Milgard Tempering, Inc. v. Selas Corp. of America

Citation761 F.2d 553
Decision Date24 May 1985
Docket NumberNos. 84-4025,84-4056,s. 84-4025
Parties40 UCC Rep.Serv. 1714 MILGARD TEMPERING, INC., Plaintiff-Appellant-Cross-Appellee, v. SELAS CORPORATION OF AMERICA, a foreign corporation, Defendant-Appellee-Cross-Appellant.
CourtU.S. Court of Appeals — Ninth Circuit

J. Richard Creatura, Gordon, Thomas, Honeywell, Malanca, Peterson & O'Hern, Tacoma, Wash., for plaintiff-appellant-cross-appellee.

Edward M. Lane, Johnson, Lane & Gallaher, Tacoma, Wash., for defendant-appellee-cross-appellant.

Appeal from the United States District Court for the Western District of Washington.

Before WRIGHT, KENNEDY and ANDERSON, Circuit Judges.

EUGENE A. WRIGHT, Circuit Judge:

This case presents the question whether a consequential damages limitation justified summary judgment for defendant-seller when the limited remedy of repair and replacement allegedly failed of its essential purpose. We hold that it did not and remand for trial.

FACTS:

Milgard Manufacturing, Inc. cuts and installs glass for use in residential and commercial construction. In 1979, it negotiated a contract with Selas Corporation of America to purchase a sophisticated glass tempering furnace. With Selas' consent, this contract was assigned to plaintiff, Milgard Tempering, Inc. Negotiations, conducted with the assistance of counsel for both parties, culminated in a detailed purchase contract.

Selas contracted to design and manufacture a complex horizontal batch tempering system, for a purchase price of $1,450,000 with a $50,000 bonus if "all major components required to erect and install the equipment [were] delivered to purchaser by January 31, 1980." Contract Sec. 29.0. Milgard agreed to assemble the furnace on site, with Selas assisting with the start up and adjustment for testing. Selas retained a security interest in the furnace to insure payment.

The furnace was placed in commercial production in July 1980 without preacceptance testing as required by section 25.0 of the contract. Milgard immediately began to have problems with the system. Selas attempted to repair it but was unable to satisfy Milgard.

In January 1982, Milgard sued Selas alleging that the system was still not operating in accordance with the contract, notwithstanding Selas' extensive efforts to remedy the problems. Pursuant to negotiations, Milgard agreed to dismiss its action without prejudice and Selas undertook to operate the equipment and reimburse Milgard for operating losses during a two-month period, the losses amounting to $229,926.33.

The parties disagreed as to Selas' success in bringing the furnace system into compliance with contract specifications and Milgard sued again in March 1983. Its complaint sought relief based on "breach of contract, product liability and breach of express and implied warranty."

Selas moved for summary judgment on these issues: (1) whether a contractual bar to "consequential damages [was] enforceable as a matter of law, thereby precluding plaintiff's claim for damages; (2) [w]hether [Selas was] entitled to ... $179,417.00 plus statutory interest as the outstanding balance due ..." and (3) whether the parties had previously settled their dispute through an accord and satisfaction.

The district court granted summary judgment for Selas. It ruled that section 28.5 of the contract, 1 which excluded Selas' The court awarded Selas $129,417 plus statutory interest, representing the balance of the purchase price, less the delivery bonus. Subsequently, the court awarded Selas $66,222.58 in attorneys' fees under section 28.1(f) of the contract, but denied recovery for time spent by Selas' in-house counsel in actively litigating the case. 3

liability for consequential damages, was enforceable as a matter of law since the risk allocation provisions were the result of negotiations between sophisticated parties and their counsel. The court held further that the parties had reached an "[a]ccord and satisfaction" rendering the damage provisions of Wash.Rev.Code 62A.2-717 (1983) 2 inapplicable. The court was apparently referring to the terms of the agreement under which the first lawsuit was dropped.

Milgard appeals the summary judgment and award of attorneys' fees while Selas cross-appeals summary judgment on the delivery bonus and the failure to award attorneys' fees for in-house counsel.

ANALYSIS:

I. Standard of Review

We review "[a]n appeal from an order granting or denying a summary judgment ... de novo." Alaska v. United States, 754 F.2d 851, 853 (9th Cir.1985). "All 'evidence and factual inferences' must be viewed in the light most favorable to the adverse party and the summary judgment may be upheld only if 'there are no genuine issues of material fact and [the movant is] entitled to judgment as a matter of law.' " Id. (quoting Martino v. Santa Clara Valley Water Dist., 703 F.2d 1141, 1145 (9th Cir.), cert. denied, --- U.S. ----, 104 S.Ct. 151, 78 L.Ed.2d 141 (1983) ).

Federal law governs the appropriateness of summary judgment under Fed.R.Civ.P. 56(c). However, Washington law governs the substantive issues in this diversity action. Bank of California, N.A. v. Opie, 663 F.2d 977, 980 (9th Cir.1981). We review district court interpretations of state law de novo. In re McLinn, 739 F.2d 1395, 1397 (9th Cir.1984) (en banc).

II. Consequential Damages

A. Unconscionability

The contract limited Milgard's remedies in the event of breach of warranty to repair or replacement of the defective equipment. See Contract Sec. 28.5, note 1 supra. Under Wash.Rev.Code Sec. 62A.2-719(3) (1983), consequential damages may be limited or excluded unless the limitation or exclusion is unconscionable. 4 The limitation is prima The district court noted that the consequential damage limitation was the result of "arms length negotiations through competent, experienced counsel," and held that it was conscionable and enforceable as a matter of law. However, unconscionability at the outset is not the only limit on enforcement of a consequential damage limitation.

facie conscionable when commercial parties are involved. Id.

B. Failure of the Limited Remedy

"Where circumstances cause an exclusive or limited remedy to fail of its essential purpose, remedy may be had as provided in this Title." Wash.Rev.Code Sec. 62A.2-719(2) (1983) (emphasis added). "Unreasonable delays in repairing or inability to adequately repair a product" may cause "a limited remedy 'to fail of its essential purpose.' " Lidstrand v. Silvercrest Indus., 28 Wash.App. 359, 365, 623 P.2d 710, 714 (1981) (quoting Ehlers v. Chrysler Motor Corp., 88 S.D. 612, 619, 226 N.W.2d 157, 161 (1975) ). For purposes of Selas' summary judgment motion, we must assume the limited remedy failed of its essential purpose.

The issue becomes whether the separate limitation on consequential damages remains enforceable. The Washington courts have yet to confront a situation in which a party seeks to enforce a consequential damages limitation in the face of a limited repair or replacement remedy which has failed. See Fiorito Bros., Inc. v. Fruehauf Corp., 747 F.2d 1309, 1314 (9th Cir.1984) (predicting Washington law in analogous situation). We must predict how Washington's "highest court would decide [this] case." Id. (quoting Takahashi v. Loomis Armored Car Service, 625 F.2d 314, 316 (9th Cir.1980) ).

The district court did not have the benefit of Fiorito when it ruled on Selas' summary judgment motion. Indeed, when faced with an analogous situation, the Sixth Circuit, applying Washington law, held that the only limit on a separate consequential damage limitation was unconscionability, manifested by "grossly unequal bargaining power at the time of [contract] formation." Lewis Refrigeration Co. v. Sawyer Fruit, Vegetable and Cold Storage Co., 709 F.2d 427, 435 (6th Cir.1983).

However, in Fiorito, we rejected this reasoning and found Wash.Rev.Code Sec. 62A.2-719(2) (1983) to be an independent limit on "contractual arrangements [such as consequential damage limitations] which become oppressive by change of circumstances." Fiorito, 747 F.2d at 1315 (emphasis added) (quoting Official Washington Comments to Sec. 2-719).

In Fiorito we predicted that Washington courts would adopt a case by case approach and examine the provisions of "each contract" to determine whether the parties intended the exclusive remedy and damage exclusion provisions to operate as "separable elements of risk allocation" or as inseparable parts of a comprehensive risk allocation package. Id. (quoting the district court opinion); accord S.M. Wilson & Co. v. Smith Intern., Inc., 587 F.2d 1363, 1375 (9th Cir.1978) (California law requires case by case examination to determine whether "[t]he default of the seller is ... so total and fundamental as to require that its consequential damage limitation be expunged from the contract.")

In light of Fiorito, summary judgment here was inappropriate. Only after all of the circumstances surrounding the negotiation and performance of the contract have been determined at trial can the enforceability of the consequential damages limitation be determined. For instance, its enforceability necessarily depends on whether and the extent to which Selas breached its warranty obligations. These facts are hotly disputed.

III. Judgment for Purchase Price

A. Delivery Bonus

The district court concluded erroneously that Selas conceded its failure to meet the delivery date necessary to earn the bonus. It conceded only that this issue may involve disputed facts. Milgard concedes that entitlement to the bonus should be determined after trial.

B. Accord and Satisfaction

Accord and satisfaction depends upon "a meeting of the minds" leading to "an intention by both parties to satisfy ... prior obligation[s] by performance of the new." Plywood Marketing Assoc. v. Astoria Plywood Corp., 16 Wash.App. 566, 574, 558 P.2d 283, 289 (1976). "The key element...

To continue reading

Request your trial
31 cases
  • Wye Oak Tech., Inc. v. Republic of Iraq
    • United States
    • U.S. District Court — District of Columbia
    • August 17, 2021
    ...PPG Indus., Inc. v. Celanese Polymer Specialties Co., Inc. , 840 F.2d 1565, 1570 (Fed. Cir. 1988) ; Milgard Tempering, Inc. v. Selas Corp. of Am. , 761 F.2d 553, 558 (9th Cir. 1985) ; Burger King Corp. v. Mason , 710 F.2d 1480, 1499 (11th Cir. 1983). This comports with the BSA's requirement......
  • American Nursery Products, Inc. v. Indian Wells Orchards
    • United States
    • Washington Supreme Court
    • September 20, 1990
    ... ... v. Perfection Tire Corp., ... Page 227 ... 125 Wash. 84, 215 P. 360 (1923) ... See also Milgard Tempering, Inc. v. Selas Corp. Iof ... Page 229 ... ...
  • Friends of the Columbia Gorge v. Energy Facility Siting Council
    • United States
    • Oregon Supreme Court
    • December 10, 2020
    ...fees for salaried in-house attorneys, the "modern trend" has been to use the market-value approach. Milgard Tempering, Inc. v. Selas Corp. of Am. , 761 F.2d 553, 558 (9th Cir. 1985) ; see AMX Enterprises, L.L.P. v. Master Realty Corp. , 283 S.W.3d 506, 518 (Tex. App. 2009) (adopting the mar......
  • Ritchie Enterprises v. Honeywell Bull, Inc.
    • United States
    • U.S. District Court — District of Kansas
    • January 17, 1990
    ...F.2d 951, 955 (9th Cir.1977), or where repairs were unreasonably delayed or never effectively made, Milgard Tempering, Inc. v. Selas Corp. of America, 761 F.2d 553, 556 (9th Cir.1985). In other words, when unexpected circumstances presently prevent the agreed remedy from yielding its purpor......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT