Mion Chemical Brick Corp. v. Daniel Const. Co.

Decision Date24 February 1965
Docket NumberNos. 40987,40988,No. 1,s. 40987,1
Citation141 S.E.2d 839,111 Ga.App. 369
PartiesMION CHEMICAL BRICK CORPORATION v. DANIEL CONSTRUCTION COMPANY, Inc. DANIEL CONSTRUCTION COMPANY, Inc. v. MION CHEMICAL BRICK CORPORATION
CourtGeorgia Court of Appeals

Clifford Oxford, Eugene S. Taylor, Atlanta, for plaintiff in error.

Gambrell, Harlan, Russell & Moye, E. Smythe Gambrell, Edward W. Killorin, John K. Train, III, Atlanta, for defendant in error.

Syllabus Opinion by the Court

PANNELL, Judge.

1. Where a prime contractor, without claiming that the work is covered by the subcontract, orally orders extra work, as such, with notice that the subcontractor regards the work as extra and expects additional compensation therefor, the subcontractor can recover for the work notwithstanding a stipulation of the subcontract requiring a written order therefor. State Highway Dep't. v. Wright Contracting Co., 107 Ga.App. 758, 764, 131 S.E.2d 808; see, generally, Anno. in 66 A.L.R. 649; Bailey v. Martin, 101 Ga.App. 63, 112 S.E.2d 807; cp. Heard v. Dooley County, 101 Ga. 619(2), 28 S.E. 986. Upon application of the above ruling to the pleadings and evidence in the instant case, the trial court erred in directing a verdict in favor of the defendant prime contractor. The evidence was sufficient to authorize a finding that at least some, if not all, of the extra work in performing the subcontract was occasioned by faulty work of the prime contractor, that this condition and the necessity for extra work and expectation of remuneration therefor was conveyed to the authorized representative of the prime contractor, and that such representative authorized the extra work.

2. The allegations of the petition in the instant case were sufficient to set forth a cause of action under the ruling in Division 1 above, and the trial court did not err in overruling the general demurrers thereto.

3. Where, prior to or contemporaneously with the execution of a written contract between a prime contractor and a subcontractor, the prime contractor represents that the area where the sbucontractor will have to work will be dried in or roofed over before the subcontractor will be called upon to begin work, and the written contract recites that, 'The subcontractor agrees to begin work as soon as he is notified by the contractor that the ground is clear or the structure (or structures) far enough advanced to allow the beginning of that portion included herein, and will carry forward and complete his work as rapidly as the contractor may judge that the progress of the structure (or structures) will permit,' and it is not alleged that said prior or contemporaneous oral agreement was the inducement or consideration, in whole or in part, for entering into the written contract, damages for the alleged breach of such oral agreement cannot be...

To continue reading

Request your trial
8 cases
  • Brookhaven Landscape & Grading Co., Inc. v. J. F. Barton Contracting Co.
    • United States
    • U.S. Court of Appeals — Eleventh Circuit
    • May 17, 1982
    ...Co. v. Tri-State Electrical Contractors, Inc., 137 Ga.App. 504, 224 S.E.2d 487, 488-89 (1976); Mion Chemical Brick Corp. v. Daniel Construction Co., 111 Ga.App. 369, 141 S.E.2d 839, 840 (1965); State Highway Dept. v. Wright Contracting Co., 107 Ga.App. 758, 131 S.E.2d 808, 812 (1963). Waive......
  • Excavators and Erectors, Inc. v. Bullard Engineers, Inc.
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • December 27, 1973
    ...court's conclusion, see Clark v. Belleau, 114 Ga. App. 587, 151 S.E.2d 894, 896 (1966); Mion Chemical Brick Corp. v. Daniel Construction Co., 111 Ga.App. 369, 141 S.E.2d 839, 840 (1965), and therefore the evidence of nonpayment to Bullard was properly Defendants' second contention is that t......
  • Continental Cas. Co. v. Wilson-Avery, Inc., WILSON-AVER
    • United States
    • Georgia Court of Appeals
    • May 3, 1967
    ...of faulty work either of the prime contractor or of another subcontractor. In this connection see Mion Chemical Brick Corp. v. Daniel Construction Co., 111 Ga.App. 369(1), 141 S.E.2d 839. The specifications, which were made a part of the subcontract, stipulated: 'The contractor shall examin......
  • Pro Metal Bldg. Systems, Inc. v. T.E. Driskell Grading Co., Inc., 67282
    • United States
    • Georgia Court of Appeals
    • March 6, 1984
    ...evidence that such additional work "was occasioned by faulty work" on the part of appellant. Mion Chemical Brick Corp. v. Daniel Constr. Co., 111 Ga.App. 369, 141 S.E.2d 839 (1965). Accordingly, it cannot be said that, as a matter of law, appellee was unauthorized to receive "extra" compens......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT