Middle River-Snake River v. Drewes, Inc.

Decision Date15 February 2005
Docket NumberNo. A04-825.,A04-825.
Citation692 N.W.2d 87
PartiesMIDDLE RIVER-SNAKE RIVER WATERSHED DISTRICT, Plaintiff, v. DENNIS DREWES, INC., Appellant, J.O.R. Engineering, Inc., Respondent.
CourtMinnesota Court of Appeals

Zenas Baer, Zenas Baer and Associates, Hawley, MN, for appellant. Stephen W. Plambeck (pro hac vice), Jacqueline S. Anderson, Nilles, Ilvedson, Stroup, Plambeck & Selbo, Ltd., Fargo, ND, for respondent.

Considered and decided by KALITOWSKI, Presiding Judge; LANSING, Judge; and WRIGHT, Judge.

OPINION

LANSING, Judge.

In this dispute over the construction of a floodwater impoundment system, the contractor challenges two district court orders: its grant of summary judgment dismissing a counterclaim against the project engineer and its decision to cap damages. Because we find no error in the district court's dismissal of the contractor's counterclaim for failure to serve an expert-identification affidavit as required by Minn.Stat. § 544.42, subds. 2 and 4 (2004), we do not reach the damages issue, and we affirm.

FACTS

Middle River-Snake River Watershed District contracted with Dennis Drewes, Inc., to work on the Angus Oslo flood-impoundment project. After submitting its initial bid, Drewes inspected the project site several times and examined soil reports accompanying the project proposal. These soil reports, prepared by Midwest Testing Laboratory, indicated that the soil was "moist" and therefore ideal for construction. At the time of bidding, the site appeared undisturbed by farm operations, and the contract did not refer to ongoing farming operations.

The contract, in compliance with statutory requirements, appoints a project engineer, J.O.R. Engineering, Inc., and describes the project engineer's role. J.O.R. is not, however, a party to the contract. The contract sets forth specifications for the work, provisions for changed conditions, and responsibilities of the parties. It requires the contractor to achieve an overall compaction of 95% and prohibits lifts greater than twelve inches in height.

The contract explicitly addresses the work alterations and changed site conditions that relate to this litigation. If the contractor discovers a materially different site condition that affects its work, the contract requires it to provide written notice to the engineer and the other party before performing the affected work, particularly if the contract adjustment requires additional compensation. After acknowledging that the engineer shall have the right to modify specifications as circumstances may require, the contract provides that "[i]n this event, ... no change shall be made that will ... increase the total cost by more than ten percent (10%) of the total contract price." The contract explains the engineer's authority and responsibilities, including its involvement in developing the plan's specifications and monitoring the site, but notes in several places that the engineer's review of the work and specifications does not relieve Drewes of its contractual obligations.

After beginning work on the project, two independent problems arose. First, the soil was wetter than anticipated. Second, a neighboring farmer, who had a lease with the watershed district, disked the project site. The combined effect of the disking and the wet soil made it more difficult to obtain the required compaction and caused Drewes to use lifts greater than twelve inches in height. Drewes, however, did not notify either J.O.R. or the watershed district of the changed conditions before working on the affected areas.

Upon discovering that neither the compaction nor the lift heights complied with the contract's specifications, the watershed district filed a declaratory action to determine the rights and responsibilities of the parties under the contract. In its answer to the complaint, Drewes asserted multiple counterclaims against the watershed district. Drewes also impleaded J.O.R. as an "additional defendant on the counterclaim," alleging three causes of action: negligence, estoppel, and tortious interference with its contract. The watershed district moved for summary judgment on Drewes' counterclaims. J.O.R. also moved for summary judgment because, among other reasons, Drewes failed to serve a mandatory expert-identification affidavit.

The district court initially denied J.O.R.'s and the watershed district's summary-judgment motions, but the motions were twice renewed. In the first renewal, the watershed district grouped them with a motion in limine to cap damages. The district court granted the motion to cap damages but again denied summary judgment against Drewes. Shortly before the second renewal, Drewes and the watershed district resolved their "respective claims against each other" and stipulated to dismissal. The stipulation preserved Drewes' claim against J.O.R. Following the second renewal, initiated by J.O.R., the district court granted summary judgment for J.O.R. for three reasons: (1) Drewes failed to comply with the expert-witness disclosure requirements in Minn.Stat. § 544.42 (2004); (2) J.O.R. owed no duty to Drewes; and (3) the alleged breach did not proximately cause the harm suffered.

The district court's summary-judgment order, in addition to dismissing Drewes' negligence "counterclaim" against J.O.R., also dismissed Drewes' claim for estoppel and intentional interference with contractual relations. Drewes appeals from that part of the summary judgment dismissing his negligence claim against J.O.R. and also appeals the district court's earlier order that capped the amount of damages that could be recovered.

ISSUES
I. Did the district court err in dismissing the contractor's negligence claim against the project engineer for failure to serve an expert-identification affidavit within 180 days after initiating the professional-malpractice claim?
II. Did the district court err in granting summary judgment because it concluded the engineer owed no duty to the contractor?
ANALYSIS

On appeal from summary judgment, we consider whether genuine issues of material fact exist and whether the district court erred in its application of the law. Offerdahl v. Univ. of Minn. Hosps. & Clinics, 426 N.W.2d 425, 427 (Minn.1988). This consideration views the evidence in the light most favorable to the nonmoving party and resolves any doubts on the existence of a material-fact issue against the moving party. Fabio v. Bellomo, 504 N.W.2d 758, 761 (Minn.1993).

I

The interpretation of a statute is a question of law that we review de novo. Lolling v. Midwest Patrol, 545 N.W.2d 372, 375 (Minn.1996). When applying a statute, courts must give effect to its plain meaning, which takes into account the structure of the statute and the language of the specific statutory provision in the context of the statute as a whole. Glen Paul Court Neighborhood Ass'n v. Paster, 437 N.W.2d 52, 56 (Minn.1989) (reasoning that sections of statute must be read together to give words their plain meaning); see also United States v. Jennings, 323 F.3d 263, 274-75 (4th Cir.2003)

(determining meaning by reference to language itself, specific context in which language is used, and broader context of statute as whole). We presume that plain and unambiguous statutory language manifests legislative intent. Lenz v. Coon Creek Watershed Dist., 278 Minn. 1, 9, 153 N.W.2d 209, 216 (1967). Courts refrain from construing statutory provisions that convey a plain meaning "in order to preserve language as an effective medium of communication from legislatures to courts." Krzalic v. Republic Title Co., 314 F.3d 875, 879 (7th Cir.2002).

Negligence actions against professionals, including engineers, must comply with the disclosure requirements in Minn.Stat. § 544.42, subd. 2 (2004). Subject to exceptions that do not apply here, the expert-witness disclosure requirements provide for service of two affidavits on the adverse party. Id. Generally, a party must serve the first affidavit, an affidavit of expert review, with the pleadings. Minn.Stat. § 544.42, subds. 2(1), 3 (2004). Within 180 days after the first affidavit, the party must serve a second affidavit, the expert-identification affidavit, which identifies the expert witnesses and provides the substance of the experts' opinions together with a summary of the grounds for each opinion. Id., subds. 2(2), 4 (2004). Only the second affidavit is at issue in this litigation.

A party's failure to provide the second affidavit "results, upon motion, in mandatory dismissal of each action with prejudice as to which expert testimony is necessary to establish a prima facie case." Id., subd. 6 (2004). The mandatory-dismissal subdivision provides that a motion to dismiss "based upon claimed deficiencies of the affidavit ... shall not be granted unless, after notice by the court, the nonmoving party is given 60 days to satisfy the disclosure requirements." Id.

It is undisputed that Drewes served the expert-review affidavit, but failed to serve the expert-identification affidavit within the following 180 days. J.O.R. filed its motion to dismiss for noncompliance with the expert-identification requirements, and Drewes filed the missing affidavit three days later. Drewes contends that filing the missing affidavit within 60 days after the motion to dismiss exempts it from the mandatory-dismissal provision and that the district court erred in determining that the 60-day cure period did not apply. No Minnesota appellate court has addressed this precise issue.

The disputed statutory provision prescribes a penalty for failure to serve the expert-identification affidavit within the required time period:

Failure to comply ... results, upon motion, in mandatory dismissal of each action with prejudice as to which expert testimony is necessary to establish a prima facie case, provided that an initial motion to dismiss an action under this paragraph based upon claimed deficiencies of the affidavit ... shall not be granted unless, after
...

To continue reading

Request your trial
19 cases
  • Lake Superior v. Hammel, No. A05-800.
    • United States
    • Minnesota Court of Appeals
    • 6 d2 Junho d2 2006
    ...must comply with expert-disclosure requirements under Minn. Stat. § 544.42, subd. 2 (2004). See Middle River-Snake River Watershed Dist. v. Dennis Drewes, Inc., 692 N.W.2d 87, 90 (Minn.App.2005) (discussing expert-affidavit requirements in negligence action against engineer). The expert-rev......
  • Fontaine v. Steen, No. A07-2327.
    • United States
    • Minnesota Court of Appeals
    • 27 d2 Janeiro d2 2009
    ...(2008). We have previously noted the similarity in professional malpractice proceedings. See Middle River-Snake River Watershed Dist. v. Dennis Drewes, Inc., 692 N.W.2d 87, 91 (Minn. App.2005) (discussing parallel reasoning used in construing requirements of Minn. Stat. § 145.682 and Minn.S......
  • Guzick v. Kimball
    • United States
    • Minnesota Court of Appeals
    • 6 d1 Outubro d1 2014
    ...may not invoke the safe-harbor provision to file a first affidavit of expert disclosure. See Middle River-Snake River Watershed Dist. v. Dennis Drewes, Inc., 692 N.W.2d 87, 91-92 (Minn. App. 2005). Thus, if appellant failed to file documents that could satisfy the expert-disclosure requirem......
  • Lariat Cos. v. Wigley, A17-0210
    • United States
    • Minnesota Court of Appeals
    • 14 d1 Setembro d1 2020
    ...with respect to the other four badges of fraud, wife has forfeited this challenge. See Middle River-Snake River Watershed Dist. v. Dennis Drewes, Inc., 692 N.W.2d 87, 91-92 (Minn. App. 2005) (concluding that challenge to district court's legal conclusion was waived because the issue was not......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT