Mechanical Air Engineering Co. v. Totem Const. Co., 1

Decision Date09 May 1989
Docket NumberNo. 1,CA-CIV,1
PartiesMECHANICAL AIR ENGINEERING COMPANY, an Arizona corporation, Plaintiff-Appellee, v. TOTEM CONSTRUCTION COMPANY, an Arizona corporation, Defendant-Appellant. 9924.
CourtArizona Court of Appeals
OPINION

GRANT, Chief Judge.

This appeal raises a question of first impression: whether a liquidated damage provision in a contract is enforceable only upon a showing of actual damages. The appeal is taken from a partial summary judgment on the liquidated damage issue, an arbitration award and an award of attorney's fees.

FACTS

Totem Construction Company (Totem) was the general contractor on some remodeling and construction at Glendale Community College. Mechanical Air Engineering Company (MAECO) was a subcontractor, furnishing labor and materials for heating, ventilating, air conditioning, sheet metal, and plumbing work. The parties agreed in paragraph 19 of their contract to damages in the amount of $350 for each day of MAECO's delay:

The SUBCONTRACTOR will cooperate with the CONTRACTOR and other SUBCONTRACTORS whose work might interface with the SUBCONTRACTOR'S work and will participate in the coordination of such interface as required, specifically, noting and advising the CONTRACTOR of any interference. The CONTRACTOR, however, will not be liable to the SUBCONTRACTOR for any delays in scheduling the work to be performed by the SUBCONTRACTOR, or any damages arising from such delays. SUBCONTRACTOR and CONTRACTOR agree that if the SUBCONTRACTOR fails to perform within the time specified on the progress schedule posted at the project site, that damages will occur to the CONTRACTOR but that such damages while capable of calculation are not capable of being specifically known at this time. Therefore in lieu of proof of such damages SUBCONTRACTOR and CONTRACTOR agree that a reasonable sum for such damages (and not as a penalty) is the sum of $350.00 per calendar days in excess of the time specifically and that such shall constitute liquidated damages agreed to.

MAECO sued Totem alleging that $16,000 was owed on its subcontracts and change orders. Totem counterclaimed, alleging that MAECO caused 46 days of delay and seeking $16,100 under the stipulated damage clause.

MAECO moved for summary judgment on the counterclaim, arguing that the damage clause was unenforceable because Totem suffered no actual loss as a result of any delay in completion of construction. In support of its motion, MAECO attached Totem's response to interrogatories indicating that Totem had been paid the general contract price on the project, $634,198 by Glendale Community College, and that no damages, back charges, or offsets had been assessed against Totem as a result of any construction delays.

Totem filed a cross-motion for summary judgment, arguing that it was immaterial whether it had been assessed any damage under its general contract. MAECO claims that Totem provided no evidence that it had incurred any actual loss as a result of MAECO's delay or that its actual loss was difficult to prove.

The trial court granted MAECO's motion for partial summary judgment because Totem failed to show any loss:

THE COURT: Gentlemen, I think that the way I understand the law, the liquidated damage provision is enforceable if there is some showing of damages. I don't see any.

I'm going to grant the motion of Maeco and deny the motion of Totem. I am setting it forth on the record on that specific issue. I may be wrong. I think there has to be some showing of some damage to trigger the concept that it would be difficult to assess the value of that damage.

The trial court entered judgment in favor of MAECO for $16,101.63. The trial court also awarded MAECO $10,000 of the $16,854.50 requested attorney's fees.

ISSUES

Totem raises two arguments on appeal:

(1) That the liquidated damage clause was enforceable regardless of whether any evidence of actual loss was provided; and

(2) That Totem offered some evidence of actual loss.

LIQUIDATED DAMAGE CLAUSE

We hold that a contract's liquidated damage clause is enforceable despite no showing of an amount of actual damage. We do so based on general contract principles and law interpreting liquidated damage clauses specifically.

First, it is a general principle of contract law that when parties bind themselves by a lawful contract, a court must give effect to that contract as written if the terms are clear and unambiguous. Estes Co. v. Aztec Const., Inc., 139 Ariz. 166, 168, 677 P.2d 939, 941 (App.1983). Paragraph 19 imposes no specific requirement that Totem show actual damages. On the other hand, MAECO argues that the clause does not say that no damages whatsoever need be shown.

Even though those specific words are not included, we cannot impose such a requirement on Totem. To require Totem to show an amount of actual damages would be to require Totem to do precisely what the parties agreed Totem need not do. Imposing such a requirement would not give effect to the contract's clear and unambiguous terms.

Second, we hold that the liquidated damage clause is reasonable even though it contains no requirement that the party enforcing the clause show actual damages.

When a court concludes that a liquidated damage clause is a penalty, it will refuse to enforce the clause as void and against public policy. Instead, it will limit recovery to the actual loss. However, when a court concludes that the clause is for liquidated damages, it will enforce the clause.

This distinction was developed by the courts of equity, which refused to enforce penal bonds. In order to coerce performance, a penal bond required the promisor to pay a stipulated amount upon breach. Later courts concluded that when actual loss could not be easily calculated, a liquidated damage clause was a valid alternative. See generally Comment, Liquidated Damages: A Comparison of the Common Law and the Uniform Commercial Code, 45 Fordham L.Rev. 1349, 1349-50 (1977). A liquidated damage clause serves a useful purpose when it would be difficult to prove the amount of loss with the degree of certainty required by law. 5 Corbin on Contracts § 1062 at 357-58, 361. A liquidated damage clause promotes...

To continue reading

Request your trial
5 cases
  • Tortolita Veterinary Servs. v. Rodden
    • United States
    • Arizona Court of Appeals
    • 27 Agosto 2021
    ... ... ¶ ... 1 Tortolita Veterinary Services PC, dba Adobe ... applying the law." Eller Media Co. v. City of ... Tucson, 198 Ariz. 127, ¶ ... Mech. Air ... Eng'g Co. v. Totem Constr. Co., 166 Ariz. 191, 194 ... (App ... ...
  • Longnecker v. Am. Express Co., 2:14-cv-0069-HRH
    • United States
    • U.S. District Court — District of Arizona
    • 28 Mayo 2014
    ...court must give effect to that contract as written if the terms are clear and unambiguous." Mechanical Air Eng'g Co. v. Totem Const. Co., 801 P.2d 426, 427-28 (Ariz. Ct. App. 1989). Plaintiffs argue that defendants have failed to meet their burden of showing that valid arbitration agreement......
  • Tortolita Veterinary Servs. v. Rodden
    • United States
    • Arizona Court of Appeals
    • 2 Julio 2021
    ...damages has the burden of persuasion to show that the clause is for liquidated damages and not a penalty. Mech. Air Eng'g Co. v. Totem Constr. Co., 166 Ariz. 191, 194 (App. 1989).¶11 A liquidated damages provision is reasonable if it "approximates either the loss anticipated at the time of ......
  • Carson v. Ryan
    • United States
    • U.S. District Court — District of Arizona
    • 16 Octubre 2020
    ...and unambiguous." Longnecker v. Am. Exp. Co., 23 F. Supp. 3d 1099, 1106 (D. Ariz. 2014) (quoting Mechanical Air Eng'g Co. v. Totem Const. Co., 801 P.2d 426, 427-28 (Ariz. Ct. App. 1989)) (emphasis added). Extrinsicevidence may be used only for "contract interpretation" and may not be used "......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT