, distinguish between Reasonable value to the owner and Actual cost to the contractor. It is the former to which the plaintiff is entitled.

The question is exclusively one of fact and depends entirely upon the proof to support the claim. There was voluminous testimony concerning the work done and numerous exhibits were introduced. However, in the last analysis plaintiff relies on his exhibit 13. This exhibit was prepared some three or four months after the contract was terminated and lists each item for which he seeks payment. It adds up to a total of $3684.00. Later the amount was reduced to $3301.00 by elimination of the bill for electrical work, which defendants had paid directly to the electrical contractor.

Plaintiff's proof at its best is contradictory and unsatisfactory. Of the amounts shown on exhibit 13 some are of questionable propriety. Others appear to be duplications, and still others, particularly labor claims, are admittedly incorrect both as to the amount charged and the hours worked.

Much of plaintiff's trouble may be traced to inexperience as a contractor. Although only involving $6600.00 this was his 'giggest job.' He had neither the equipment nor the financing to handle it. He had no tools or equipment, no regular employees, no insurance coverage. All these were furnished by a friendly competitor, Joseph Gazzo, who also gave plaintiff money and advice, particularly the latter.

Plaintiff did not even have such day-to-day items as buckets, shovels, brooms, cleaning rags, saws, safety helmets, goggles, barrels, picks, wrecking bars, hammers, ladders, drop cloths, gloves, and small hand tools.

Plaintiff literally kept books out of his pocket. He has virtually no records, no cancelled checks showing payments, few receipts. The inevitable result is a failure of proof.

We detail a few things from exhibit 13 to show the unsatisfactory nature of the evidence. Although plaintiff advertised he made free estimates--which was one of the reasons defendants sought him out--exhibit 13 contains a charge of $85.00 for making an estimate. When questioned about this, plaintiff's only explanation was, 'The advertising for free estimates did not pertain to fire jobs. * * *'

One material bill was charged to defendants at.$331.00, although the receipt shows it should have been $227.00. Another was billed to defendants at $72.00 when the correct amount was $17.00. Plaintiff employed three or four persons for common labor and the evidence shows they were paid $2.00 an hour. However, they were listed as having received either $3.00 or $3.50 per hour. In each instance, too, the hours for which defendants were charged exceeded those for which the men were paid. For one laborer plaintiff charged defendants 51 1/2 hours, but could show only 34 hours worked; for another he charged 57 hours, but the evidence was limited to 40 1/2; and for himself he listed 76 hours instead of the 44 for which he could account.

Plaintiff also insists he is entitled to a 25 percent markup on both labor and material for profit.

Although the authoritis are split on the propriety of allowing profit as a lienable claim under statutes like ours which afford liens 'to secure payment for material or labor furnished or labor performed' (section 572.2, Code), we do not appear to have had this question on the precise facts now before us. In A & R Concrete & Construction Co. v. Braklow, 251 Iowa 1067, 1073, 103 N.W.2d 89, 92, we held profit was an allowable item in a cost plus contract. See 57 C.J.S. Mechanics' Liens § 49, page 540.

In the present case, however, we must measure plaintiff's lien by the reasonable value of material furnished and labor performed.

Other jurisdictions have split on the question. Some hold statutes similar to ours do not permit profit to be included in the value of work done or material furnished. Withrow v. Wright, 215 Ark. 654, 222 S.W.2d 809, 811, and Hyde v. Taylor, 235 Ark. 113, 357 S.W.2d 289, 292. However, a contrary result was reached in Bangor Roofing & Sheet Metal Co. v. Robbins Plumbing Co., 151 Me, 145, 116 A.2d 664 and Rebisso Inc. v. Frick, 159 Ohio St. 449, 112 N.E.2d 651, 654; House v. Fissell, 188 Md. 160, 51 A.2d 669, 672; ...

To continue reading

Request your trial
9 cases
  • Flynn Builders, L.C. v. Lande
    • United States
    • Iowa Supreme Court
    • June 1, 2012
    ...we have frequently held the trial court is in a more advantageous position than we to put credence where it belongs.” McDonald v. Welch, 176 N.W.2d 846, 849 (Iowa 1970).III. Discussion. A. Law Related to Mechanic's Liens and Substantial Performance. Mechanic's liens were not recognized at c......
  • Sulzberger Excavating, Inc. v. Glass
    • United States
    • Iowa Court of Appeals
    • March 20, 1984
    ...we have frequently held the trial court is in a more advantageous position than we to put credence where it belongs. McDonald v. Welch, 176 N.W.2d 846, 849 (Iowa 1970) (citations omitted). The burden of proof is upon the mechanic's lien claimant. Ringland-Johnson-Crowley Co. v. First Centra......
  • Olberding Const. Co., Inc. v. Ruden, 2--57009
    • United States
    • Iowa Supreme Court
    • June 30, 1976
    ...value of the services rendered and materials furnished, and should be distinguished from actual cost to the contractor. McDonald v. Welch, 176 N.W.2d 846, 847 (Iowa 1970). The Rudens assert trial court's figure of $5,114.85 is too First, the Rudens direct our attention to Olberding's initia......
  • Nepstad Custom Homes Co. v. Krull
    • United States
    • Iowa Court of Appeals
    • November 28, 1994
    ...we have frequently held the trial court is in a more advantageous position than we to put credence where it belongs. McDonald v. Welch, 176 N.W.2d 846, 849 (Iowa 1970). We note that in Sulzberger, the defendant raised a counterclaim based on failure to perform work in a workmanlike manner, ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT