Metro Insulation Corp. v. Leventhal

Decision Date12 April 1973
Citation1 Mass.App.Ct. 213,294 N.E.2d 508
PartiesMETRO INSULATION CORP. v. Robert LEVENTHAL & others.
CourtAppeals Court of Massachusetts

Robert J. Sherer, Boston (Judith K. Wyman, Newton Center, with him), for Robert Leventhal and others.

Peter J. Gagne, Boston (Sally A. Corwin, Boston, with him), for Metro Insulation Corp.

Brian P. Shillue, Boston, for Boston Housing Authority.

Before HALE, C.J., and GOODMAN and GRANT, JJ.

GRANT, Justice.

This proceeding under G.L. c. 149, § 29 (as amended through St.1964, c. 609, §§ 4 and 5), was originally brought by Metro Insulation Corp. (Metro), a sub subcontractor, against persons doing business as Beacon Construction Company 1 (Beacon), the general contractor, and the surety on Beacon's bond 2 to recover for two extras of insulation work performed by Metro 3 in connection with the construction of a federally assisted housing project for the elderly owned by the Boston Housing Authority (Authority). The Authority was brought into the proceeding on Beacon's counterclaim alleging, in effect, that the Authority should be responsible to beacon for any liability for extras which Metro might succeed in establishing. Frank Sullivan Co. (Sullivan), the plumbing subcontractor and the concern with which Metro had its direct contractual relationships, was not joined as a party.

Metro, following Beacon's responses to Metro's notices to admit facts, moved with supporting affidavit for the entry of a decree in its favor (G.L. c. 149, § 29; G.L. c. 231, § 59). Beacon filed an affidavit in opposition to Metro's motion and (together with the surety) moved, with supporting affidavit, for dismissal of Metro's original bill or, in the alternative, for a decree against the Aughority. The Authority filed an affidavit in opposition to so much of Beacon's motion as was directed to it, but no affidavit directly responsive to the matters set out in Metro's affidavit. After hearing the Superior Court allowed Metro's motion, denied Beacon's motion, and entered a final decree ordering Beacon and its surety to pay Metro the total of both extras (see fn. 3, supra). Beacon and the surety have appealed from the interlocutory decree denying their motion and from the final decree.

We shall confine our consideration of the case to the specific issues which have been argued in the briefs of the parties. Rule 1:13 of the Supreme Judicial Court, 351 Mass. 738. Rule 1:13 of the Appeals Court. Beacon does not seriously dispute Metro's right to recover for either of the claimed extras, contending instead that the ultimate responsibility should lie with the Authority to pay for all work not required under the basic contract between itself and the Authority. The Authority's main reliance is on the asserted failure of Metro and Beacon to comply with procedural requirements found in the basic contract. As the two claims for extras are unrelated we discuss them separately. The facts recited are taken from Beacon's responses to Metro's notices to admit and from the various affidavits. None of them is disputed.

1. The first claim for extra payment is with respect to Metro's insulation of certain hot water piping in the seventh floor ceiling and of certain cold water piping in the pump and boiler rooms of the building.

At some point in time prior to June 13, 1967, the engineer employed by the Authority's architect inquired of Metro as to the type of insulation it proposed to employ in the upper floors of the building. By its letter of that date to the engineer Metro replied that the specifications of the basic contract did not call for the insulation of such piping 4 and that it had not carried anything for such insulation in the bid which it had submitted to Sullivan, the plumbing subcontractor. By letter of June 30 Sullivan requested Metro to submit a . . .. c. Except in an emergency by the specifications.' By letter of July 17 Metro submitted separate prices to Sullivan for insulation of hot water piping in the seventh floor ceiling and cold water piping in the pump and boiler rooms. Acting on a request from the Authority, Sullivan instructed Metro to send a breakdown of its quotations 'priced in accordance with the contract specifications.' Metro did so, and Sullivan in turn sent the revised quotation to Beacon on August 21. On August 22 Beacon wrote Sullivan that the architect had 'verbally authorized that this insulation was to be installed and that it was subject to a change order' and concluded by saying that '(i)n the meantime, it appears that we are authorized to proceed with this change.' Sullivan, by a letter of August 24, sent a copy of Beacon's letter to Metro.

Following Metro's receipt of the last two letters a conference was had between and among Metro, Sullivan, Beacon, the architect, the engineer and the Authority at which Metro was 'informed by all those present that a change order for the proposed extra insulation work in the amount of Metro's proposal was forthcoming and that Metro was to proceed with the work immediately so as not to hold up' the project. Metro thereafter went ahead and completed the work 'in reliance on the oral and written authorization to proceed and the agreement to pay it additional money.' 5 The Authority, apparently acting under the provisions of art. 10 of the General Conditions of the basic contract, 6 submitted a relevant change order to the Department of Housing and Urban Development (HUD) for its written approval. HUD, for reasons we need not assess, refused to approve the change order for the insulation work. Metro does not appear to have received notice of such disapproval until on or about November 14, 1967, by which time it had completed the work for which it now seeks to recover the price quoted by it. There then followed a flurry of correspondence whereby those concerned either did or did not succeed in complying with the requirements of art. 15 7 of [1 Mass.App.Ct. 218] the General Conditions of the basic contract. We need not decide any question in that regard.

No one contends that the insulation work which forms the basis of this claim was required by the specifications. Beacon suggests, and the Authority argues, that the claim should be barred by the failure of Metro and Sullivan to comply with the notice and other requirements of art. 15 of the General Conditions (fn. 7) following HUD's failure to approve the change order. 8 We do not think there was a 'dispute' within the meaning of art. 15; almost as soon as the problem was discovered, and even before HUD approval was sought, it was expressly agreed by the archietect and all the parties to this litigation that the insulation requested by the architect was not required by the specifications and should be paid for as an extra. 9 Cf. Chiappisi v. Granger Contracting Co. Inc., 352 Mass. 174, 176--178, 223 N.E.2d 924, Beacon Construction Co. of Massachusetts v. United States, 314 F.2d 501, 504 (Ct.Cl.). If the Authority had requested us to consider the effect of the provisions of art. 10 of the General Conditions (fn. 6), we would have regarded them as waived by the Authority's actions, prior to seeking HUD approval of the change order, in directing the work to proceed and agreeing that it should be paid for. See Stuart v. Cambridge, 125 Mass. 102, 109--110; Farm-Rite Implement Co. v. Fenestra Inc., 340 Mass. 276, 286-- 287, 163 N.E.2d 285; M. L. Shalloo, Inc. v. Ricciardi & Sons Construction, Inc., 348 Mass. 682, 685--686, 206 N.E.2d 239; J. P. Smith Co., Inc. v. Wexler Construction Co., Inc., 353 Mass....

To continue reading

Request your trial
3 cases
  • Hardware Specialties, Inc. v. Mishara Const. Co., Inc.
    • United States
    • Appeals Court of Massachusetts
    • May 21, 1974
    ...Jefferson Constr. Co., 339 Mass. 356, 367--369, 159 N.E.2d 95 (1959); Metro Insulation Corp. v. Leventhal, 1 Mass.App. ---, --- - ---, a 294 N.E.2d 508. Contrast Daly v. Kingston, 177 Mass. 312, 316--317, 58 N.E. 1019 (1901); Meegan v. Hall, 241 Mass. 449, 451--452, 135 N.E. 555 (1922). Suc......
  • Com. v. Bartoloni
    • United States
    • Appeals Court of Massachusetts
    • April 9, 1974
  • John H. Barrett, Inc. v. Joseph Rugo, Inc.
    • United States
    • Appeals Court of Massachusetts
    • March 27, 1975
    ...v. Salem, 214 Mass. 358, 362--363, 101 N.E. 974 (1913). See also Metro Insulation Corp. v. Leventhal, 1 Mass.App. ---, ---, b 294 N.E.2d 508 (1973). Judgment 1 The Aetna Casualty & Surety Company.a. Mass.Adv.Sh. (1975) 123, 125.b. Mass.App.Ct.Adv.Sh. (1973) 249, 253. ...

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT